Skip to content
GharKundli

SHIVKRISHNA ARCADE

by Shiv Krishana Developers (Globe) · Ualawe, Raigarh

Possession date of SHIVKRISHNA ARCADE: 28 November 2022, moved from 28 May 2021 (18 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52000011590. Status: Lapsed (registration period ended). 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (November 2022) has passed.

What do you want to know about SHIVKRISHNA ARCADE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SHIVKRISHNA ARCADE has moved

  1. 28 May 2021

    Completion date given when the project was registered

  2. 28 May 2022

    Extended at the builder's request (MahaRERA application EXT52000009295)

    Reason the builder gave MahaRERA:
    “The construction work in the project is almost completed. The delay was majorly due to the pandemic situation. We will be submitting the application for occupancy certification in short span. Thus, we hereby request you to kindly grant us t…” Read the full reason“The construction work in the project is almost completed. The delay was majorly due to the pandemic situation. We will be submitting the application for occupancy certification in short span. Thus, we hereby request you to kindly grant us the extension for one year and also generate the new certificate with the revised date.”
  3. 28 November 2022

    Revised completion date on MahaRERA

Source: SHIVKRISHNA ARCADE’s extension records on MahaRERA (P52000011590), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SHIVKRISHNA ARCADE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints, and how it ended
  • Construction pace against the November 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000011590
Status
Lapsed (registration period ended)
Builder
Shiv Krishana Developers
Location
Ualawe, Raigarh · 410206
Project type
Residential / Group Housing
Registered on
31 Aug 2017
Completion date at registration
May 2021
Latest completion date
November 2022
Delay so far
18 months
Homes
23
Towers
1
Complaints on MahaRERA
2
Court cases listed
0
Title report on file
Not found

Construction progress of SHIVKRISHNA ARCADE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Shivkrishna Arcade100%100%40%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHIVKRISHNA ARCADE every month.

SHIVKRISHNA ARCADE: buildings, flats and land, as filed on MahaRERA

  • Buildings: Shivkrishna Arcade (6 floors)
  • Land: 349 sq m (about 0.1 acres) · sanctioned built-up 522 sq m · recreational space 349 sq m

The builder’s record and reviews

Globe Infra Developers 1 (a group of 5 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 2 still being built, none past the promised date yet; 5 lapsed. 2 complaints on MahaRERA across 1 project.

Read Google reviews of SHIVKRISHNA ARCADE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SHIVKRISHNA ARCADE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SHIVKRISHNA ARCADE

What is the possession date of SHIVKRISHNA ARCADE?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SHIVKRISHNA ARCADE in Ualawe, Raigarh is 28 November 2022 — 18 months later than 28 May 2021, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for SHIVKRISHNA ARCADE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SHIVKRISHNA ARCADE's builder has filed on MahaRERA, the official one, is 28 November 2022, already 18 months later than the 28 May 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SHIVKRISHNA ARCADE extended?

According to GharKundli's check of MahaRERA records (updated November 2026), SHIVKRISHNA ARCADE's builder applied to MahaRERA to extend the completion date once: to 28 May 2022, giving the reason "The construction work in the project is almost completed. The delay was majorly due to the pandemic situation. We will be submitting the application for occupancy certification in short span. Thus, we hereby request you to kindly grant us the extension for one year and also generate the new certificate with the revised date.".

What is the RERA number of SHIVKRISHNA ARCADE?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SHIVKRISHNA ARCADE in Ualawe, Raigarh is P52000011590.

Is SHIVKRISHNA ARCADE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHIVKRISHNA ARCADE is registered as P52000011590 and its status is "Lapsed (registration period ended)".

What is the construction status of SHIVKRISHNA ARCADE?

According to GharKundli's check of MahaRERA records (updated November 2026), SHIVKRISHNA ARCADE's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Shivkrishna Arcade is 100% done and internal work 40%. GharKundli's full report compares construction progress with the deadline.

Does SHIVKRISHNA ARCADE have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SHIVKRISHNA ARCADE safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), SHIVKRISHNA ARCADE is registered on MahaRERA as P52000011590, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 18 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SHIVKRISHNA ARCADE's possession date changes?

The latest dates are on SHIVKRISHNA ARCADE's MahaRERA page (P52000011590). GharKundli's Kundli Watch sends a free WhatsApp update on SHIVKRISHNA ARCADE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SHIVKRISHNA ARCADE have?

According to GharKundli's check of MahaRERA records (updated November 2026), SHIVKRISHNA ARCADE has one building filed: Shivkrishna Arcade with 6 floors.

How big is the land of SHIVKRISHNA ARCADE?

According to GharKundli's check of MahaRERA records (updated November 2026), SHIVKRISHNA ARCADE stands on 349 sq m of land (about 0.1 acres), with 522 sq m of sanctioned built-up area and 349 sq m of recreational open space.

What is the track record of SHIVKRISHNA ARCADE's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Globe Infra Developers 1 (a group of 5 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 2 still being built, none past the promised date yet; 5 lapsed. 2 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SHIVKRISHNA ARCADE?

Google Maps has reviews of SHIVKRISHNA ARCADE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SHIVKRISHNA ARCADE?

SHIVKRISHNA ARCADE by Shiv Krishana Developers (Globe) is in Ualawe, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000011590, per GharKundli's check of MahaRERA records.

How many homes are in SHIVKRISHNA ARCADE?

According to GharKundli's check of MahaRERA records (updated November 2026), SHIVKRISHNA ARCADE has 23 homes in 1 tower registered on MahaRERA.

When was SHIVKRISHNA ARCADE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SHIVKRISHNA ARCADE was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SHIVKRISHNA ARCADE?

No court cases are listed for SHIVKRISHNA ARCADE on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SHIVKRISHNA ARCADE?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Shiv Krishana Developers, the company Globe files this project under.

Other projects in Panvel

All 2,664 projects in Panvel (410206) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.