Skip to content
GharKundli

Sheltrex Smart Phone City Project 1 - Phase III

by Sheltrex Karjat Pvt. Ltd. · Akurle - Shirse Village, Raigarh

Possession date of Sheltrex Smart Phone City Project 1 - Phase III: 30 December 2021. This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52000004186. Status: Lapsed (registration period ended). 9 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2021) has passed.

What do you want to know about Sheltrex Smart Phone City Project 1 - Phase III?

Ask us on WhatsAppNo login needed. A real person replies.

GharKundli’s full report on Sheltrex Smart Phone City Project 1 - Phase III

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 9 complaints and 40 court cases, and how it ended
  • Construction pace against the December 2021 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52000004186
Status
Lapsed (registration period ended)
Builder
Sheltrex Karjat Pvt. Ltd.
Location
Akurle - Shirse Village, Raigarh · 410201
Project type
Residential / Group Housing
Registered on
8 Aug 2017
Completion date at registration
December 2021
Latest completion date
December 2021
Homes
3,679
Towers
49
Complaints on MahaRERA
9
Court cases listed
40
Title report on file
Not found
Builder's other MahaRERA projects
6

Construction progress of Sheltrex Smart Phone City Project 1 - Phase III, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
V1100%67%0%0%
V2100%67%0%0%
V3100%67%0%0%
V4100%67%0%0%
V5100%67%0%0%
V6100%67%0%0%
U1100%67%0%0%
U2100%67%0%0%
U3100%67%0%0%
U4100%67%0%0%
U5100%67%0%0%
U6100%67%0%0%
T1100%67%0%0%
T2100%67%0%0%
T3100%67%0%0%
T4100%67%0%0%
T6100%67%0%0%
S1100%67%0%0%
S2100%67%0%0%
S3100%67%0%0%
S5100%67%0%0%
PNS1 Proposed but not sanctioned0%0%0%0%
PNS-2 Proposed but not sanctioned0%0%0%0%
PNS-3 Proposed but not sanctioned0%0%0%0%
PNS-4 Proposed but not sanctioned0%0%0%0%
PNS-5 Proposed but not sanctioned0%0%0%0%
PNS-6 Proposed but not sanctioned0%0%0%0%
PNS-7 Proposed but not sanctioned0%0%0%0%
PNS-8 Proposed but not sanctioned0%0%0%0%
PNS-9 Proposed but not sanctioned0%0%0%0%

Showing 30 of 49 towers.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sheltrex Smart Phone City Project 1 - Phase III every month.

Sheltrex Smart Phone City Project 1 - Phase III: buildings, flats and land, as filed on MahaRERA

  • Buildings: V1 (3 floors) · V2 (3 floors) · V3 (3 floors) · V4 (3 floors) · V5 (3 floors) · V6 (3 floors) · U1 (3 floors) · U2 (3 floors) · and 22 more
  • Land: 22,311 sq m (about 5.5 acres) · sanctioned built-up 22,496 sq m · recreational space 49,129 sq m

The builder’s record and reviews

Sheltrex Karjat has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 7 lapsed. 68 complaints on MahaRERA across 6 projects.

Read Google reviews of Sheltrex Smart Phone City Project 1 - Phase III →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sheltrex Smart Phone City Project 1 - Phase III: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Sheltrex Smart Phone City Project 1 - Phase III

What is the possession date of Sheltrex Smart Phone City Project 1 - Phase III?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Sheltrex Smart Phone City Project 1 - Phase III in Akurle - Shirse Village, Raigarh is 30 December 2021. That date has already passed.

Is the builder's possession date different from the MahaRERA date for Sheltrex Smart Phone City Project 1 - Phase III?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sheltrex Smart Phone City Project 1 - Phase III's builder has filed on MahaRERA, the official one, is 30 December 2021, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Sheltrex Smart Phone City Project 1 - Phase III?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Sheltrex Smart Phone City Project 1 - Phase III in Akurle - Shirse Village, Raigarh is P52000004186.

