VAISHNOVI HEIGHTS
by VAISHNOVI CONSTRUCTION COMPANY · Ulwe, Raigarh
Possession: VAISHNOVI HEIGHTS is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000010966. Status: Completed.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about VAISHNOVI HEIGHTS?
How the possession date of VAISHNOVI HEIGHTS has moved
30 June 2018
Completion date given when the project was registered
30 June 2019
Extended at the builder's request (MahaRERA application EXT52000001409)
Reason the builder gave MahaRERA: “Since we could not complete the project by the said completion date. We hereby request you to extend the completion date to 30/06/2019.”
5 March 2020
Extended at the builder's request (MahaRERA application EA06022619751)
Reason the builder gave MahaRERA:
“The reason for seeking an extension of the project registration are as follows: 1. We have received the Occupancy Certificate (OC) for the project on 05/03/2020. We had tried to upload it but due to technical issues the same was not possibl…” Read the full reason
“The reason for seeking an extension of the project registration are as follows: 1. We have received the Occupancy Certificate (OC) for the project on 05/03/2020. We had tried to upload it but due to technical issues the same was not possible. 2. We are now in the final stage of completing the remaining compliance formalities required under MahaRERA after receiving the OC. 3. To ensure that all post-OC compliance obligations are fulfilled properly and without any errors, we request an extension until 05/03/2020. This will help us complete the process smoothly and in full compliance with the…”
Source: VAISHNOVI HEIGHTS’s extension records on MahaRERA (P52000010966), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on VAISHNOVI HEIGHTS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the March 2020 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000010966
- Status
- Completed
- Builder
- VAISHNOVI CONSTRUCTION COMPANY
- Location
- Ulwe, Raigarh · 400707
- Project type
- Others
- Registered on
- 31 Aug 2017
- Completion date at registration
- June 2018
- Latest completion date
- March 2020
- Delay so far
- 21 months
- Homes
- 96
- Sold or booked
- 100%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of VAISHNOVI HEIGHTS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A-WING | 100% | 100% | 100% | 100% |
| B-WING | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- A-WING: covers 16 floors
- B-WING: covers 16 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on VAISHNOVI HEIGHTS every month.
VAISHNOVI HEIGHTS: buildings, flats and land, as filed on MahaRERA
- Buildings: A-WING (16 floors, 57 units) · B-WING (16 floors, 57 units)
- Land: 2,549 sq m (about 0.6 acres) · sanctioned built-up 3,823 sq m · recreational space 242 sq m
The builder’s record and reviews
SAI Krupa Builders & Developers (a group of 4 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 20 months); 3 still being built, 3 past the promised date (typically 94 months late). No complaints on MahaRERA.
Read Google reviews of VAISHNOVI HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
VAISHNOVI HEIGHTS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about VAISHNOVI HEIGHTS
What is the possession date of VAISHNOVI HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VAISHNOVI HEIGHTS in Ulwe, Raigarh is 5 March 2020 — 21 months later than 30 June 2018, the date given at registration.
Is the builder's possession date different from the MahaRERA date for VAISHNOVI HEIGHTS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date VAISHNOVI HEIGHTS's builder has filed on MahaRERA, the official one, is 5 March 2020, already 21 months later than the 30 June 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of VAISHNOVI HEIGHTS extended?
According to GharKundli's check of MahaRERA records (updated October 2026), VAISHNOVI HEIGHTS's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2019, giving the reason "Since we could not complete the project by the said completion date. We hereby request you to extend the completion date to 30/06/2019."; to 5 March 2020, giving the reason "The reason for seeking an extension of the project registration are as follows: 1. We have received the Occupancy Certificate (OC) for the project on 05/03/2020. We had tried to upload it but due to technical issues the same was not possible. 2. We are now in the final stage of completing the remaining compliance formalities required under MahaRERA after receiving the OC. 3. To ensure that all post-OC compliance obligations are fulfilled properly and without any errors, we request an extension until 05/03/2020. This will help us complete the process smoothly and in full compliance with the…".
What is the RERA number of VAISHNOVI HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of VAISHNOVI HEIGHTS in Ulwe, Raigarh is P52000010966.
Is VAISHNOVI HEIGHTS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), VAISHNOVI HEIGHTS is registered as P52000010966 and its status is "Completed".
What is the construction status of VAISHNOVI HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), VAISHNOVI HEIGHTS's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does VAISHNOVI HEIGHTS have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is VAISHNOVI HEIGHTS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), VAISHNOVI HEIGHTS is registered on MahaRERA as P52000010966, its MahaRERA status is "Completed", its completion date has moved 21 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if VAISHNOVI HEIGHTS's possession date changes?
The latest dates are on VAISHNOVI HEIGHTS's MahaRERA page (P52000010966). GharKundli's Kundli Watch sends a free WhatsApp update on VAISHNOVI HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does VAISHNOVI HEIGHTS have?
According to GharKundli's check of MahaRERA records (updated October 2026), VAISHNOVI HEIGHTS has 2 buildings filed: A-WING with 16 floors and 57 units; B-WING with 16 floors and 57 units.
How big is the land of VAISHNOVI HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), VAISHNOVI HEIGHTS stands on 2,549 sq m of land (about 0.6 acres), with 3,823 sq m of sanctioned built-up area and 242 sq m of recreational open space.
What is the track record of VAISHNOVI HEIGHTS's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), SAI Krupa Builders & Developers (a group of 4 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 20 months); 3 still being built, 3 past the promised date (typically 94 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of VAISHNOVI HEIGHTS?
Google Maps has reviews of VAISHNOVI HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is VAISHNOVI HEIGHTS?
VAISHNOVI HEIGHTS by VAISHNOVI CONSTRUCTION COMPANY is in Ulwe, Raigarh (pincode 400707), Maharashtra, and is registered on MahaRERA as P52000010966, per GharKundli's check of MahaRERA records.
How many homes are in VAISHNOVI HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), VAISHNOVI HEIGHTS has 96 homes in 2 towers registered on MahaRERA, and 100% of them are sold or booked.
When was VAISHNOVI HEIGHTS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), VAISHNOVI HEIGHTS was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on VAISHNOVI HEIGHTS?
No court cases are listed for VAISHNOVI HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of VAISHNOVI HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VAISHNOVI CONSTRUCTION COMPANY.
Check it yourself on MahaRERA
- How to check the possession date of VAISHNOVI HEIGHTS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Ulwe
- BHAGWATI BELLEZA
- KRISHNA AVENUE
- Reddy's Gurukrupa Heights
- SARANG TOPAZ
- JAYDEV HEIGHTS
- SHREE SIDDHI RESIDENCY
- ABHINANDAN CORNER
- SADANALINI RESIDENCY
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.