Mantra Marquis Tower 4

by ACME REALTIES PRIVATE LIMITED · Jogeshwari East, MumbaiAlso near Andheri East, Jvlr, Andheri West

Possession date of Mantra Marquis Tower 4: 30 October 2027, moved from 30 December 2022 (54 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800002133, and currently active. Its completion date has moved from December 2022 to October 2027: 54 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 16 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Mantra Marquis Tower 4?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Mantra Marquis Tower 4 has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 29 December 2023

    Extended at the builder's request (MahaRERA application EXT51800012834)

    Reason the builder gave MahaRERA: “1. Force Majeure COVID-19 Pandemic 2. Ongoing Litigations and Complaints 3. Various Challenges to Project”
  3. 30 June 2027

    Extended at the builder's request (MahaRERA application EA24022619988)

    Reason the builder gave MahaRERA:
    “The Promoter company underwent Corporate Insolvency Resolution Process (CIRP) under the Insolvency and Bankruptcy Code, 2016. Pursuant to the approved Resolution Plan, Mantra Properties and Developers Private Limited along with Mr. Rohit Gu…” Read the full reason“The Promoter company underwent Corporate Insolvency Resolution Process (CIRP) under the Insolvency and Bankruptcy Code, 2016. Pursuant to the approved Resolution Plan, Mantra Properties and Developers Private Limited along with Mr. Rohit Gupta were appointed as the Successful Resolution Applicants (SRA). As per the approved Resolution Plan and NCLT Order, the delivery schedule for the units to homebuyers is stipulated within 18 months from the Effective Date (Effective Date: 30/12/2025).”
  4. 30 October 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Mantra Marquis Tower 4’s extension records on MahaRERA (P51800002133), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Mantra Marquis Tower 4

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 16 complaints and 10 court cases, and how it ended
  • Construction pace against the October 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P51800002133
Status
Registered and active
Builder
ACME REALTIES PRIVATE LIMITED
Location
Jogeshwari East, Mumbai · 400060
Project type
Residential / Group Housing
Registered on
31 Jul 2017
Completion date at registration
December 2022
Latest completion date
October 2027
Delay so far
54 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
150
Sold or booked
80%
Towers
1
Complaints on MahaRERA
16
Court cases listed
10
Appeals at the tribunal
1
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Mantra Marquis Tower 4, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Boulevard Tower 4100%100%100%30%

Commencement certificate (CC), as filed on MahaRERA

  • Boulevard Tower 4: covers 33 floors

Latest CC order on MahaRERA: dated 03/02/2023.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Mantra Marquis Tower 4 every month.

Mantra Marquis Tower 4: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
2 BHK73172
3 BHK1,000 – 1,00352
Other87926

The builder’s record and reviews

Acme Realties has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 30 months late). 40 complaints on MahaRERA across 2 projects.

Read Google reviews of Mantra Marquis Tower 4 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Mantra Marquis Tower 4: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Mantra Marquis Tower 4

What is the possession date of Mantra Marquis Tower 4?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Mantra Marquis Tower 4 in Jogeshwari East, Mumbai is 30 October 2027 — 54 months later than 30 December 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Mantra Marquis Tower 4?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Mantra Marquis Tower 4's builder has filed on MahaRERA, the official one, is 30 October 2027, already 54 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Mantra Marquis Tower 4 extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Mantra Marquis Tower 4's builder applied to MahaRERA to extend the completion date 2 times: to 29 December 2023, giving the reason "1. Force Majeure COVID-19 Pandemic 2. Ongoing Litigations and Complaints 3. Various Challenges to Project"; to 30 June 2027, giving the reason "The Promoter company underwent Corporate Insolvency Resolution Process (CIRP) under the Insolvency and Bankruptcy Code, 2016. Pursuant to the approved Resolution Plan, Mantra Properties and Developers Private Limited along with Mr. Rohit Gupta were appointed as the Successful Resolution Applicants (SRA). As per the approved Resolution Plan and NCLT Order, the delivery schedule for the units to homebuyers is stipulated within 18 months from the Effective Date (Effective Date: 30/12/2025).". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Mantra Marquis Tower 4?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Mantra Marquis Tower 4 in Jogeshwari East, Mumbai is P51800002133.

Is Mantra Marquis Tower 4 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Mantra Marquis Tower 4 is registered as P51800002133 and its status is "Registered and active". On MahaRERA's own list: On MahaRERA's insolvency (NCLT) list. MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.

What is the construction status of Mantra Marquis Tower 4?

According to GharKundli's check of MahaRERA records (updated October 2026), Mantra Marquis Tower 4's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Boulevard Tower 4 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Mantra Marquis Tower 4 have complaints on MahaRERA?

16 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Mantra Marquis Tower 4 safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Mantra Marquis Tower 4 is registered on MahaRERA as P51800002133, its completion date has moved 54 months since registration, 16 complaints are listed against it and it is on MahaRERA's list "On MahaRERA's insolvency (NCLT) list". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does Mantra Marquis Tower 4 have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Mantra Marquis Tower 5 (P51800001690, possession 30 Oct 2027). Check that your agreement names the registration of your own wing.

How can I get updates if Mantra Marquis Tower 4's possession date changes?

The latest dates are on Mantra Marquis Tower 4's MahaRERA page (P51800002133). GharKundli's Kundli Watch sends a free WhatsApp update on Mantra Marquis Tower 4 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Mantra Marquis Tower 4 have?

According to GharKundli's check of MahaRERA records (updated October 2026), Mantra Marquis Tower 4 has one building filed: Boulevard Tower 4 with 33 floors and 150 units.

What are the flat sizes (carpet area) in Mantra Marquis Tower 4?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Mantra Marquis Tower 4: 2 BHK: 731 sq ft carpet (72 homes); 3 BHK: 1000 to 1003 sq ft carpet (52 homes); Other: 879 sq ft carpet (26 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does Mantra Marquis Tower 4 have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 237 covered car parking spaces for Mantra Marquis Tower 4.

How big is the land of Mantra Marquis Tower 4?

According to GharKundli's check of MahaRERA records (updated October 2026), Mantra Marquis Tower 4 stands on 32,839 sq m of land (about 8.1 acres), with 13,048 sq m of sanctioned built-up area.

What is the track record of Mantra Marquis Tower 4's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Acme Realties has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 still being built, 2 past the promised date (typically 30 months late). 40 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Mantra Marquis Tower 4?

Google Maps has reviews of Mantra Marquis Tower 4 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 16 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Mantra Marquis Tower 4?

Mantra Marquis Tower 4 by ACME REALTIES PRIVATE LIMITED is in Jogeshwari East, Mumbai (pincode 400060), near Andheri East, Jvlr, Andheri West, Maharashtra, and is registered on MahaRERA as P51800002133, per GharKundli's check of MahaRERA records.

How many homes are in Mantra Marquis Tower 4?

According to GharKundli's check of MahaRERA records (updated October 2026), Mantra Marquis Tower 4 has 150 homes in 1 tower registered on MahaRERA, and 80% of them are sold or booked.

When was Mantra Marquis Tower 4 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Mantra Marquis Tower 4 was registered on MahaRERA on 31 July 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Mantra Marquis Tower 4?

10 court cases are listed for Mantra Marquis Tower 4 on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Mantra Marquis Tower 4?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is ACME REALTIES PRIVATE LIMITED, which has 1 other project registered on MahaRERA.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in pincode 400060

All 97 projects in Jogeshwari East (400060) →

Other projects by ACME REALTIES PRIVATE LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.