Acons Prive
by Akshay Gulati · Vidya Nagar, RaigarhAlso near Chendhare, Alibag
Possession: Acons Prive is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000030437. Status: Completed.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Acons Prive?
How the possession date of Acons Prive has moved
1 December 2025
Completion date given when the project was registered
30 June 2026
Extended at the builder's request (MahaRERA application EA05012619296)
Reason the builder gave MahaRERA:
“We would like to state that the extension is being sought primarily because the Occupancy Certificate (OC) for the project is currently awaited. Although the construction work has been substantially completed, the final statutory approvals…” Read the full reason
“We would like to state that the extension is being sought primarily because the Occupancy Certificate (OC) for the project is currently awaited. Although the construction work has been substantially completed, the final statutory approvals and processes required for the issuance of the OC are still in progress. These procedures have taken longer than anticipated due to coordination with various authorities and the sequential nature of compliance checks involved. As the OC is a mandatory requirement for marking the project as complete on the MahaRERA portal, we are constrained from closing t…”
Source: Acons Prive’s extension records on MahaRERA (P52000030437), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Acons Prive
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000030437
- Status
- Completed
- Builder
- Akshay Gulati
- Location
- Vidya Nagar, Raigarh · 402201
- Project type
- Others
- Registered on
- 25 Aug 2021
- Completion date at registration
- December 2025
- Latest completion date
- June 2026
- Delay so far
- 6 months
- Homes
- 100
- Sold or booked
- 62%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Acons Prive, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Acons Prive Building 1 | 100% | 100% | 100% | 80% |
| Acons Prive Building 2 | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- Acons Prive Building 1: covers 6 (G + 5)
- Acons Prive Building 2: covers 6 (G + 5)
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Acons Prive every month.
Acons Prive: buildings, flats and land, as filed on MahaRERA
- Buildings: Acons Prive Building 1 (7 floors, 49 units) · Acons Prive Building 2 (7 floors, 60 units)
- Land: 2,250 sq m (about 0.6 acres) · sanctioned built-up 5,131 sq m
- Boundaries filed include: Society
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Aarun Gulati (a group of 2 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 15 months); 1 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of Acons Prive →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Acons Prive: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Acons Prive
What is the possession date of Acons Prive?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Acons Prive in Vidya Nagar, Raigarh is 30 June 2026 — 6 months later than 1 December 2025, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Acons Prive?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Acons Prive's builder has filed on MahaRERA, the official one, is 30 June 2026, already 6 months later than the 1 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Acons Prive extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Acons Prive's builder applied to MahaRERA to extend the completion date once: to 30 June 2026, giving the reason "We would like to state that the extension is being sought primarily because the Occupancy Certificate (OC) for the project is currently awaited. Although the construction work has been substantially completed, the final statutory approvals and processes required for the issuance of the OC are still in progress. These procedures have taken longer than anticipated due to coordination with various authorities and the sequential nature of compliance checks involved. As the OC is a mandatory requirement for marking the project as complete on the MahaRERA portal, we are constrained from closing t…".
What is the RERA number of Acons Prive?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Acons Prive in Vidya Nagar, Raigarh is P52000030437.
Is Acons Prive registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Acons Prive is registered as P52000030437 and its status is "Completed".
What is the construction status of Acons Prive?
According to GharKundli's check of MahaRERA records (updated October 2026), Acons Prive's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Acons Prive have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Acons Prive safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Acons Prive is registered on MahaRERA as P52000030437, its MahaRERA status is "Completed", its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Acons Prive's possession date changes?
The latest dates are on Acons Prive's MahaRERA page (P52000030437). GharKundli's Kundli Watch sends a free WhatsApp update on Acons Prive every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Acons Prive have?
According to GharKundli's check of MahaRERA records (updated October 2026), Acons Prive has 2 buildings filed: Acons Prive Building 1 with 7 floors and 49 units; Acons Prive Building 2 with 7 floors and 60 units.
How big is the land of Acons Prive?
According to GharKundli's check of MahaRERA records (updated October 2026), Acons Prive stands on 2,250 sq m of land (about 0.6 acres), with 5,131 sq m of sanctioned built-up area.
What is the track record of Acons Prive's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Aarun Gulati (a group of 2 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 15 months); 1 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Acons Prive?
Google Maps has reviews of Acons Prive written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Acons Prive?
Acons Prive by Akshay Gulati is in Vidya Nagar, Raigarh (pincode 402201), near Chendhare, Alibag, Maharashtra, and is registered on MahaRERA as P52000030437, per GharKundli's check of MahaRERA records. Its boundaries filed there include Society.
How many homes are in Acons Prive?
According to GharKundli's check of MahaRERA records (updated October 2026), Acons Prive has 100 homes in 2 towers registered on MahaRERA, and 62% of them are sold or booked.
When was Acons Prive registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Acons Prive was registered on MahaRERA on 25 August 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on Acons Prive?
No court cases are listed for Acons Prive on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Acons Prive?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Akshay Gulati, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Acons Prive
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Alibag
- PRAJYOT EXTEND
- Esmeralda by Forstar
- VAIBHAV CO-OPERATIVE HOUSING SOCIETY PROPOSED
- Jog Plaza
- THE ELYSIAN
- 7 KOLGAON-PHASE-1
- SaffronSuites Alibaug - 9
- BALIBAUG REKREASI
Other projects by Akshay Gulati
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.