MAPLE IVY

by PANKTI JIGNESH GORADIA · Ulwe, Raigarh

Possession date of MAPLE IVY: 31 December 2022, moved from 30 September 2020 (27 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52000015717. Status: Lapsed (registration period ended). 9 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2022) has passed.

What do you want to know about MAPLE IVY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of MAPLE IVY has moved

  1. 30 September 2020

    Completion date given when the project was registered

  2. 31 December 2022

    Extended at the builder's request (MahaRERA application EXT52000011048)

    Reason the builder gave MahaRERA:
    “Considerable time is lost in covid 19 pandemic and shortage of labor and multiple lockdowns added to the delay. work at project site is however going on smoothly and we are sure of completing the project well within this revised timelines.…” Read the full reason“Considerable time is lost in covid 19 pandemic and shortage of labor and multiple lockdowns added to the delay. work at project site is however going on smoothly and we are sure of completing the project well within this revised timelines. We have obtained necessary consent of more than 50% of allottees and have uploaded the same as below.”

Source: MAPLE IVY’s extension records on MahaRERA (P52000015717), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on MAPLE IVY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 9 complaints, and how it ended
  • Construction pace against the December 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000015717
Status
Lapsed (registration period ended)
Builder
PANKTI JIGNESH GORADIA
Location
Ulwe, Raigarh · 400707
Project type
Residential / Group Housing
Registered on
19 Mar 2018
Completion date at registration
September 2020
Latest completion date
December 2022
Delay so far
27 months
Homes
2
Sold or booked
100%
Towers
1
Complaints on MahaRERA
9
Court cases listed
0
Appeals at the tribunal
7
Title report on file
Not found

Construction progress of MAPLE IVY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
MAPLE IVY WING B100%75%55%30%

Commencement certificate (CC), as filed on MahaRERA

  • MAPLE IVY WING B: covers 17 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on MAPLE IVY every month.

MAPLE IVY: buildings, flats and land, as filed on MahaRERA

  • Buildings: MAPLE IVY WING B (17 floors, 3 units)
  • Car parking: 1 covered
  • Land: 3,297 sq m (about 0.8 acres) · sanctioned built-up 4,948 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of MAPLE IVY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

MAPLE IVY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about MAPLE IVY

What is the possession date of MAPLE IVY?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for MAPLE IVY in Ulwe, Raigarh is 31 December 2022 — 27 months later than 30 September 2020, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for MAPLE IVY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date MAPLE IVY's builder has filed on MahaRERA, the official one, is 31 December 2022, already 27 months later than the 30 September 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of MAPLE IVY extended?

According to GharKundli's check of MahaRERA records (updated November 2026), MAPLE IVY's builder applied to MahaRERA to extend the completion date once: to 31 December 2022, giving the reason "Considerable time is lost in covid 19 pandemic and shortage of labor and multiple lockdowns added to the delay. work at project site is however going on smoothly and we are sure of completing the project well within this revised timelines. We have obtained necessary consent of more than 50% of allottees and have uploaded the same as below.".

What is the RERA number of MAPLE IVY?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of MAPLE IVY in Ulwe, Raigarh is P52000015717.

Is MAPLE IVY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), MAPLE IVY is registered as P52000015717 and its status is "Lapsed (registration period ended)".

What is the construction status of MAPLE IVY?

According to GharKundli's check of MahaRERA records (updated November 2026), MAPLE IVY's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on MAPLE IVY WING B is 75% done and internal work 55%. GharKundli's full report compares construction progress with the deadline.

Does MAPLE IVY have complaints on MahaRERA?

9 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is MAPLE IVY safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), MAPLE IVY is registered on MahaRERA as P52000015717, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 27 months since registration and 9 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if MAPLE IVY's possession date changes?

The latest dates are on MAPLE IVY's MahaRERA page (P52000015717). GharKundli's Kundli Watch sends a free WhatsApp update on MAPLE IVY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does MAPLE IVY have?

According to GharKundli's check of MahaRERA records (updated November 2026), MAPLE IVY has one building filed: MAPLE IVY WING B with 17 floors and 3 units.

How much parking does MAPLE IVY have?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 1 covered car parking spaces for MAPLE IVY.

How big is the land of MAPLE IVY?

According to GharKundli's check of MahaRERA records (updated November 2026), MAPLE IVY stands on 3,297 sq m of land (about 0.8 acres), with 4,948 sq m of sanctioned built-up area.

Where can I read reviews of MAPLE IVY?

Google Maps has reviews of MAPLE IVY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 9 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is MAPLE IVY?

MAPLE IVY by PANKTI JIGNESH GORADIA is in Ulwe, Raigarh (pincode 400707), Maharashtra, and is registered on MahaRERA as P52000015717, per GharKundli's check of MahaRERA records.

How many homes are in MAPLE IVY?

According to GharKundli's check of MahaRERA records (updated November 2026), MAPLE IVY has 2 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.

When was MAPLE IVY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), MAPLE IVY was registered on MahaRERA on 19 March 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on MAPLE IVY?

No court cases are listed for MAPLE IVY on MahaRERA, and 7 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of MAPLE IVY?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is PANKTI JIGNESH GORADIA.

Other projects in Ulwe

All 58 projects in Jnpt (400707) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.