Is Sheltrex Smart Phone City Project 1 - Phase III registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sheltrex Smart Phone City Project 1 - Phase III is registered as P52000004186 and its status is "Lapsed (registration period ended)". On MahaRERA's own list: On MahaRERA's insolvency (NCLT) list. MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.

What is the construction status of Sheltrex Smart Phone City Project 1 - Phase III?

According to GharKundli's check of MahaRERA records (updated November 2026), Sheltrex Smart Phone City Project 1 - Phase III's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 0% to 67% across 30 towers. GharKundli's full report compares construction progress with the deadline.

Does Sheltrex Smart Phone City Project 1 - Phase III have complaints on MahaRERA?

9 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Sheltrex Smart Phone City Project 1 - Phase III safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Sheltrex Smart Phone City Project 1 - Phase III is registered on MahaRERA as P52000004186, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder, 9 complaints are listed against it and it is on MahaRERA's list "On MahaRERA's insolvency (NCLT) list". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Sheltrex Smart Phone City Project 1 - Phase III have other wings or phases?

Yes. MahaRERA lists 4 other registrations of the same project, each with its own possession date: Sheltrex Smart Phone City Project 1 - Phase II (P52000012196, possession 30 Dec 2021); Sheltrex Smart Phone City Project 1 - Phase IV (P52000007063, possession 30 Dec 2021); Sheltrex Smart Phone City Project 1- Phase V (P52000010525, possession 30 Dec 2021); Sheltrex Smart Phone city Project 1- Phase VI (P52000008685, possession 30 Dec 2021). Check that your agreement names the registration of your own wing.

How can I get updates if Sheltrex Smart Phone City Project 1 - Phase III's possession date changes?

The latest dates are on Sheltrex Smart Phone City Project 1 - Phase III's MahaRERA page (P52000004186). GharKundli's Kundli Watch sends a free WhatsApp update on Sheltrex Smart Phone City Project 1 - Phase III every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sheltrex Smart Phone City Project 1 - Phase III have?

According to GharKundli's check of MahaRERA records (updated November 2026), Sheltrex Smart Phone City Project 1 - Phase III has 30 buildings filed: V1 with 3 floors; V2 with 3 floors; V3 with 3 floors; V4 with 3 floors; V5 with 3 floors; V6 with 3 floors; and 24 more.

How big is the land of Sheltrex Smart Phone City Project 1 - Phase III?

According to GharKundli's check of MahaRERA records (updated November 2026), Sheltrex Smart Phone City Project 1 - Phase III stands on 22,311 sq m of land (about 5.5 acres), with 22,496 sq m of sanctioned built-up area and 49,129 sq m of recreational open space.

What is the track record of Sheltrex Smart Phone City Project 1 - Phase III's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Sheltrex Karjat has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 7 lapsed. 68 complaints on MahaRERA across 6 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Sheltrex Smart Phone City Project 1 - Phase III?

Google Maps has reviews of Sheltrex Smart Phone City Project 1 - Phase III written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 9 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Sheltrex Smart Phone City Project 1 - Phase III?

Sheltrex Smart Phone City Project 1 - Phase III by Sheltrex Karjat Pvt. Ltd. is in Akurle - Shirse Village, Raigarh (pincode 410201), Maharashtra, and is registered on MahaRERA as P52000004186, per GharKundli's check of MahaRERA records.

How many homes are in Sheltrex Smart Phone City Project 1 - Phase III?

According to GharKundli's check of MahaRERA records (updated November 2026), Sheltrex Smart Phone City Project 1 - Phase III has 3,679 homes in 49 towers registered on MahaRERA.

When was Sheltrex Smart Phone City Project 1 - Phase III registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sheltrex Smart Phone City Project 1 - Phase III was registered on MahaRERA on 8 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Sheltrex Smart Phone City Project 1 - Phase III?

40 court cases are listed for Sheltrex Smart Phone City Project 1 - Phase III on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Sheltrex Smart Phone City Project 1 - Phase III?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Sheltrex Karjat Pvt. Ltd., which has 6 other projects registered on MahaRERA.

Other projects in Akurle - Shirse Village

All 311 projects in Karjat (410201) →

Other projects by Sheltrex Karjat Pvt. Ltd.

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.