SAI DEEP RESIDENCY

by PAVAN MAHATMA DEVALKAR · Pushpak Nagar, Raigarh

Possession date of SAI DEEP RESIDENCY: 31 December 2026, moved from 31 December 2024 (20 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000034601, and currently active. Its completion date has moved from December 2024 to December 2026: 20 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SAI DEEP RESIDENCY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SAI DEEP RESIDENCY has moved

  1. 31 December 2024

    Completion date given when the project was registered

  2. 31 August 2026

    Extended at the builder's request (MahaRERA application EA19112518373)

    Reason the builder gave MahaRERA: “earlier due to some personal reason it was delayed but now the project is almost completed and we are applied for oc hence till the oc will received we are applied for extension so i request you to please approved the extension”
  3. 31 December 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: SAI DEEP RESIDENCY’s extension records on MahaRERA (P52000034601), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SAI DEEP RESIDENCY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000034601
Status
Registered and active
Builder
PAVAN MAHATMA DEVALKAR
Location
Pushpak Nagar, Raigarh · 410221
Project type
Others
Registered on
11 Apr 2022
Completion date at registration
December 2024
Latest completion date
December 2026
Delay so far
20 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
15
Sold or booked
83%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of SAI DEEP RESIDENCY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SAI DEEP RESIDENCY100%100%100%98%

Commencement certificate (CC), as filed on MahaRERA

  • SAI DEEP RESIDENCY: covers G+4

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAI DEEP RESIDENCY every month.

SAI DEEP RESIDENCY: buildings, flats and land, as filed on MahaRERA

  • Buildings: SAI DEEP RESIDENCY (5 floors, 18 units)
  • Car parking: 5 open
  • Land: 300 sq m (about 0.1 acres) · sanctioned built-up 449 sq m

The builder’s record and reviews

Pavan Mahatma Devalkar has 5 projects on MahaRERA since 2021, this one included. Of the 5 GharKundli has checked: 5 still being built, 2 past the promised date (typically 24 months late). No complaints on MahaRERA.

Read Google reviews of SAI DEEP RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SAI DEEP RESIDENCY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SAI DEEP RESIDENCY

What is the possession date of SAI DEEP RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SAI DEEP RESIDENCY in Pushpak Nagar, Raigarh is 31 December 2026 — 20 months later than 31 December 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for SAI DEEP RESIDENCY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SAI DEEP RESIDENCY's builder has filed on MahaRERA, the official one, is 31 December 2026, already 20 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SAI DEEP RESIDENCY extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI DEEP RESIDENCY's builder applied to MahaRERA to extend the completion date once: to 31 August 2026, giving the reason "earlier due to some personal reason it was delayed but now the project is almost completed and we are applied for oc hence till the oc will received we are applied for extension so i request you to please approved the extension". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of SAI DEEP RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SAI DEEP RESIDENCY in Pushpak Nagar, Raigarh is P52000034601.

Is SAI DEEP RESIDENCY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI DEEP RESIDENCY is registered as P52000034601 and its status is "Registered and active".

What is the construction status of SAI DEEP RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI DEEP RESIDENCY's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SAI DEEP RESIDENCY is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does SAI DEEP RESIDENCY have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is SAI DEEP RESIDENCY safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI DEEP RESIDENCY is registered on MahaRERA as P52000034601, its completion date has moved 20 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SAI DEEP RESIDENCY's possession date changes?

The latest dates are on SAI DEEP RESIDENCY's MahaRERA page (P52000034601). GharKundli's Kundli Watch sends a free WhatsApp update on SAI DEEP RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SAI DEEP RESIDENCY have?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI DEEP RESIDENCY has one building filed: SAI DEEP RESIDENCY with 5 floors and 18 units.

How much parking does SAI DEEP RESIDENCY have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 5 open car parking spaces for SAI DEEP RESIDENCY.

How big is the land of SAI DEEP RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI DEEP RESIDENCY stands on 300 sq m of land (about 0.1 acres), with 449 sq m of sanctioned built-up area.

What is the track record of SAI DEEP RESIDENCY's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Pavan Mahatma Devalkar has 5 projects on MahaRERA since 2021, this one included. Of the 5 GharKundli has checked: 5 still being built, 2 past the promised date (typically 24 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of SAI DEEP RESIDENCY?

Google Maps has reviews of SAI DEEP RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SAI DEEP RESIDENCY?

SAI DEEP RESIDENCY by PAVAN MAHATMA DEVALKAR is in Pushpak Nagar, Raigarh (pincode 410221), Maharashtra, and is registered on MahaRERA as P52000034601, per GharKundli's check of MahaRERA records.

How many homes are in SAI DEEP RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI DEEP RESIDENCY has 15 homes in 1 tower registered on MahaRERA, and 83% of them are sold or booked.

When was SAI DEEP RESIDENCY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAI DEEP RESIDENCY was registered on MahaRERA on 11 April 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on SAI DEEP RESIDENCY?

No court cases are listed for SAI DEEP RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of SAI DEEP RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PAVAN MAHATMA DEVALKAR, which has 3 other projects registered on MahaRERA.

All projects with possession due in 2026 in Raigad →

Other projects in Panvel

All 102 projects in Panvel (410221) →

Other projects by PAVAN MAHATMA DEVALKAR

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.