Possession: CITY ICON is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000016409. Status: Completed. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about CITY ICON?
How the possession date of CITY ICON has moved
30 December 2022
Completion date given when the project was registered
30 December 2023
Extended at the builder's request (MahaRERA application EXT52000013205)
Reason the builder gave MahaRERA:
“The Project has been already completed virtually in Apr-2022 and accordingly application for OC is already filed with CIDCO Ltd on 12-04-2022, but OC is delayed on account of various reasons beyond our control and more particularly due to p…” Read the full reason
“The Project has been already completed virtually in Apr-2022 and accordingly application for OC is already filed with CIDCO Ltd on 12-04-2022, but OC is delayed on account of various reasons beyond our control and more particularly due to pending decision of Hon High Court in PIL 154/2016 filed against CIDCO Ltd., wherein petitioner has challenged the practice followed by CIDCO to grant free FSI such as CB, FB, PT etc. CIDCO Ltd is refusing OC on the basis of pending PIL 154 of 2016 in the Hon High Court, since the decision in the matter is awaited therefore proposal of OC cannot be conside…”
Source: CITY ICON’s extension records on MahaRERA (P52000016409), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on CITY ICON
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the December 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000016409
- Status
- Completed
- Builder
- CITY BUILDCON
- Location
- Taloja Navi Mumbai, Raigarh · 410208
- Project type
- Residential / Group Housing
- Registered on
- 10 May 2018
- Completion date at registration
- December 2022
- Latest completion date
- December 2023
- Delay so far
- 12 months
- Homes
- 45
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of CITY ICON, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| CITY ICON | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on CITY ICON every month.
CITY ICON: buildings, flats and land, as filed on MahaRERA
- Buildings: CITY ICON (17 floors)
- Land: 1,050 sq m (about 0.3 acres) · sanctioned built-up 1,573 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
City Buildcon (a group of 6 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 4 finished, all within the promised date; 1 still being built, none past the promised date yet; 1 lapsed. 1 complaint on MahaRERA across 1 project.
Read Google reviews of CITY ICON →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
CITY ICON: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about CITY ICON
What is the possession date of CITY ICON?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for CITY ICON in Taloja Navi Mumbai, Raigarh is 30 December 2023 — 12 months later than 30 December 2022, the date given at registration.
Is the builder's possession date different from the MahaRERA date for CITY ICON?
Builders and listing sites often quote an earlier "target" date for handover. The completion date CITY ICON's builder has filed on MahaRERA, the official one, is 30 December 2023, already 12 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of CITY ICON extended?
According to GharKundli's check of MahaRERA records (updated November 2026), CITY ICON's builder applied to MahaRERA to extend the completion date once: to 30 December 2023, giving the reason "The Project has been already completed virtually in Apr-2022 and accordingly application for OC is already filed with CIDCO Ltd on 12-04-2022, but OC is delayed on account of various reasons beyond our control and more particularly due to pending decision of Hon High Court in PIL 154/2016 filed against CIDCO Ltd., wherein petitioner has challenged the practice followed by CIDCO to grant free FSI such as CB, FB, PT etc. CIDCO Ltd is refusing OC on the basis of pending PIL 154 of 2016 in the Hon High Court, since the decision in the matter is awaited therefore proposal of OC cannot be conside…".
What is the RERA number of CITY ICON?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of CITY ICON in Taloja Navi Mumbai, Raigarh is P52000016409.
Is CITY ICON registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), CITY ICON is registered as P52000016409 and its status is "Completed".
What is the construction status of CITY ICON?
According to GharKundli's check of MahaRERA records (updated November 2026), CITY ICON's status on MahaRERA is "Completed". As filed by the builder, slab work on CITY ICON is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does CITY ICON have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is CITY ICON safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), CITY ICON is registered on MahaRERA as P52000016409, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if CITY ICON's possession date changes?
The latest dates are on CITY ICON's MahaRERA page (P52000016409). GharKundli's Kundli Watch sends a free WhatsApp update on CITY ICON every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does CITY ICON have?
According to GharKundli's check of MahaRERA records (updated November 2026), CITY ICON has one building filed: CITY ICON with 17 floors.
How big is the land of CITY ICON?
According to GharKundli's check of MahaRERA records (updated November 2026), CITY ICON stands on 1,050 sq m of land (about 0.3 acres), with 1,573 sq m of sanctioned built-up area.
What is the track record of CITY ICON's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), City Buildcon (a group of 6 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 4 finished, all within the promised date; 1 still being built, none past the promised date yet; 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of CITY ICON?
Google Maps has reviews of CITY ICON written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is CITY ICON?
CITY ICON by CITY BUILDCON (Times) is in Taloja Navi Mumbai, Raigarh (pincode 410208), near Vashi, Kharghar, Taloja Panchnand, Maharashtra, and is registered on MahaRERA as P52000016409, per GharKundli's check of MahaRERA records.
How many homes are in CITY ICON?
According to GharKundli's check of MahaRERA records (updated November 2026), CITY ICON has 45 homes in 1 tower registered on MahaRERA.
When was CITY ICON registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), CITY ICON was registered on MahaRERA on 10 May 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on CITY ICON?
No court cases are listed for CITY ICON on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of CITY ICON?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is CITY BUILDCON, the company Times files this project under, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of CITY ICON
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 410208
- Konnark Meadows
- Vrundavan
- K K RESIDENCY
- Rudra Rajendra
- ARKAN CASTLE
- NANASETH RESIDENCY
- Saksham Heights
- GREEN LEAF
Other projects by CITY BUILDCON
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.