Possession: THE AMBIENCE GARDEN is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000012153. Status: Completed. 3 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about THE AMBIENCE GARDEN?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of THE AMBIENCE GARDEN has moved

  1. 30 June 2018

    Completion date given when the project was registered

  2. 30 April 2020

    Extended at the builder's request (MahaRERA application EXT52000000570)

    Reason the builder gave MahaRERA:
    “Despite several representations given to CIDCO time and again, it has failed to provide the basic infrastructure and amenities in the area which it is duty bound to do which is resulting in delay in completion of the Project.Because of lack…” Read the full reason“Despite several representations given to CIDCO time and again, it has failed to provide the basic infrastructure and amenities in the area which it is duty bound to do which is resulting in delay in completion of the Project.Because of lack of basic infrastructure and amenities it is becoming very difficult to complete the project on time and is further resulting in delay in handing over of possession to the buyers. We have already written to CIDCO about the problem several times but have not received any formal communication from them. Attaching a copy of various letters submitted to CIDCO…”
  3. 30 April 2020

    Extended at the builder's request (MahaRERA application EXT52000002022)

    Reason the builder gave MahaRERA:
    “Time and again we have written letters to CIDCO and have requested them to provide the basic infrastructure and facilities in the area required to complete the project on time but CIDCO has failed to provide the same till date. Due to lack…” Read the full reason“Time and again we have written letters to CIDCO and have requested them to provide the basic infrastructure and facilities in the area required to complete the project on time but CIDCO has failed to provide the same till date. Due to lack of basic infrastructure and facilities it took us more time to complete the construction of the building and with great difficulty we completed the construction and applied for Occupancy Certificate on 14/03/2019.However,We have not received the Occupancy Certificate till date and hence it is not possible to provide possession to the Buyers before 30/06/2019”
  4. 30 June 2026

    Extended at the builder's request (MahaRERA application EXT52000023035)

    Reason the builder gave MahaRERA: “Due to shortage of material and labor not able to complete project please grant us extension till 30/06/2026”

Source: THE AMBIENCE GARDEN’s extension records on MahaRERA (P52000012153), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on THE AMBIENCE GARDEN

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 3 complaints, and how it ended
  • Construction pace against the June 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000012153
Status
Completed
Builder
MUKUND ARSS DEVELOPERS
Location
Vashi, Raigarh · 400702
Project type
Others
Registered on
1 Sep 2017
Completion date at registration
June 2018
Latest completion date
June 2026
Delay so far
96 months
Homes
126
Sold or booked
69%
Towers
1
Complaints on MahaRERA
3
Court cases listed
0
Appeals at the tribunal
1
Title report on file
Not found

Construction progress of THE AMBIENCE GARDEN, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
THE AMBIENCE GARDEN100%100%98%100%

Commencement certificate (CC), as filed on MahaRERA

  • THE AMBIENCE GARDEN: covers G+7Floor

Want to know when this changes? Kundli Watch sends a free WhatsApp update on THE AMBIENCE GARDEN every month.

THE AMBIENCE GARDEN: buildings, flats and land, as filed on MahaRERA

  • Buildings: THE AMBIENCE GARDEN (9 floors, 140 units)
  • Land: 3,249 sq m (about 0.8 acres) · sanctioned built-up 4,872 sq m
  • Boundaries filed include: 09 MTS WIDE ROAD, 24 MTS WIDE ROAD

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of THE AMBIENCE GARDEN →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

THE AMBIENCE GARDEN: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about THE AMBIENCE GARDEN

What is the possession date of THE AMBIENCE GARDEN?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for THE AMBIENCE GARDEN in Vashi, Raigarh is 30 June 2026 — 96 months later than 30 June 2018, the date given at registration.

Is the builder's possession date different from the MahaRERA date for THE AMBIENCE GARDEN?

Builders and listing sites often quote an earlier "target" date for handover. The completion date THE AMBIENCE GARDEN's builder has filed on MahaRERA, the official one, is 30 June 2026, already 96 months later than the 30 June 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of THE AMBIENCE GARDEN extended?

