Balaji Palms Phase - 1

by Balaji Vishwakarma Associates · Alibag, Raigarh

Possession: Balaji Palms Phase - 1 is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000020435. Status: Completed. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Balaji Palms Phase - 1?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Balaji Palms Phase - 1 has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 30 December 2023

    Extended at the builder's request (MahaRERA application EXT52000013944)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covi…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19”

Source: Balaji Palms Phase - 1’s extension records on MahaRERA (P52000020435), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Balaji Palms Phase - 1

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the December 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52000020435
Status
Completed
Builder
Balaji Vishwakarma Associates
Location
Alibag, Raigarh · 402201
Project type
Residential / Group Housing
Registered on
10 Apr 2019
Completion date at registration
December 2022
Latest completion date
December 2023
Delay so far
12 months
Homes
64
Towers
3
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Balaji Palms Phase - 1, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
D Wing100%100%100%100%
E Wing100%100%100%100%
F Wing100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Balaji Palms Phase - 1 every month.

Balaji Palms Phase - 1: buildings, flats and land, as filed on MahaRERA

  • Buildings: D Wing (6 floors) · E Wing (6 floors) · F Wing (6 floors)
  • Land: 2,338 sq m (about 0.6 acres) · sanctioned built-up 2,745 sq m

The builder’s record and reviews

Balaji Vishwakarma Associates has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 6 months). 1 complaint on MahaRERA across 1 project.

Read Google reviews of Balaji Palms Phase - 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Balaji Palms Phase - 1: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Balaji Palms Phase - 1

What is the possession date of Balaji Palms Phase - 1?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Balaji Palms Phase - 1 in Alibag, Raigarh is 30 December 2023 — 12 months later than 30 December 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Balaji Palms Phase - 1?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Balaji Palms Phase - 1's builder has filed on MahaRERA, the official one, is 30 December 2023, already 12 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Balaji Palms Phase - 1 extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Balaji Palms Phase - 1's builder applied to MahaRERA to extend the completion date once: to 30 December 2023, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19".

What is the RERA number of Balaji Palms Phase - 1?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Balaji Palms Phase - 1 in Alibag, Raigarh is P52000020435.

Is Balaji Palms Phase - 1 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Balaji Palms Phase - 1 is registered as P52000020435 and its status is "Completed".

What is the construction status of Balaji Palms Phase - 1?

According to GharKundli's check of MahaRERA records (updated November 2026), Balaji Palms Phase - 1's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.

Does Balaji Palms Phase - 1 have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Balaji Palms Phase - 1 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Balaji Palms Phase - 1 is registered on MahaRERA as P52000020435, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Balaji Palms Phase - 1 have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Balaji Palms Phase -II (P52000033832, possession 29 Jun 2025). Check that your agreement names the registration of your own wing.

How can I get updates if Balaji Palms Phase - 1's possession date changes?

The latest dates are on Balaji Palms Phase - 1's MahaRERA page (P52000020435). GharKundli's Kundli Watch sends a free WhatsApp update on Balaji Palms Phase - 1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Balaji Palms Phase - 1 have?

According to GharKundli's check of MahaRERA records (updated November 2026), Balaji Palms Phase - 1 has 3 buildings filed: D Wing with 6 floors; E Wing with 6 floors; F Wing with 6 floors.

How big is the land of Balaji Palms Phase - 1?

According to GharKundli's check of MahaRERA records (updated November 2026), Balaji Palms Phase - 1 stands on 2,338 sq m of land (about 0.6 acres), with 2,745 sq m of sanctioned built-up area.

What is the track record of Balaji Palms Phase - 1's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Balaji Vishwakarma Associates has 2 projects on MahaRERA since 2019, this one included. Of the 2 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 6 months). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Balaji Palms Phase - 1?

Google Maps has reviews of Balaji Palms Phase - 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Balaji Palms Phase - 1?

Balaji Palms Phase - 1 by Balaji Vishwakarma Associates is in Alibag, Raigarh (pincode 402201), Maharashtra, and is registered on MahaRERA as P52000020435, per GharKundli's check of MahaRERA records.

How many homes are in Balaji Palms Phase - 1?

According to GharKundli's check of MahaRERA records (updated November 2026), Balaji Palms Phase - 1 has 64 homes in 3 towers registered on MahaRERA.

When was Balaji Palms Phase - 1 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Balaji Palms Phase - 1 was registered on MahaRERA on 10 April 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on Balaji Palms Phase - 1?

No court cases are listed for Balaji Palms Phase - 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Balaji Palms Phase - 1?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Balaji Vishwakarma Associates, which has 1 other project registered on MahaRERA.

Other projects in pincode 402201

All 111 projects in Alibag (402201) →

Other projects by Balaji Vishwakarma Associates

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.