Skip to content
GharKundli

Dineshkunj CHS Ltd

by Swastik Realty Pvt Ltd · Bandra East, MumbaiAlso near Goregaon West, Kalanagar, Goregaon East

Possession: Dineshkunj CHS Ltd is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800004364. Status: Completed. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Dineshkunj CHS Ltd?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Dineshkunj CHS Ltd has moved

  1. 30 June 2018

    Completion date given when the project was registered

  2. 30 April 2020

    Extended at the builder's request (MahaRERA application EXT51800000458)

    Reason the builder gave MahaRERA:
    “1. The Project has been granted Registration No P51800004364 with validity up to 30thJune, 2018. 2. The Super Structure of the registered project is fully complete. However, possession cannot be handed over owing to the following reasons: a…” Read the full reason“1. The Project has been granted Registration No P51800004364 with validity up to 30thJune, 2018. 2. The Super Structure of the registered project is fully complete. However, possession cannot be handed over owing to the following reasons: a. The applicable development regulations mandate provision of a Pit Stack Parking in the project prior to grant of Occupancy Certificate. The Work Order for the same was given on 01.02.2018 and the work was to be completed by the contractor by March, 2018. However, the same has not been completed till date. A Notice dated.17.05.2018 and 25.06.2018 has bee…”
  3. 30 April 2020

    Extended at the builder's request (MahaRERA application EXT51800001976)

    Reason the builder gave MahaRERA:
    “1. The Project has been granted Registration No.P51800004364 with validity up to 30th June, 2019. 2. The applicable development regulations mandate provision of a Pit Stack Parking in the project prior to grant of Occupancy Certificate. The…” Read the full reason“1. The Project has been granted Registration No.P51800004364 with validity up to 30th June, 2019. 2. The applicable development regulations mandate provision of a Pit Stack Parking in the project prior to grant of Occupancy Certificate. The Work Order for the same was given on 01.02.2018 and the work was to be completed by the contractor by March, 2018. However, the same has not been completed in all respects and not issued the certificate to that effect till date. A Notice dated.17.05.2018, 25.06.2018, 06.07.2018, 11.01.2019 and 05.02.19 has been issued to the contractor. The application f…”
  4. 31 March 2021

    Extended at the builder's request (MahaRERA application EXT51800008411)

    Reason the builder gave MahaRERA:
    “1. The Project has been granted Registration No.P51800004364 with validity up to 30th October, 2020. 2. The Promoter has applied for grant of electric supply and electric meters has been installed and the electric supply has been started, b…” Read the full reason“1. The Project has been granted Registration No.P51800004364 with validity up to 30th October, 2020. 2. The Promoter has applied for grant of electric supply and electric meters has been installed and the electric supply has been started, by the company. 3. The promoter has applied and MCGM has approved Water Connection P-Form on 31.10.2017 and Plug Connection is approved on 23.04.2018 which will be connected on obtaining O.C. 4. The promoter has applied for grant of Gas supply and the same has been sanctioned, installed and the supply has been started by the company. 5. The Architect has p…”

Source: Dineshkunj CHS Ltd’s extension records on MahaRERA (P51800004364), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Dineshkunj CHS Ltd

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the March 2021 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800004364
Status
Completed
Builder
Swastik Realty Pvt Ltd
Location
Bandra East, Mumbai · 400062
Project type
Residential / Group Housing
Registered on
9 Aug 2017
Completion date at registration
June 2018
Latest completion date
March 2021
Delay so far
33 months
Homes
11
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Appeals at the tribunal
1
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of Dineshkunj CHS Ltd, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Dineshkunj CHS Ltd100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Dineshkunj CHS Ltd every month.

Dineshkunj CHS Ltd: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Swastik Realty has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 56 months); 1 still being built, 1 past the promised date (typically 52 months late); 1 lapsed. 2 complaints on MahaRERA across 2 projects.

