by HIRANIMANTHAN BUILDERS AND DEVELOPERS · Nehru Nagar, MumbaiAlso near Kurla West, Chembur

Registered on MahaRERA under P51800004914. Status: Completed. Its completion date has moved from December 2019 to November 2024, 59 months later.

Source: GharKundli’s check of MahaRERA records, November 2026.

GharKundli’s full report on SWANAND BLDG NO 33

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800004914
Status
Completed
Builder
HIRANIMANTHAN BUILDERS AND DEVELOPERS
Location
Nehru Nagar, