Monika Residency
by JANKI DEVELOPERS · Pushpak New, Raigarh
Possession date of Monika Residency: 31 December 2025, moved from 30 June 2024 (18 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P52000028412. Status: Lapsed (registration period ended). 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
The latest completion date on MahaRERA (December 2025) has passed.
What do you want to know about Monika Residency?
How the possession date of Monika Residency has moved
30 June 2024
Completion date given when the project was registered
30 June 2025
Extended at the builder's request (MahaRERA application EXT52000018801)
Reason the builder gave MahaRERA:
“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covi…” Read the full reason
“In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19.”31 December 2025
Extended at the builder's request (MahaRERA application EA24072502185)
Reason the builder gave MahaRERA:
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these…” Read the full reason
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work.”
Source: Monika Residency’s extension records on MahaRERA (P52000028412), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Monika Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the December 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000028412
- Status
- Lapsed (registration period ended)
- Builder
- JANKI DEVELOPERS
- Location
- Pushpak New, Raigarh · 410206
- Project type
- Others
- Registered on
- 2 Mar 2021
- Completion date at registration
- June 2024
- Latest completion date
- December 2025
- Delay so far
- 18 months
- Homes
- 28
- Sold or booked
- 41%
- Towers
- 1
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of Monika Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Monika Residency | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Monika Residency: covers 8 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Monika Residency every month.
Monika Residency: buildings, flats and land, as filed on MahaRERA
- Buildings: Monika Residency (8 floors, 34 units)
- Land: 580 sq m (about 0.1 acres) · sanctioned built-up 869 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Monika Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Monika Residency: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Monika Residency
What is the possession date of Monika Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Monika Residency in Pushpak New, Raigarh is 31 December 2025 — 18 months later than 30 June 2024, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Monika Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Monika Residency's builder has filed on MahaRERA, the official one, is 31 December 2025, already 18 months later than the 30 June 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Monika Residency extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Monika Residency's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2025, giving the reason "In accordance with circular no 28, we hereby apply for extension of our project u/s 6 in Format B. The project was delayed for reasons beyond our control on account of various reasons and more particularly on account of the pandemic of Covid-19."; to 31 December 2025, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to unforeseen circumstances, including procurement issues, financial constraints, and site challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work.".
What is the RERA number of Monika Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Monika Residency in Pushpak New, Raigarh is P52000028412.
Is Monika Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Monika Residency is registered as P52000028412 and its status is "Lapsed (registration period ended)".
What is the construction status of Monika Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Monika Residency's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on Monika Residency is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Monika Residency have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Monika Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Monika Residency is registered on MahaRERA as P52000028412, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 18 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Monika Residency's possession date changes?
The latest dates are on Monika Residency's MahaRERA page (P52000028412). GharKundli's Kundli Watch sends a free WhatsApp update on Monika Residency every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Monika Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), Monika Residency has one building filed: Monika Residency with 8 floors and 34 units.
How big is the land of Monika Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Monika Residency stands on 580 sq m of land (about 0.1 acres), with 869 sq m of sanctioned built-up area.
Where can I read reviews of Monika Residency?
Google Maps has reviews of Monika Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Monika Residency?
Monika Residency by JANKI DEVELOPERS is in Pushpak New, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000028412, per GharKundli's check of MahaRERA records.
How many homes are in Monika Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Monika Residency has 28 homes in 1 tower registered on MahaRERA, and 41% of them are sold or booked.
When was Monika Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Monika Residency was registered on MahaRERA on 2 March 2021. GharKundli did not find a title report on the land on file there.
Are there court cases on Monika Residency?
No court cases are listed for Monika Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Monika Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is JANKI DEVELOPERS, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Monika Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Pushpak New
- SAHEJANAND
- SAI ELEGANCE
- ROCKGOLD RUBY
- GANGA HEIGHTS
- Sai Heights
- MADHAV HEIGHTS
- Savitri Ashirwad Apartment
- SIDDHIVINAYAK RESIDENCY
Other projects by JANKI DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.