A K ORION
by A K DEVELOPERS · Kharghar, Raigarh
Possession: A K ORION is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000008553. Status: Completed. 8 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about A K ORION?
How the possession date of A K ORION has moved
31 March 2019
Completion date given when the project was registered
30 March 2020
Extended at the builder's request (MahaRERA application EXT52000001597)
Reason the builder gave MahaRERA:
“3. That at the time of applying for RERA registration we envisaged to complete the project on or before 31/03/2019. However the construction work is delayed due to shortage of funds & other reasons. Hence it will not be possible for us to c…” Read the full reason
“3. That at the time of applying for RERA registration we envisaged to complete the project on or before 31/03/2019. However the construction work is delayed due to shortage of funds & other reasons. Hence it will not be possible for us to complete the entire construction work of the project on or before the 31/03/2019. Now we plan to complete the pending construction work,finishing work and obtain Occupancy Certificate of the project on or before 31/03/2020.”31 December 2021
Extended at the builder's request (MahaRERA application EXT52000008464)
Reason the builder gave MahaRERA:
“at the time of applying for extension for completion of project under Maharera Act, 2016 we envisaged to complete the project on or before 31/03/2020. However the construction work was stopped from 20/03/2020 to 31/10/2020 due to COVID Pand…” Read the full reason
“at the time of applying for extension for completion of project under Maharera Act, 2016 we envisaged to complete the project on or before 31/03/2020. However the construction work was stopped from 20/03/2020 to 31/10/2020 due to COVID Pandemic. The construction work also delayed due to shortage of funds and non availability of workers. Hence we could not complete the project as planned. 4. We have already completed 95% of the project work. Now only part of finishing work and fire safety measures remains to be completed, we will complete the entire pending work on or before 31/12/2021.”31 December 2023
Extended at the builder's request (MahaRERA application EXT52000017797)
Reason the builder gave MahaRERA: “The project was completed before expiry date due to problem of CIDCO planning authority the OC was delay.”
Source: A K ORION’s extension records on MahaRERA (P52000008553), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on A K ORION
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 8 complaints, and how it ended
- Construction pace against the December 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000008553
- Status
- Completed
- Builder
- A K DEVELOPERS
- Location
- Kharghar, Raigarh · 410208
- Project type
- Others
- Registered on
- 19 Aug 2017
- Completion date at registration
- March 2019
- Latest completion date
- December 2023
- Delay so far
- 57 months
- Homes
- 108
- Towers
- 1
- Complaints on MahaRERA
- 8
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
Construction progress of A K ORION, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A K ORION | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on A K ORION every month.
A K ORION: buildings, flats and land, as filed on MahaRERA
- Buildings: A K ORION (24 floors)
- Land: 2,350 sq m (about 0.6 acres) · sanctioned built-up 3,523 sq m
The builder’s record and reviews
A K Developers has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 52 months); 1 still being built, none past the promised date yet. 8 complaints on MahaRERA across 1 project.
Read Google reviews of A K ORION →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
A K ORION: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about A K ORION
What is the possession date of A K ORION?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for A K ORION in Kharghar, Raigarh is 31 December 2023 — 57 months later than 31 March 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for A K ORION?
Builders and listing sites often quote an earlier "target" date for handover. The completion date A K ORION's builder has filed on MahaRERA, the official one, is 31 December 2023, already 57 months later than the 31 March 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of A K ORION extended?
According to GharKundli's check of MahaRERA records (updated November 2026), A K ORION's builder applied to MahaRERA to extend the completion date 3 times: to 30 March 2020, giving the reason "3. That at the time of applying for RERA registration we envisaged to complete the project on or before 31/03/2019. However the construction work is delayed due to shortage of funds & other reasons. Hence it will not be possible for us to complete the entire construction work of the project on or before the 31/03/2019. Now we plan to complete the pending construction work,finishing work and obtain Occupancy Certificate of the project on or before 31/03/2020."; to 31 December 2021, giving the reason "at the time of applying for extension for completion of project under Maharera Act, 2016 we envisaged to complete the project on or before 31/03/2020. However the construction work was stopped from 20/03/2020 to 31/10/2020 due to COVID Pandemic. The construction work also delayed due to shortage of funds and non availability of workers. Hence we could not complete the project as planned. 4. We have already completed 95% of the project work. Now only part of finishing work and fire safety measures remains to be completed, we will complete the entire pending work on or before 31/12/2021."; to 31 December 2023, giving the reason "The project was completed before expiry date due to problem of CIDCO planning authority the OC was delay.".
What is the RERA number of A K ORION?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of A K ORION in Kharghar, Raigarh is P52000008553.
Is A K ORION registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), A K ORION is registered as P52000008553 and its status is "Completed".
What is the construction status of A K ORION?
According to GharKundli's check of MahaRERA records (updated November 2026), A K ORION's status on MahaRERA is "Completed". As filed by the builder, slab work on A K ORION is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does A K ORION have complaints on MahaRERA?
8 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is A K ORION safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), A K ORION is registered on MahaRERA as P52000008553, its MahaRERA status is "Completed", its completion date has moved 57 months since registration and 8 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if A K ORION's possession date changes?
The latest dates are on A K ORION's MahaRERA page (P52000008553). GharKundli's Kundli Watch sends a free WhatsApp update on A K ORION every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does A K ORION have?
According to GharKundli's check of MahaRERA records (updated November 2026), A K ORION has one building filed: A K ORION with 24 floors.
How big is the land of A K ORION?
According to GharKundli's check of MahaRERA records (updated November 2026), A K ORION stands on 2,350 sq m of land (about 0.6 acres), with 3,523 sq m of sanctioned built-up area.
What is the track record of A K ORION's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), A K Developers has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 52 months); 1 still being built, none past the promised date yet. 8 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of A K ORION?
Google Maps has reviews of A K ORION written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 8 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is A K ORION?
A K ORION by A K DEVELOPERS is in Kharghar, Raigarh (pincode 410208), Maharashtra, and is registered on MahaRERA as P52000008553, per GharKundli's check of MahaRERA records.
How many homes are in A K ORION?
According to GharKundli's check of MahaRERA records (updated November 2026), A K ORION has 108 homes in 1 tower registered on MahaRERA.
When was A K ORION registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), A K ORION was registered on MahaRERA on 19 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on A K ORION?
No court cases are listed for A K ORION on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of A K ORION?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is A K DEVELOPERS, which has 4 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of A K ORION
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Kharghar
All 337 projects in Taloja (410208) →Other projects by A K DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.