AAROHI COMPLEX

by M/S TODAY SHYAM DEVELOPERS · Navi Mumbai, RaigarhAlso near Kalamboli, Taloja A.V

Possession: AAROHI COMPLEX is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000015331. Status: Completed. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about AAROHI COMPLEX?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of AAROHI COMPLEX has moved

  1. 28 November 2022

    Completion date given when the project was registered

  2. 31 December 2023

    Extended at the builder's request (MahaRERA application EXT52000012948)

    Reason the builder gave MahaRERA: “The slabs of super structure work is 100% completed only the internal works like plumbing fittings , installation of lifts and finishing works are in progress.”
  3. 31 December 2024

    Extended at the builder's request (MahaRERA application EXT52000018915)

    Reason the builder gave MahaRERA: “The promoter has completed 100% work and only finishing work like plumbing, plaster, electrical fitting, etc.”
  4. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT52000027351)

    Reason the builder gave MahaRERA: “The project has been delayed due to the pending completion of the plumbing fixtures.”
  5. 10 July 2025

    Extended at the builder's request (MahaRERA application EA25092517938)

    Reason the builder gave MahaRERA:
    “We had submitted the application for Occupancy Certificate within the stipulated time; however, the OC was actually issued on 10.07.2025, which falls after the RERA completion date of 30.06.2025. Accordingly, we request a 10 Days extension…” Read the full reason“We had submitted the application for Occupancy Certificate within the stipulated time; however, the OC was actually issued on 10.07.2025, which falls after the RERA completion date of 30.06.2025. Accordingly, we request a 10 Days extension to regularize the completion timeline.”

Source: AAROHI COMPLEX’s extension records on MahaRERA (P52000015331), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on AAROHI COMPLEX

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the July 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000015331
Status
Completed
Builder
M/S TODAY SHYAM DEVELOPERS
Location
Navi Mumbai, Raigarh · 410208
Project type
Others
Registered on
15 Feb 2018
Completion date at registration
November 2022
Latest completion date
July 2025
Delay so far
32 months
Homes
133
Sold or booked
33%
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of AAROHI COMPLEX, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
AAROHI COMPLEX100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • AAROHI COMPLEX: covers 9 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on AAROHI COMPLEX every month.

AAROHI COMPLEX: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of AAROHI COMPLEX →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

AAROHI COMPLEX: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about AAROHI COMPLEX

What is the possession date of AAROHI COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AAROHI COMPLEX in Navi Mumbai, Raigarh is 10 July 2025 — 32 months later than 28 November 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for AAROHI COMPLEX?

Builders and listing sites often quote an earlier "target" date for handover. The completion date AAROHI COMPLEX's builder has filed on MahaRERA, the official one, is 10 July 2025, already 32 months later than the 28 November 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of AAROHI COMPLEX extended?

According to GharKundli's check of MahaRERA records (updated October 2026), AAROHI COMPLEX's builder applied to MahaRERA to extend the completion date 4 times: to 31 December 2023, giving the reason "The slabs of super structure work is 100% completed only the internal works like plumbing fittings , installation of lifts and finishing works are in progress."; to 31 December 2024, giving the reason "The promoter has completed 100% work and only finishing work like plumbing, plaster, electrical fitting, etc."; to 30 June 2025, giving the reason "The project has been delayed due to the pending completion of the plumbing fixtures."; to 10 July 2025, giving the reason "We had submitted the application for Occupancy Certificate within the stipulated time; however, the OC was actually issued on 10.07.2025, which falls after the RERA completion date of 30.06.2025. Accordingly, we request a 10 Days extension to regularize the completion timeline.".

What is the RERA number of AAROHI COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of AAROHI COMPLEX in Navi Mumbai, Raigarh is P52000015331.

Is AAROHI COMPLEX registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AAROHI COMPLEX is registered as P52000015331 and its status is "Completed".

What is the construction status of AAROHI COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), AAROHI COMPLEX's status on MahaRERA is "Completed". As filed by the builder, slab work on AAROHI COMPLEX is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does AAROHI COMPLEX have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is AAROHI COMPLEX safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), AAROHI COMPLEX is registered on MahaRERA as P52000015331, its MahaRERA status is "Completed", its completion date has moved 32 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if AAROHI COMPLEX's possession date changes?

The latest dates are on AAROHI COMPLEX's MahaRERA page (P52000015331). GharKundli's Kundli Watch sends a free WhatsApp update on AAROHI COMPLEX every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does AAROHI COMPLEX have?

According to GharKundli's check of MahaRERA records (updated October 2026), AAROHI COMPLEX has one building filed: AAROHI COMPLEX with 9 floors and 147 units.

How much parking does AAROHI COMPLEX have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 36 covered and 2 open car parking spaces for AAROHI COMPLEX.

How big is the land of AAROHI COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), AAROHI COMPLEX stands on 2,448 sq m of land (about 0.6 acres), with 3,666 sq m of sanctioned built-up area.

Where can I read reviews of AAROHI COMPLEX?

Google Maps has reviews of AAROHI COMPLEX written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is AAROHI COMPLEX?

AAROHI COMPLEX by M/S TODAY SHYAM DEVELOPERS is in Navi Mumbai, Raigarh (pincode 410208), near Kalamboli, Taloja A.V, Maharashtra, and is registered on MahaRERA as P52000015331, per GharKundli's check of MahaRERA records.

How many homes are in AAROHI COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), AAROHI COMPLEX has 133 homes in 1 tower registered on MahaRERA, and 33% of them are sold or booked.

When was AAROHI COMPLEX registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), AAROHI COMPLEX was registered on MahaRERA on 15 February 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on AAROHI COMPLEX?

No court cases are listed for AAROHI COMPLEX on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of AAROHI COMPLEX?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is M/S TODAY SHYAM DEVELOPERS.

Other projects in pincode 410208

All 337 projects in Taloja (410208) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.