SAI GREENS

by REKHA SUBHASH JAGDALE · Bramhan Ali, Raigarh

Possession date of SAI GREENS: 31 December 2025, moved from 30 September 2019 (75 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52000003773. Status: Lapsed (registration period ended). 3 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (December 2025) has passed.

What do you want to know about SAI GREENS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SAI GREENS has moved

  1. 30 September 2019

    Completion date given when the project was registered

  2. 30 September 2020

    Extended at the builder's request (MahaRERA application EXT52000005630)

    Reason the builder gave MahaRERA:
    “The work is behind the schedule due to technical issues regarding the road connectivity to the project. The connecting road to the project plot was encroached by the attached neighboring plot owners by construction of unauthorized structure…” Read the full reason“The work is behind the schedule due to technical issues regarding the road connectivity to the project. The connecting road to the project plot was encroached by the attached neighboring plot owners by construction of unauthorized structures, illegal extention of their compound wall etc. We had to take this matter of encroachment to CIDCO/NAINA, & Palaspe Grampanchayat. After follow-up with CIDCO/NAINA & Palaspe Grampanchayat now said encroachment is removed and the road connectivity to the project is restored. After this removal of road encroachment now work at the site is in full progress…”
  3. 31 December 2022

    Extended at the builder's request (MahaRERA application EXT52000009672)

    Reason the builder gave MahaRERA:
    “The construction work is substantially suffered and delayed due to COVID 19 Lockdown, non-availability of Labor & Staff, Construction Material etc. Hence the extension is required to complete the balance work as per existing approved plan a…” Read the full reason“The construction work is substantially suffered and delayed due to COVID 19 Lockdown, non-availability of Labor & Staff, Construction Material etc. Hence the extension is required to complete the balance work as per existing approved plan and give possession to the existing flat buyers AND also to do the proposed additional construction as per proposed revised plan after getting the approval of the concerned authorities. Further the marketing/sale of Balance flat/inventory is also to be done which is becoming difficult day by day due to COVID 19 lockdown and slow down in the real estate mar…”
  4. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT52000017879)

    Reason the builder gave MahaRERA:
    “The work is nearing completion as per the approved Development permission Ref No. CIDCO/NAINA/PANVEL/Palaspe/BP-44/CC/2017/73 dated 03.02.2017. This permission was issued based on Interim Draft Development Plan and Draft Development Control…” Read the full reason“The work is nearing completion as per the approved Development permission Ref No. CIDCO/NAINA/PANVEL/Palaspe/BP-44/CC/2017/73 dated 03.02.2017. This permission was issued based on Interim Draft Development Plan and Draft Development Control & Promotion Rules & Regulations dated 07.11.2016. And as per that draft interim DP Rules we had been deprived off our legitimate eligible FSI of approx. 250 sq. mtr. as the area used for Staircase, Lobbies etc. was not excluded from the usable area and hence there was reduction in the usable area approved by NAINA at that time. But however subsequently t…”

Source: SAI GREENS’s extension records on MahaRERA (P52000003773), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SAI GREENS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 3 complaints, and how it ended
  • Construction pace against the December 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000003773
Status
Lapsed (registration period ended)
Builder
REKHA SUBHASH JAGDALE
Location
Bramhan Ali, Raigarh · 410221
Project type
Residential / Group Housing
Registered on
6 Aug 2017
Completion date at registration
September 2019
Latest completion date
December 2025
Delay so far
75 months
Homes
24
Sold or booked
79%
Towers
1
Complaints on MahaRERA
3
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of SAI GREENS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Laxmi Vishnu Vihar100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Laxmi Vishnu Vihar: covers 4 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAI GREENS every month.

SAI GREENS: buildings, flats and land, as filed on MahaRERA

  • Buildings: Laxmi Vishnu Vihar (5 floors, 24 units)
  • Land: 753 sq m (about 0.2 acres) · sanctioned built-up 714 sq m

The builder’s record and reviews

Rekha Subhash Jagdale has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 still being built, none past the promised date yet; 2 lapsed. 3 complaints on MahaRERA across 1 project.

