SOLSTICE PHASE- I
by NEELAM FINANCE (BOMBAY ) PVT LTD · Kamraj Nagar, MumbaiAlso near Ghatkopar East, Ghatkopar Kirol, Chembur
Possession date of SOLSTICE PHASE- I: 30 April 2027, moved from 30 December 2022 (48 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900002750, and currently active. Its completion date has moved from December 2022 to April 2027: 48 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 7 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SOLSTICE PHASE- I?
GharKundli’s full report on SOLSTICE PHASE- I
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 7 complaints and 4 court cases, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900002750
- Status
- Registered and active
- Builder
- NEELAM FINANCE (BOMBAY ) PVT LTD
- Location
- Kamraj Nagar, Mumbai · 400077
- Project type
- Residential / Group Housing
- Registered on
- 4 Aug 2017
- Completion date at registration
- December 2022
- Latest completion date
- April 2027
- Delay so far
- 48 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 332
- Sold or booked
- 89%
- Towers
- 1
- Complaints on MahaRERA
- 7
- Court cases listed
- 4
- Appeals at the tribunal
- 1
- Title report on file
- Not found
Construction progress of SOLSTICE PHASE- I, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SETARIA AND SAVERIA | 90% | 90% | 90% | 80% |
Commencement certificate (CC), as filed on MahaRERA
- SETARIA AND SAVERIA: covers PLINTH LEVEL
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SOLSTICE PHASE- I every month.
SOLSTICE PHASE- I: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 420 – 480 | 100 |
| 2 BHK | 876 – 877 | 96 |
| Other | 915 | 88 |
| 3 BHK | 1,152 | 48 |
- Buildings: SETARIA AND SAVERIA (31 floors, 332 units)
- Land: 18,100 sq m (about 4.5 acres) · sanctioned built-up 67,381 sq m · recreational space 1,754 sq m
- Boundaries filed include: EASTERN EXPRESS HIGHWAY
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Neelam Finance Bombay (a group of 3 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 1 finished, all within the promised date; 4 still being built, 1 past the promised date (typically 30 months late). 13 complaints on MahaRERA across 5 projects.
Read Google reviews of SOLSTICE PHASE- I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SOLSTICE PHASE- I: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SOLSTICE PHASE- I
What is the possession date of SOLSTICE PHASE- I?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SOLSTICE PHASE- I in Kamraj Nagar, Mumbai is 30 April 2027 — 48 months later than 30 December 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SOLSTICE PHASE- I?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SOLSTICE PHASE- I's builder has filed on MahaRERA, the official one, is 30 April 2027, already 48 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of SOLSTICE PHASE- I?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SOLSTICE PHASE- I in Kamraj Nagar, Mumbai is P51900002750.
Is SOLSTICE PHASE- I registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SOLSTICE PHASE- I is registered as P51900002750 and its status is "Registered and active".
What is the construction status of SOLSTICE PHASE- I?
According to GharKundli's check of MahaRERA records (updated October 2026), SOLSTICE PHASE- I's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SETARIA AND SAVERIA is 90% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.
Does SOLSTICE PHASE- I have complaints on MahaRERA?
7 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SOLSTICE PHASE- I safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SOLSTICE PHASE- I is registered on MahaRERA as P51900002750, its completion date has moved 48 months since registration and 7 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SOLSTICE PHASE- I's possession date changes?
The latest dates are on SOLSTICE PHASE- I's MahaRERA page (P51900002750). GharKundli's Kundli Watch sends a free WhatsApp update on SOLSTICE PHASE- I every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SOLSTICE PHASE- I have?
According to GharKundli's check of MahaRERA records (updated October 2026), SOLSTICE PHASE- I has one building filed: SETARIA AND SAVERIA with 31 floors and 332 units.
What are the flat sizes (carpet area) in SOLSTICE PHASE- I?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SOLSTICE PHASE- I: 1 BHK: 420 to 480 sq ft carpet (100 homes); 2 BHK: 876 to 877 sq ft carpet (96 homes); Other: 915 sq ft carpet (88 homes); 3 BHK: 1152 sq ft carpet (48 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of SOLSTICE PHASE- I?
According to GharKundli's check of MahaRERA records (updated October 2026), SOLSTICE PHASE- I stands on 18,100 sq m of land (about 4.5 acres), with 67,381 sq m of sanctioned built-up area and 1,754 sq m of recreational open space.
What is the track record of SOLSTICE PHASE- I's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Neelam Finance Bombay (a group of 3 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 1 finished, all within the promised date; 4 still being built, 1 past the promised date (typically 30 months late). 13 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SOLSTICE PHASE- I?
Google Maps has reviews of SOLSTICE PHASE- I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 7 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SOLSTICE PHASE- I?
SOLSTICE PHASE- I by NEELAM FINANCE (BOMBAY ) PVT LTD is in Kamraj Nagar, Mumbai (pincode 400077), near Ghatkopar East, Ghatkopar Kirol, Chembur, Maharashtra, and is registered on MahaRERA as P51900002750, per GharKundli's check of MahaRERA records. Its boundaries filed there include EASTERN EXPRESS HIGHWAY.
How many homes are in SOLSTICE PHASE- I?
According to GharKundli's check of MahaRERA records (updated October 2026), SOLSTICE PHASE- I has 332 homes in 1 tower registered on MahaRERA, and 89% of them are sold or booked.
When was SOLSTICE PHASE- I registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SOLSTICE PHASE- I was registered on MahaRERA on 4 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on SOLSTICE PHASE- I?
4 court cases are listed for SOLSTICE PHASE- I on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of SOLSTICE PHASE- I?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is NEELAM FINANCE (BOMBAY ) PVT LTD.
Check it yourself on MahaRERA
- How to check the possession date of SOLSTICE PHASE- I
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
All projects in Ghatkopar East (400077) →
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.