Vaibhav CHS Ltd
by Swastik Realty Pvt Ltd · Goregaon west, MumbaiAlso near Kalanagar, Pahadi goregaon, Goregaon East
Possession date of Vaibhav CHS Ltd: 31 December 2025, moved from 30 June 2018 (90 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800004113. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about Vaibhav CHS Ltd?
How the possession date of Vaibhav CHS Ltd has moved
30 June 2018
Completion date given when the project was registered
30 June 2020
Extended at the builder's request (MahaRERA application EXT51800000457)
Reason the builder gave MahaRERA:
“The project has been granted registration No is P51800004113 with validity up to 30th June, 2018. The real estate project comprises of ground plus 10 upper floors. Of these, the ground and 1st to 4th Floors have already been granted Occupan…” Read the full reason
“The project has been granted registration No is P51800004113 with validity up to 30th June, 2018. The real estate project comprises of ground plus 10 upper floors. Of these, the ground and 1st to 4th Floors have already been granted Occupancy Certificate and the flats situated therein handed over to the society members. Thereafter, these occupants have carried out several illegal additions and alterations to their premises which are contrary to the sanctioned OC Plan thereby causing FSI violations. As a result, though the rest of the building has already been completed, the promoter has bee…”30 June 2020
Extended at the builder's request (MahaRERA application EXT51800001977)
Reason the builder gave MahaRERA:
“The project has been granted registration No.P51800004113 with validity up to 30.06.2019. The real estate project comprises of Ground + 10 upper floors. The said real estate project is completed in all respect upto 10th floors. Of these, th…” Read the full reason
“The project has been granted registration No.P51800004113 with validity up to 30.06.2019. The real estate project comprises of Ground + 10 upper floors. The said real estate project is completed in all respect upto 10th floors. Of these, the ground and 1st to 4th Floors have already been granted Occupancy Certificate and the flats situated therein handed over to the members and fit-out possession for the remaining members. The promoter has been unable to procure O.C. for the remaining floors, for the following reasons. The occupants have carried out several illegal additions and alterations…”31 December 2025
Extended at the builder's request (MahaRERA application EXT51800010170)
Reason the builder gave MahaRERA:
“The project has registration No. P51800004113 with validity upto 30.12.2020. Project is of G+10 upper floors. Project is completed in all respect upto 10th floors. OC is granted upto 4th floor and flats situated therein are handed over to m…” Read the full reason
“The project has registration No. P51800004113 with validity upto 30.12.2020. Project is of G+10 upper floors. Project is completed in all respect upto 10th floors. OC is granted upto 4th floor and flats situated therein are handed over to members and fit-out possession has been given for the remaining members. Promoter has been unable to procure OC for remaining floors, for following reasons. Occupants have carried out illegal additions and alterations to their premises which are contrary to the sanctioned Plan thereby causing FSI violations. Report dtd.20.05.2018 submitted by EE/MCGM as pe…”
Source: Vaibhav CHS Ltd’s extension records on MahaRERA (P51800004113), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Vaibhav CHS Ltd
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint and 3 court cases, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800004113
- Status
- Lapsed (registration period ended)
- Builder
- Swastik Realty Pvt Ltd
- Location
- Goregaon west, Mumbai · 400104
- Project type
- Residential / Group Housing
- Registered on
- 8 Aug 2017
- Completion date at registration
- June 2018
- Latest completion date
- December 2025
- Delay so far
- 90 months
- Homes
- 75
- Sold or booked
- 100%
- Towers
- 2
- Complaints on MahaRERA
- 1
- Court cases listed
- 3
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of Vaibhav CHS Ltd, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Vaibhav CHS Ltd - A | 100% | 11% | 100% | 90% |
| Vaibhav CHS Ltd - B | 100% | 100% | 100% | 90% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vaibhav CHS Ltd every month.
Vaibhav CHS Ltd: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 435 – 789 | 72 |
| Shops | 150 – 164 | 12 |
| Office Space | 515 – 626 | 4 |
| 1 BHK | 325 – 376 | 3 |
- Buildings: Vaibhav CHS Ltd - A (12 floors) · Vaibhav CHS Ltd - B (12 floors)
- Land: 1,095 sq m (about 0.3 acres) · sanctioned built-up 3,923 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Swastik Realty has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 56 months); 1 still being built, 1 past the promised date (typically 52 months late); 1 lapsed. 2 complaints on MahaRERA across 2 projects.