Read Google reviews of SAI GREENS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SAI GREENS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SAI GREENS

What is the possession date of SAI GREENS?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SAI GREENS in Bramhan Ali, Raigarh is 31 December 2025 — 75 months later than 30 September 2019, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for SAI GREENS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SAI GREENS's builder has filed on MahaRERA, the official one, is 31 December 2025, already 75 months later than the 30 September 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SAI GREENS extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI GREENS's builder applied to MahaRERA to extend the completion date 3 times: to 30 September 2020, giving the reason "The work is behind the schedule due to technical issues regarding the road connectivity to the project. The connecting road to the project plot was encroached by the attached neighboring plot owners by construction of unauthorized structures, illegal extention of their compound wall etc. We had to take this matter of encroachment to CIDCO/NAINA, & Palaspe Grampanchayat. After follow-up with CIDCO/NAINA & Palaspe Grampanchayat now said encroachment is removed and the road connectivity to the project is restored. After this removal of road encroachment now work at the site is in full progress…"; to 31 December 2022, giving the reason "The construction work is substantially suffered and delayed due to COVID 19 Lockdown, non-availability of Labor & Staff, Construction Material etc. Hence the extension is required to complete the balance work as per existing approved plan and give possession to the existing flat buyers AND also to do the proposed additional construction as per proposed revised plan after getting the approval of the concerned authorities. Further the marketing/sale of Balance flat/inventory is also to be done which is becoming difficult day by day due to COVID 19 lockdown and slow down in the real estate mar…"; to 31 December 2025, giving the reason "The work is nearing completion as per the approved Development permission Ref No. CIDCO/NAINA/PANVEL/Palaspe/BP-44/CC/2017/73 dated 03.02.2017. This permission was issued based on Interim Draft Development Plan and Draft Development Control & Promotion Rules & Regulations dated 07.11.2016. And as per that draft interim DP Rules we had been deprived off our legitimate eligible FSI of approx. 250 sq. mtr. as the area used for Staircase, Lobbies etc. was not excluded from the usable area and hence there was reduction in the usable area approved by NAINA at that time. But however subsequently t…".

What is the RERA number of SAI GREENS?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SAI GREENS in Bramhan Ali, Raigarh is P52000003773.

Is SAI GREENS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI GREENS is registered as P52000003773 and its status is "Lapsed (registration period ended)".

What is the construction status of SAI GREENS?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI GREENS's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Laxmi Vishnu Vihar is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SAI GREENS have complaints on MahaRERA?

3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SAI GREENS safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI GREENS is registered on MahaRERA as P52000003773, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 75 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SAI GREENS's possession date changes?

The latest dates are on SAI GREENS's MahaRERA page (P52000003773). GharKundli's Kundli Watch sends a free WhatsApp update on SAI GREENS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SAI GREENS have?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI GREENS has one building filed: Laxmi Vishnu Vihar with 5 floors and 24 units.

How big is the land of SAI GREENS?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI GREENS stands on 753 sq m of land (about 0.2 acres), with 714 sq m of sanctioned built-up area.

What is the track record of SAI GREENS's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Rekha Subhash Jagdale has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 still being built, none past the promised date yet; 2 lapsed. 3 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SAI GREENS?

Google Maps has reviews of SAI GREENS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SAI GREENS?

SAI GREENS by REKHA SUBHASH JAGDALE is in Bramhan Ali, Raigarh (pincode 410221), Maharashtra, and is registered on MahaRERA as P52000003773, per GharKundli's check of MahaRERA records.

How many homes are in SAI GREENS?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI GREENS has 24 homes in 1 tower registered on MahaRERA, and 79% of them are sold or booked.

When was SAI GREENS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI GREENS was registered on MahaRERA on 6 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SAI GREENS?

No court cases are listed for SAI GREENS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of SAI GREENS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is REKHA SUBHASH JAGDALE, which has 2 other projects registered on MahaRERA.