According to GharKundli's check of MahaRERA records (updated October 2026), THE AMBIENCE GARDEN's builder applied to MahaRERA to extend the completion date 3 times: to 30 April 2020, giving the reason "Despite several representations given to CIDCO time and again, it has failed to provide the basic infrastructure and amenities in the area which it is duty bound to do which is resulting in delay in completion of the Project.Because of lack of basic infrastructure and amenities it is becoming very difficult to complete the project on time and is further resulting in delay in handing over of possession to the buyers. We have already written to CIDCO about the problem several times but have not received any formal communication from them. Attaching a copy of various letters submitted to CIDCO…"; to 30 April 2020, giving the reason "Time and again we have written letters to CIDCO and have requested them to provide the basic infrastructure and facilities in the area required to complete the project on time but CIDCO has failed to provide the same till date. Due to lack of basic infrastructure and facilities it took us more time to complete the construction of the building and with great difficulty we completed the construction and applied for Occupancy Certificate on 14/03/2019.However,We have not received the Occupancy Certificate till date and hence it is not possible to provide possession to the Buyers before 30/06/2019"; to 30 June 2026, giving the reason "Due to shortage of material and labor not able to complete project please grant us extension till 30/06/2026".

What is the RERA number of THE AMBIENCE GARDEN?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of THE AMBIENCE GARDEN in Vashi, Raigarh is P52000012153.

Is THE AMBIENCE GARDEN registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), THE AMBIENCE GARDEN is registered as P52000012153 and its status is "Completed".

What is the construction status of THE AMBIENCE GARDEN?

According to GharKundli's check of MahaRERA records (updated October 2026), THE AMBIENCE GARDEN's status on MahaRERA is "Completed". As filed by the builder, slab work on THE AMBIENCE GARDEN is 100% done and internal work 98%. GharKundli's full report compares construction progress with the deadline.

Does THE AMBIENCE GARDEN have complaints on MahaRERA?

3 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is THE AMBIENCE GARDEN safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), THE AMBIENCE GARDEN is registered on MahaRERA as P52000012153, its MahaRERA status is "Completed", its completion date has moved 96 months since registration and 3 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if THE AMBIENCE GARDEN's possession date changes?

The latest dates are on THE AMBIENCE GARDEN's MahaRERA page (P52000012153). GharKundli's Kundli Watch sends a free WhatsApp update on THE AMBIENCE GARDEN every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does THE AMBIENCE GARDEN have?

According to GharKundli's check of MahaRERA records (updated October 2026), THE AMBIENCE GARDEN has one building filed: THE AMBIENCE GARDEN with 9 floors and 140 units.

How big is the land of THE AMBIENCE GARDEN?

According to GharKundli's check of MahaRERA records (updated October 2026), THE AMBIENCE GARDEN stands on 3,249 sq m of land (about 0.8 acres), with 4,872 sq m of sanctioned built-up area.

Where can I read reviews of THE AMBIENCE GARDEN?

Google Maps has reviews of THE AMBIENCE GARDEN written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 3 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is THE AMBIENCE GARDEN?

THE AMBIENCE GARDEN by MUKUND ARSS DEVELOPERS is in Vashi, Raigarh (pincode 400702), Maharashtra, and is registered on MahaRERA as P52000012153, per GharKundli's check of MahaRERA records. Its boundaries filed there include 09 MTS WIDE ROAD, 24 MTS WIDE ROAD.

How many homes are in THE AMBIENCE GARDEN?

According to GharKundli's check of MahaRERA records (updated October 2026), THE AMBIENCE GARDEN has 126 homes in 1 tower registered on MahaRERA, and 69% of them are sold or booked.

When was THE AMBIENCE GARDEN registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), THE AMBIENCE GARDEN was registered on MahaRERA on 1 September 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on THE AMBIENCE GARDEN?

No court cases are listed for THE AMBIENCE GARDEN on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of THE AMBIENCE GARDEN?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MUKUND ARSS DEVELOPERS.