Read Google reviews of Vaibhav CHS Ltd →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Vaibhav CHS Ltd: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Vaibhav CHS Ltd
What is the possession date of Vaibhav CHS Ltd?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Vaibhav CHS Ltd in Goregaon west, Mumbai is 31 December 2025 — 90 months later than 30 June 2018, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Vaibhav CHS Ltd?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Vaibhav CHS Ltd's builder has filed on MahaRERA, the official one, is 31 December 2025, already 90 months later than the 30 June 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Vaibhav CHS Ltd extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Vaibhav CHS Ltd's builder applied to MahaRERA to extend the completion date 3 times: to 30 June 2020, giving the reason "The project has been granted registration No is P51800004113 with validity up to 30th June, 2018. The real estate project comprises of ground plus 10 upper floors. Of these, the ground and 1st to 4th Floors have already been granted Occupancy Certificate and the flats situated therein handed over to the society members. Thereafter, these occupants have carried out several illegal additions and alterations to their premises which are contrary to the sanctioned OC Plan thereby causing FSI violations. As a result, though the rest of the building has already been completed, the promoter has bee…"; to 30 June 2020, giving the reason "The project has been granted registration No.P51800004113 with validity up to 30.06.2019. The real estate project comprises of Ground + 10 upper floors. The said real estate project is completed in all respect upto 10th floors. Of these, the ground and 1st to 4th Floors have already been granted Occupancy Certificate and the flats situated therein handed over to the members and fit-out possession for the remaining members. The promoter has been unable to procure O.C. for the remaining floors, for the following reasons. The occupants have carried out several illegal additions and alterations…"; to 31 December 2025, giving the reason "The project has registration No. P51800004113 with validity upto 30.12.2020. Project is of G+10 upper floors. Project is completed in all respect upto 10th floors. OC is granted upto 4th floor and flats situated therein are handed over to members and fit-out possession has been given for the remaining members. Promoter has been unable to procure OC for remaining floors, for following reasons. Occupants have carried out illegal additions and alterations to their premises which are contrary to the sanctioned Plan thereby causing FSI violations. Report dtd.20.05.2018 submitted by EE/MCGM as pe…".
What is the RERA number of Vaibhav CHS Ltd?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Vaibhav CHS Ltd in Goregaon west, Mumbai is P51800004113.
Is Vaibhav CHS Ltd registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vaibhav CHS Ltd is registered as P51800004113 and its status is "Lapsed (registration period ended)".
What is the construction status of Vaibhav CHS Ltd?
According to GharKundli's check of MahaRERA records (updated October 2026), Vaibhav CHS Ltd's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 11% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Vaibhav CHS Ltd have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Vaibhav CHS Ltd safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Vaibhav CHS Ltd is registered on MahaRERA as P51800004113, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 90 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Vaibhav CHS Ltd's possession date changes?
The latest dates are on Vaibhav CHS Ltd's MahaRERA page (P51800004113). GharKundli's Kundli Watch sends a free WhatsApp update on Vaibhav CHS Ltd every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Vaibhav CHS Ltd have?
According to GharKundli's check of MahaRERA records (updated October 2026), Vaibhav CHS Ltd has 2 buildings filed: Vaibhav CHS Ltd - A with 12 floors; Vaibhav CHS Ltd - B with 12 floors.
What are the flat sizes (carpet area) in Vaibhav CHS Ltd?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Vaibhav CHS Ltd: 2 BHK: 435 to 789 sq ft carpet (72 homes); 1 BHK: 325 to 376 sq ft carpet (3 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Vaibhav CHS Ltd?
According to GharKundli's check of MahaRERA records (updated October 2026), Vaibhav CHS Ltd stands on 1,095 sq m of land (about 0.3 acres), with 3,923 sq m of sanctioned built-up area.
What is the track record of Vaibhav CHS Ltd's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Swastik Realty has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 56 months); 1 still being built, 1 past the promised date (typically 52 months late); 1 lapsed. 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Vaibhav CHS Ltd?
Google Maps has reviews of Vaibhav CHS Ltd written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Vaibhav CHS Ltd?
Vaibhav CHS Ltd by Swastik Realty Pvt Ltd is in Goregaon west, Mumbai (pincode 400104), near Kalanagar, Pahadi goregaon, Goregaon East, Maharashtra, and is registered on MahaRERA as P51800004113, per GharKundli's check of MahaRERA records.
How many homes are in Vaibhav CHS Ltd?
According to GharKundli's check of MahaRERA records (updated October 2026), Vaibhav CHS Ltd has 75 homes in 2 towers registered on MahaRERA, and 100% of them are sold or booked.
When was Vaibhav CHS Ltd registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Vaibhav CHS Ltd was registered on MahaRERA on 8 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Vaibhav CHS Ltd?
3 court cases are listed for Vaibhav CHS Ltd on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Vaibhav CHS Ltd?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Swastik Realty Pvt Ltd, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Vaibhav CHS Ltd
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 400104
- EKTA TRIPOLIS PHASE II
- Sunteck Pinnacle 1
- Paras Residency
- DRM Sheetal Landmark
- io Residences by PCPL
- io Tower by PCPL
- Apricus
- Bali Ananda
Other projects by Swastik Realty Pvt Ltd
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.