Skip to content
GharKundli

COMMANDERS HEERA SIDDHI HOMES PHASE III

by MEGAPLEX PROPERTIES LLP · Karade Khurd, Raigarh

Possession date of COMMANDERS HEERA SIDDHI HOMES PHASE III: 30 April 2028, moved from 30 December 2023 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000023450, and currently active. Its completion date has moved from December 2023 to April 2028: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 2 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about COMMANDERS HEERA SIDDHI HOMES PHASE III?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of COMMANDERS HEERA SIDDHI HOMES PHASE III has moved

  1. 30 December 2023

    Completion date given when the project was registered

  2. 30 December 2027

    Extended at the builder's request (MahaRERA application EXT52000018416)

    Reason the builder gave MahaRERA:
    “In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of C…” Read the full reason“In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 53.42% allottees for purpose of extension of RERA registration period of the said project.”
  3. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: COMMANDERS HEERA SIDDHI HOMES PHASE III’s extension records on MahaRERA (P52000023450), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on COMMANDERS HEERA SIDDHI HOMES PHASE III

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 complaints, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52000023450
Status
Registered and active
Builder
MEGAPLEX PROPERTIES LLP
Location
Karade Khurd, Raigarh · 410220
Project type
Residential / Group Housing
Registered on
16 Dec 2019
Completion date at registration
December 2023
Latest completion date
April 2028
Delay so far
48 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
462
Sold or booked
13%
Towers
8
Complaints on MahaRERA
2
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of COMMANDERS HEERA SIDDHI HOMES PHASE III, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
B5100%0%0%0%
B6100%0%0%0%
B7100%0%0%0%
B8100%0%0%0%
B9100%0%0%0%
B10100%15%0%0%
B11100%15%0%0%
B12100%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • B5: covers 9 floors
  • B6: covers 9 floors
  • B7: covers 9 floors
  • B8: covers 9 floors
  • B9: covers 9 floors
  • B10: covers 9 floors
  • B11: covers 9 floors
  • B12: covers 9 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on COMMANDERS HEERA SIDDHI HOMES PHASE III every month.

COMMANDERS HEERA SIDDHI HOMES PHASE III: buildings, flats and land, as filed on MahaRERA

  • Buildings: B5 (9 floors, 82 units) · B6 (9 floors, 70 units) · B7 (9 floors, 56 units) · B8 (9 floors, 63 units) · B9 (9 floors, 35 units) · B10 (9 floors, 35 units) · B11 (9 floors, 63 units) · B12 (9 floors, 76 units)
  • Car parking: 8 covered
  • Land: 14,000 sq m (about 3.5 acres) · sanctioned built-up 17,600 sq m · recreational space 1,400 sq m

The builder’s record and reviews

Megaplex Properties has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 24 months late). 4 complaints on MahaRERA across 2 projects.

Read Google reviews of COMMANDERS HEERA SIDDHI HOMES PHASE III →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

COMMANDERS HEERA SIDDHI HOMES PHASE III: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about COMMANDERS HEERA SIDDHI HOMES PHASE III

What is the possession date of COMMANDERS HEERA SIDDHI HOMES PHASE III?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for COMMANDERS HEERA SIDDHI HOMES PHASE III in Karade Khurd, Raigarh is 30 April 2028 — 48 months later than 30 December 2023, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for COMMANDERS HEERA SIDDHI HOMES PHASE III?

Builders and listing sites often quote an earlier "target" date for handover. The completion date COMMANDERS HEERA SIDDHI HOMES PHASE III's builder has filed on MahaRERA, the official one, is 30 April 2028, already 48 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of COMMANDERS HEERA SIDDHI HOMES PHASE III extended?

According to GharKundli's check of MahaRERA records (updated October 2026), COMMANDERS HEERA SIDDHI HOMES PHASE III's builder applied to MahaRERA to extend the completion date once: to 30 December 2027, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 7(3) in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19. We have consent of 53.42% allottees for purpose of extension of RERA registration period of the said project.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of COMMANDERS HEERA SIDDHI HOMES PHASE III?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of COMMANDERS HEERA SIDDHI HOMES PHASE III in Karade Khurd, Raigarh is P52000023450.

