KRISHNA RESIDENCY

by PRATAP BABAJI SHINDE · Taloja, RaigarhAlso near Kharghar, Vashi, Navi Mumbai

Possession: KRISHNA RESIDENCY is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000034269. Status: Completed.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about KRISHNA RESIDENCY?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of KRISHNA RESIDENCY has moved

  1. 31 December 2025

    Completion date given when the project was registered

  2. 30 June 2026

    Extended at the builder's request (MahaRERA application EA20012619519)

    Reason the builder gave MahaRERA: “Our project has been 100% completed, and we are waiting for the Occupancy Certificate.”

Source: KRISHNA RESIDENCY’s extension records on MahaRERA (P52000034269), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on KRISHNA RESIDENCY

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000034269
Status
Completed
Builder
PRATAP BABAJI SHINDE
Location
Taloja, Raigarh · 410208
Project type
Residential / Group Housing
Registered on
30 Mar 2022
Completion date at registration
December 2025
Latest completion date
June 2026
Delay so far
6 months
Homes
103
Sold or booked
81%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of KRISHNA RESIDENCY, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
KRISHNA RESIDENCY100%100%100%90%

Commencement certificate (CC), as filed on MahaRERA

  • KRISHNA RESIDENCY: covers 11 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on KRISHNA RESIDENCY every month.

KRISHNA RESIDENCY: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of KRISHNA RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

KRISHNA RESIDENCY: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about KRISHNA RESIDENCY

What is the possession date of KRISHNA RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for KRISHNA RESIDENCY in Taloja, Raigarh is 30 June 2026 — 6 months later than 31 December 2025, the date given at registration.

Is the builder's possession date different from the MahaRERA date for KRISHNA RESIDENCY?

Builders and listing sites often quote an earlier "target" date for handover. The completion date KRISHNA RESIDENCY's builder has filed on MahaRERA, the official one, is 30 June 2026, already 6 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of KRISHNA RESIDENCY extended?

According to GharKundli's check of MahaRERA records (updated October 2026), KRISHNA RESIDENCY's builder applied to MahaRERA to extend the completion date once: to 30 June 2026, giving the reason "Our project has been 100% completed, and we are waiting for the Occupancy Certificate.".

What is the RERA number of KRISHNA RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of KRISHNA RESIDENCY in Taloja, Raigarh is P52000034269.

Is KRISHNA RESIDENCY registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), KRISHNA RESIDENCY is registered as P52000034269 and its status is "Completed".

What is the construction status of KRISHNA RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), KRISHNA RESIDENCY's status on MahaRERA is "Completed". As filed by the builder, slab work on KRISHNA RESIDENCY is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does KRISHNA RESIDENCY have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is KRISHNA RESIDENCY safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), KRISHNA RESIDENCY is registered on MahaRERA as P52000034269, its MahaRERA status is "Completed", its completion date has moved 6 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if KRISHNA RESIDENCY's possession date changes?

The latest dates are on KRISHNA RESIDENCY's MahaRERA page (P52000034269). GharKundli's Kundli Watch sends a free WhatsApp update on KRISHNA RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does KRISHNA RESIDENCY have?

According to GharKundli's check of MahaRERA records (updated October 2026), KRISHNA RESIDENCY has one building filed: KRISHNA RESIDENCY with 11 floors and 119 units.

How much parking does KRISHNA RESIDENCY have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 33 covered and 97 open car parking spaces for KRISHNA RESIDENCY.

How big is the land of KRISHNA RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), KRISHNA RESIDENCY stands on 1,970 sq m of land (about 0.5 acres), with 5,421 sq m of sanctioned built-up area.

Where can I read reviews of KRISHNA RESIDENCY?

Google Maps has reviews of KRISHNA RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is KRISHNA RESIDENCY?

KRISHNA RESIDENCY by PRATAP BABAJI SHINDE is in Taloja, Raigarh (pincode 410208), near Kharghar, Vashi, Navi Mumbai, Maharashtra, and is registered on MahaRERA as P52000034269, per GharKundli's check of MahaRERA records.

How many homes are in KRISHNA RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), KRISHNA RESIDENCY has 103 homes in 1 tower registered on MahaRERA, and 81% of them are sold or booked.

When was KRISHNA RESIDENCY registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), KRISHNA RESIDENCY was registered on MahaRERA on 30 March 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on KRISHNA RESIDENCY?

No court cases are listed for KRISHNA RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of KRISHNA RESIDENCY?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is PRATAP BABAJI SHINDE.

Other projects in pincode 410208

All 337 projects in Taloja (410208) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.