Read Google reviews of Dineshkunj CHS Ltd →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Dineshkunj CHS Ltd: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Dineshkunj CHS Ltd

What is the possession date of Dineshkunj CHS Ltd?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Dineshkunj CHS Ltd in Bandra East, Mumbai is 31 March 2021 — 33 months later than 30 June 2018, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Dineshkunj CHS Ltd?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Dineshkunj CHS Ltd's builder has filed on MahaRERA, the official one, is 31 March 2021, already 33 months later than the 30 June 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Dineshkunj CHS Ltd extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Dineshkunj CHS Ltd's builder applied to MahaRERA to extend the completion date 3 times: to 30 April 2020, giving the reason "1. The Project has been granted Registration No P51800004364 with validity up to 30thJune, 2018. 2. The Super Structure of the registered project is fully complete. However, possession cannot be handed over owing to the following reasons: a. The applicable development regulations mandate provision of a Pit Stack Parking in the project prior to grant of Occupancy Certificate. The Work Order for the same was given on 01.02.2018 and the work was to be completed by the contractor by March, 2018. However, the same has not been completed till date. A Notice dated.17.05.2018 and 25.06.2018 has bee…"; to 30 April 2020, giving the reason "1. The Project has been granted Registration No.P51800004364 with validity up to 30th June, 2019. 2. The applicable development regulations mandate provision of a Pit Stack Parking in the project prior to grant of Occupancy Certificate. The Work Order for the same was given on 01.02.2018 and the work was to be completed by the contractor by March, 2018. However, the same has not been completed in all respects and not issued the certificate to that effect till date. A Notice dated.17.05.2018, 25.06.2018, 06.07.2018, 11.01.2019 and 05.02.19 has been issued to the contractor. The application f…"; to 31 March 2021, giving the reason "1. The Project has been granted Registration No.P51800004364 with validity up to 30th October, 2020. 2. The Promoter has applied for grant of electric supply and electric meters has been installed and the electric supply has been started, by the company. 3. The promoter has applied and MCGM has approved Water Connection P-Form on 31.10.2017 and Plug Connection is approved on 23.04.2018 which will be connected on obtaining O.C. 4. The promoter has applied for grant of Gas supply and the same has been sanctioned, installed and the supply has been started by the company. 5. The Architect has p…".

What is the RERA number of Dineshkunj CHS Ltd?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Dineshkunj CHS Ltd in Bandra East, Mumbai is P51800004364.

Is Dineshkunj CHS Ltd registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Dineshkunj CHS Ltd is registered as P51800004364 and its status is "Completed".

What is the construction status of Dineshkunj CHS Ltd?

According to GharKundli's check of MahaRERA records (updated November 2026), Dineshkunj CHS Ltd's status on MahaRERA is "Completed". As filed by the builder, slab work on Dineshkunj CHS Ltd is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Dineshkunj CHS Ltd have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Dineshkunj CHS Ltd safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Dineshkunj CHS Ltd is registered on MahaRERA as P51800004364, its MahaRERA status is "Completed", its completion date has moved 33 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Dineshkunj CHS Ltd's possession date changes?

The latest dates are on Dineshkunj CHS Ltd's MahaRERA page (P51800004364). GharKundli's Kundli Watch sends a free WhatsApp update on Dineshkunj CHS Ltd every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Dineshkunj CHS Ltd have?

According to GharKundli's check of MahaRERA records (updated November 2026), Dineshkunj CHS Ltd has one building filed: Dineshkunj CHS Ltd with 9 floors.

How big is the land of Dineshkunj CHS Ltd?

According to GharKundli's check of MahaRERA records (updated November 2026), Dineshkunj CHS Ltd stands on 499 sq m of land (about 0.1 acres), with 1,346 sq m of sanctioned built-up area.

What is the track record of Dineshkunj CHS Ltd's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Swastik Realty has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 56 months); 1 still being built, 1 past the promised date (typically 52 months late); 1 lapsed. 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Dineshkunj CHS Ltd?

Google Maps has reviews of Dineshkunj CHS Ltd written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Dineshkunj CHS Ltd?

Dineshkunj CHS Ltd by Swastik Realty Pvt Ltd is in Bandra East, Mumbai (pincode 400062), near Goregaon West, Kalanagar, Goregaon East, Maharashtra, and is registered on MahaRERA as P51800004364, per GharKundli's check of MahaRERA records. Its boundaries filed there include Public road.

How many homes are in Dineshkunj CHS Ltd?

According to GharKundli's check of MahaRERA records (updated November 2026), Dineshkunj CHS Ltd has 11 homes in 1 tower registered on MahaRERA.

When was Dineshkunj CHS Ltd registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Dineshkunj CHS Ltd was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Dineshkunj CHS Ltd?

No court cases are listed for Dineshkunj CHS Ltd on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Dineshkunj CHS Ltd?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Swastik Realty Pvt Ltd, which has 3 other projects registered on MahaRERA.

Other projects in Borivali

Other projects by Swastik Realty Pvt Ltd

All Borivali projects with no pincode on MahaRERA →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.