MANE PALMS PHASE 1
by RECTANGLE PROPERTIES PVT LTD · Wadala West, Raigarh
Possession date of MANE PALMS PHASE 1: 14 December 2021, moved from 31 December 2019 (24 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P52000012232. Status: Lapsed (registration period ended). 3 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2021) has passed.
What do you want to know about MANE PALMS PHASE 1?
How the possession date of MANE PALMS PHASE 1 has moved
31 December 2019
Completion date given when the project was registered
14 December 2020
Extended at the builder's request (MahaRERA application EXT52000005264)
Reason the builder gave MahaRERA: “We kindly request you to extend the project completion date to 14/12/2020, the project work is delayed due to natural calamity of heavy and extended rainfall in the vicinity.”
14 December 2021
Revised completion date on MahaRERA
Source: MANE PALMS PHASE 1’s extension records on MahaRERA (P52000012232), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on MANE PALMS PHASE 1
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 complaints, and how it ended
- Construction pace against the December 2021 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000012232
- Status
- Lapsed (registration period ended)
- Builder
- RECTANGLE PROPERTIES PVT LTD
- Location
- Wadala West, Raigarh · 410201
- Project type
- Residential / Group Housing
- Registered on
- 1 Sep 2017
- Completion date at registration
- December 2019
- Latest completion date
- December 2021
- Delay so far
- 24 months
- Homes
- 24
- Towers
- 1
- Complaints on MahaRERA
- 3
- Court cases listed
- 0
- Appeals at the tribunal
- 2
- Title report on file
- Not found
Construction progress of MANE PALMS PHASE 1, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING A | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on MANE PALMS PHASE 1 every month.
MANE PALMS PHASE 1: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING A (4 floors)
- Land: 1,496 sq m (about 0.4 acres) · sanctioned built-up 1,173 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of MANE PALMS PHASE 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
MANE PALMS PHASE 1: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about MANE PALMS PHASE 1
What is the possession date of MANE PALMS PHASE 1?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for MANE PALMS PHASE 1 in Wadala West, Raigarh is 14 December 2021 — 24 months later than 31 December 2019, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for MANE PALMS PHASE 1?
Builders and listing sites often quote an earlier "target" date for handover. The completion date MANE PALMS PHASE 1's builder has filed on MahaRERA, the official one, is 14 December 2021, already 24 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of MANE PALMS PHASE 1 extended?
According to GharKundli's check of MahaRERA records (updated November 2026), MANE PALMS PHASE 1's builder applied to MahaRERA to extend the completion date once: to 14 December 2020, giving the reason "We kindly request you to extend the project completion date to 14/12/2020, the project work is delayed due to natural calamity of heavy and extended rainfall in the vicinity.".
What is the RERA number of MANE PALMS PHASE 1?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of MANE PALMS PHASE 1 in Wadala West, Raigarh is P52000012232.
Is MANE PALMS PHASE 1 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), MANE PALMS PHASE 1 is registered as P52000012232 and its status is "Lapsed (registration period ended)".
What is the construction status of MANE PALMS PHASE 1?
According to GharKundli's check of MahaRERA records (updated November 2026), MANE PALMS PHASE 1's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on BUILDING A is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does MANE PALMS PHASE 1 have complaints on MahaRERA?
3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is MANE PALMS PHASE 1 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), MANE PALMS PHASE 1 is registered on MahaRERA as P52000012232, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if MANE PALMS PHASE 1's possession date changes?
The latest dates are on MANE PALMS PHASE 1's MahaRERA page (P52000012232). GharKundli's Kundli Watch sends a free WhatsApp update on MANE PALMS PHASE 1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does MANE PALMS PHASE 1 have?
According to GharKundli's check of MahaRERA records (updated November 2026), MANE PALMS PHASE 1 has one building filed: BUILDING A with 4 floors.
How big is the land of MANE PALMS PHASE 1?
According to GharKundli's check of MahaRERA records (updated November 2026), MANE PALMS PHASE 1 stands on 1,496 sq m of land (about 0.4 acres), with 1,173 sq m of sanctioned built-up area.
Where can I read reviews of MANE PALMS PHASE 1?
Google Maps has reviews of MANE PALMS PHASE 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is MANE PALMS PHASE 1?
MANE PALMS PHASE 1 by RECTANGLE PROPERTIES PVT LTD is in Wadala West, Raigarh (pincode 410201), Maharashtra, and is registered on MahaRERA as P52000012232, per GharKundli's check of MahaRERA records.
How many homes are in MANE PALMS PHASE 1?
According to GharKundli's check of MahaRERA records (updated November 2026), MANE PALMS PHASE 1 has 24 homes in 1 tower registered on MahaRERA.
When was MANE PALMS PHASE 1 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), MANE PALMS PHASE 1 was registered on MahaRERA on 1 September 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on MANE PALMS PHASE 1?
No court cases are listed for MANE PALMS PHASE 1 on MahaRERA, and 2 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of MANE PALMS PHASE 1?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is RECTANGLE PROPERTIES PVT LTD.
Check it yourself on MahaRERA
- How to check the possession date of MANE PALMS PHASE 1
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Wadala West
All 311 projects in Karjat (410201) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.