METROPOLIS RESIDENCES
by HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD · Bandra East, MumbaiAlso near Andheri East, Andheri West, Marol
Possession date of METROPOLIS RESIDENCES: 20 May 2018, moved from 31 December 2017 (5 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800012577. Status: Lapsed (registration period ended). 5 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (May 2018) has passed.
On MahaRERA's insolvency (NCLT) list
MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.
On MahaRERA’s list since at least 23 Oct 2026See MahaRERA’s list
What do you want to know about METROPOLIS RESIDENCES?
How the possession date of METROPOLIS RESIDENCES has moved
31 December 2017
Completion date given when the project was registered
20 May 2018
Extended at the builder's request (MahaRERA application EXT51800000004)
Reason the builder gave MahaRERA:
“The majority construction work at the project site has been completed except for few work on mechanical car parking,fire fighting and ventilation system . The Company has handed over the possession of the total no.417 number of flats out of…” Read the full reason
“The majority construction work at the project site has been completed except for few work on mechanical car parking,fire fighting and ventilation system . The Company has handed over the possession of the total no.417 number of flats out of the total sold flats of no.472 .Members have already formed the Society and the society has been registered. Further the Occupancy Certificate is awaited which may take some time.Hence we are looking for applying for updating the revised Project completion date .”
Source: METROPOLIS RESIDENCES’s extension records on MahaRERA (P51800012577), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on METROPOLIS RESIDENCES
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 5 complaints and 2 court cases, and how it ended
- Construction pace against the May 2018 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800012577
- Status
- Lapsed (registration period ended)
- Builder
- HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD
- Location
- Bandra East, Mumbai · 400053
- Project type
- Residential / Group Housing
- Registered on
- 4 Sep 2017
- Completion date at registration
- December 2017
- Latest completion date
- May 2018
- Delay so far
- 5 months
- Homes
- 472
- Towers
- 3
- Complaints on MahaRERA
- 5
- Court cases listed
- 2
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 13
Construction progress of METROPOLIS RESIDENCES, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| WING - A | 100% | 100% | 100% | 80% |
| WING-B | 100% | 100% | 100% | 80% |
| WING-C | 100% | 100% | 100% | 80% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on METROPOLIS RESIDENCES every month.
METROPOLIS RESIDENCES: buildings, flats and land, as filed on MahaRERA
- Buildings: WING - A (39 floors) · WING-B (39 floors) · WING-C (39 floors)
- Land: 8,007 sq m (about 2.0 acres) · sanctioned built-up 49,521 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Housing Development AND Infrastructure has 14 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 1 finished, all within the promised date; 7 lapsed. 215 complaints on MahaRERA across 8 projects.
Read Google reviews of METROPOLIS RESIDENCES →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
METROPOLIS RESIDENCES: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about METROPOLIS RESIDENCES
What is the possession date of METROPOLIS RESIDENCES?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for METROPOLIS RESIDENCES in Bandra East, Mumbai is 20 May 2018 — 5 months later than 31 December 2017, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for METROPOLIS RESIDENCES?
Builders and listing sites often quote an earlier "target" date for handover. The completion date METROPOLIS RESIDENCES's builder has filed on MahaRERA, the official one, is 20 May 2018, already 5 months later than the 31 December 2017 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of METROPOLIS RESIDENCES extended?
According to GharKundli's check of MahaRERA records (updated November 2026), METROPOLIS RESIDENCES's builder applied to MahaRERA to extend the completion date once: to 20 May 2018, giving the reason "The majority construction work at the project site has been completed except for few work on mechanical car parking,fire fighting and ventilation system . The Company has handed over the possession of the total no.417 number of flats out of the total sold flats of no.472 .Members have already formed the Society and the society has been registered. Further the Occupancy Certificate is awaited which may take some time.Hence we are looking for applying for updating the revised Project completion date .".
What is the RERA number of METROPOLIS RESIDENCES?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of METROPOLIS RESIDENCES in Bandra East, Mumbai is P51800012577.
Is METROPOLIS RESIDENCES registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), METROPOLIS RESIDENCES is registered as P51800012577 and its status is "Lapsed (registration period ended)". On MahaRERA's own list: On MahaRERA's insolvency (NCLT) list. MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.
What is the construction status of METROPOLIS RESIDENCES?
According to GharKundli's check of MahaRERA records (updated November 2026), METROPOLIS RESIDENCES's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does METROPOLIS RESIDENCES have complaints on MahaRERA?
5 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is METROPOLIS RESIDENCES safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), METROPOLIS RESIDENCES is registered on MahaRERA as P51800012577, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 5 months since registration, 5 complaints are listed against it and it is on MahaRERA's list "On MahaRERA's insolvency (NCLT) list". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if METROPOLIS RESIDENCES's possession date changes?
The latest dates are on METROPOLIS RESIDENCES's MahaRERA page (P51800012577). GharKundli's Kundli Watch sends a free WhatsApp update on METROPOLIS RESIDENCES every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does METROPOLIS RESIDENCES have?
According to GharKundli's check of MahaRERA records (updated November 2026), METROPOLIS RESIDENCES has 3 buildings filed: WING - A with 39 floors; WING-B with 39 floors; WING-C with 39 floors.
How big is the land of METROPOLIS RESIDENCES?
According to GharKundli's check of MahaRERA records (updated November 2026), METROPOLIS RESIDENCES stands on 8,007 sq m of land (about 2.0 acres), with 49,521 sq m of sanctioned built-up area.
What is the track record of METROPOLIS RESIDENCES's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Housing Development AND Infrastructure has 14 projects on MahaRERA since 2017, this one included. Of the 8 GharKundli has checked: 1 finished, all within the promised date; 7 lapsed. 215 complaints on MahaRERA across 8 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of METROPOLIS RESIDENCES?
Google Maps has reviews of METROPOLIS RESIDENCES written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 5 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is METROPOLIS RESIDENCES?
METROPOLIS RESIDENCES by HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD is in Bandra East, Mumbai (pincode 400053), near Andheri East, Andheri West, Marol, Maharashtra, and is registered on MahaRERA as P51800012577, per GharKundli's check of MahaRERA records.
How many homes are in METROPOLIS RESIDENCES?
According to GharKundli's check of MahaRERA records (updated November 2026), METROPOLIS RESIDENCES has 472 homes in 3 towers registered on MahaRERA.
When was METROPOLIS RESIDENCES registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), METROPOLIS RESIDENCES was registered on MahaRERA on 4 September 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on METROPOLIS RESIDENCES?
2 court cases are listed for METROPOLIS RESIDENCES on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of METROPOLIS RESIDENCES?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD, which has 13 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of METROPOLIS RESIDENCES
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Andheri
- SHRADDHA WEST RESIDENCY
- Green Bay
- SHIVSAI SRA CHS
- Live Well Chs Ltd
- KK 415 WEST
- Lotus Sky Plaza
- THERESE
- Pruthvi Symphony
Other projects by HOUSING DEVELOPMENT AND INFRASTRUCTURE LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.