Is COMMANDERS HEERA SIDDHI HOMES PHASE III registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), COMMANDERS HEERA SIDDHI HOMES PHASE III is registered as P52000023450 and its status is "Registered and active".

What is the construction status of COMMANDERS HEERA SIDDHI HOMES PHASE III?

According to GharKundli's check of MahaRERA records (updated October 2026), COMMANDERS HEERA SIDDHI HOMES PHASE III's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 0% to 15% across 8 towers. GharKundli's full report compares construction progress with the deadline.

Does COMMANDERS HEERA SIDDHI HOMES PHASE III have complaints on MahaRERA?

2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is COMMANDERS HEERA SIDDHI HOMES PHASE III safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), COMMANDERS HEERA SIDDHI HOMES PHASE III is registered on MahaRERA as P52000023450, its completion date has moved 48 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does COMMANDERS HEERA SIDDHI HOMES PHASE III have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: COMMANDERS HEERA SIDDHI HOMES (P52000017262, possession 29 Apr 2028). Check that your agreement names the registration of your own wing.

How can I get updates if COMMANDERS HEERA SIDDHI HOMES PHASE III's possession date changes?

The latest dates are on COMMANDERS HEERA SIDDHI HOMES PHASE III's MahaRERA page (P52000023450). GharKundli's Kundli Watch sends a free WhatsApp update on COMMANDERS HEERA SIDDHI HOMES PHASE III every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does COMMANDERS HEERA SIDDHI HOMES PHASE III have?

According to GharKundli's check of MahaRERA records (updated October 2026), COMMANDERS HEERA SIDDHI HOMES PHASE III has 8 buildings filed: B5 with 9 floors and 82 units; B6 with 9 floors and 70 units; B7 with 9 floors and 56 units; B8 with 9 floors and 63 units; B9 with 9 floors and 35 units; B10 with 9 floors and 35 units; and 2 more.

How much parking does COMMANDERS HEERA SIDDHI HOMES PHASE III have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 8 covered car parking spaces for COMMANDERS HEERA SIDDHI HOMES PHASE III.

How big is the land of COMMANDERS HEERA SIDDHI HOMES PHASE III?

According to GharKundli's check of MahaRERA records (updated October 2026), COMMANDERS HEERA SIDDHI HOMES PHASE III stands on 14,000 sq m of land (about 3.5 acres), with 17,600 sq m of sanctioned built-up area and 1,400 sq m of recreational open space.

What is the track record of COMMANDERS HEERA SIDDHI HOMES PHASE III's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Megaplex Properties has 2 projects on MahaRERA since 2018, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 24 months late). 4 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of COMMANDERS HEERA SIDDHI HOMES PHASE III?

Google Maps has reviews of COMMANDERS HEERA SIDDHI HOMES PHASE III written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is COMMANDERS HEERA SIDDHI HOMES PHASE III?

COMMANDERS HEERA SIDDHI HOMES PHASE III by MEGAPLEX PROPERTIES LLP is in Karade Khurd, Raigarh (pincode 410220), Maharashtra, and is registered on MahaRERA as P52000023450, per GharKundli's check of MahaRERA records.

How many homes are in COMMANDERS HEERA SIDDHI HOMES PHASE III?

According to GharKundli's check of MahaRERA records (updated October 2026), COMMANDERS HEERA SIDDHI HOMES PHASE III has 462 homes in 8 towers registered on MahaRERA, and 13% of them are sold or booked.

When was COMMANDERS HEERA SIDDHI HOMES PHASE III registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), COMMANDERS HEERA SIDDHI HOMES PHASE III was registered on MahaRERA on 16 December 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on COMMANDERS HEERA SIDDHI HOMES PHASE III?

No court cases are listed for COMMANDERS HEERA SIDDHI HOMES PHASE III on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of COMMANDERS HEERA SIDDHI HOMES PHASE III?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is MEGAPLEX PROPERTIES LLP, which has 1 other project registered on MahaRERA.

All projects with possession due in 2028 in Raigad →

Other projects in Panvel

All 9 projects in Patalganga (410220) →

Other projects by MEGAPLEX PROPERTIES LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.