by VIR Enterprises · panvel, Raigarh

Possession: Sai Aangan is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000004701. Status: Completed. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Sai Aangan?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Sai Aangan has moved

  1. 31 March 2020

    Completion date given when the project was registered

  2. 31 March 2021

    Extended at the builder's request (MahaRERA application EXT52000005986)

    Reason the builder gave MahaRERA:
    “Project was delay because of change in promoter from " Marvel Life Space LLP" to "Vir Enterprises" and we expect to received Occupancy Certificate within the period of one year. We request time limit of project to be extended up to March 20…” Read the full reason“Project was delay because of change in promoter from " Marvel Life Space LLP" to "Vir Enterprises" and we expect to received Occupancy Certificate within the period of one year. We request time limit of project to be extended up to March 2021.”
  3. 30 March 2023

    Extended at the builder's request (MahaRERA application EXT52000011609)

    Reason the builder gave MahaRERA:
    “We Vir enterprises would want an extension for our project Sai Aangan Situated at Survey Number 273, Dhansar , Navi Mumbai, as the CC issued to us by Panvel Municipal Corporation was on 7th April 2021 which was delayed by almost 15 months,…” Read the full reason“We Vir enterprises would want an extension for our project Sai Aangan Situated at Survey Number 273, Dhansar , Navi Mumbai, as the CC issued to us by Panvel Municipal Corporation was on 7th April 2021 which was delayed by almost 15 months, kindly extend the date to 30/3/2023. Thanking You.”
  4. 30 June 2023

    Extended at the builder's request (MahaRERA application EXT52000015104)

    Reason the builder gave MahaRERA:
    “Unfortunately, we have completed only 95% work of construction. So, we required time to complete remaining work of construction and also required time for receiving occupancy certificate. Therefore, we are now requesting an extension of the…” Read the full reason“Unfortunately, we have completed only 95% work of construction. So, we required time to complete remaining work of construction and also required time for receiving occupancy certificate. Therefore, we are now requesting an extension of the completion date. We understand the importance of this project, and we are doing our utmost to ensure that it is completed as soon as possible. We make request for Project delivery date to be extended till June 30, 2023.”

Source: Sai Aangan’s extension records on MahaRERA (P52000004701), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Sai Aangan

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the June 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000004701
Status
Completed
Builder
VIR Enterprises
Location
panvel, Raigarh · 410208
Project type
Residential / Group Housing
Registered on
9 Aug 2017
Completion date at registration
March 2020
Latest completion date
June 2023
Delay so far
39 months
Homes
110
Towers
2
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Sai Aangan, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
RIDDHI100%100%100%100%
SIDDHI100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sai Aangan every month.

Sai Aangan: buildings, flats and land, as filed on MahaRERA

  • Buildings: RIDDHI (8 floors) · SIDDHI (8 floors)
  • Land: 3,030 sq m (about 0.7 acres) · sanctioned built-up 2,194 sq m · recreational space 307 sq m

The builder’s record and reviews

Vir Enterprises has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 33 months). 1 complaint on MahaRERA across 1 project.

Read Google reviews of Sai Aangan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sai Aangan: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Sai Aangan

What is the possession date of Sai Aangan?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Sai Aangan in panvel, Raigarh is 30 June 2023 — 39 months later than 31 March 2020, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Sai Aangan?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sai Aangan's builder has filed on MahaRERA, the official one, is 30 June 2023, already 39 months later than the 31 March 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Sai Aangan extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Aangan's builder applied to MahaRERA to extend the completion date 3 times: to 31 March 2021, giving the reason "Project was delay because of change in promoter from " Marvel Life Space LLP" to "Vir Enterprises" and we expect to received Occupancy Certificate within the period of one year. We request time limit of project to be extended up to March 2021."; to 30 March 2023, giving the reason "We Vir enterprises would want an extension for our project Sai Aangan Situated at Survey Number 273, Dhansar , Navi Mumbai, as the CC issued to us by Panvel Municipal Corporation was on 7th April 2021 which was delayed by almost 15 months, kindly extend the date to 30/3/2023. Thanking You."; to 30 June 2023, giving the reason "Unfortunately, we have completed only 95% work of construction. So, we required time to complete remaining work of construction and also required time for receiving occupancy certificate. Therefore, we are now requesting an extension of the completion date. We understand the importance of this project, and we are doing our utmost to ensure that it is completed as soon as possible. We make request for Project delivery date to be extended till June 30, 2023.".

What is the RERA number of Sai Aangan?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Sai Aangan in panvel, Raigarh is P52000004701.

Is Sai Aangan registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Aangan is registered as P52000004701 and its status is "Completed".

What is the construction status of Sai Aangan?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Aangan's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does Sai Aangan have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Sai Aangan safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Aangan is registered on MahaRERA as P52000004701, its MahaRERA status is "Completed", its completion date has moved 39 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Sai Aangan's possession date changes?

The latest dates are on Sai Aangan's MahaRERA page (P52000004701). GharKundli's Kundli Watch sends a free WhatsApp update on Sai Aangan every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sai Aangan have?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Aangan has 2 buildings filed: RIDDHI with 8 floors; SIDDHI with 8 floors.

How big is the land of Sai Aangan?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Aangan stands on 3,030 sq m of land (about 0.7 acres), with 2,194 sq m of sanctioned built-up area and 307 sq m of recreational open space.

What is the track record of Sai Aangan's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Vir Enterprises has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 33 months). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Sai Aangan?

Google Maps has reviews of Sai Aangan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Sai Aangan?

Sai Aangan by VIR Enterprises is in panvel, Raigarh (pincode 410208), Maharashtra, and is registered on MahaRERA as P52000004701, per GharKundli's check of MahaRERA records.

How many homes are in Sai Aangan?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Aangan has 110 homes in 2 towers registered on MahaRERA.

When was Sai Aangan registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sai Aangan was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Sai Aangan?

No court cases are listed for Sai Aangan on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Sai Aangan?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VIR Enterprises, which has 1 other project registered on MahaRERA.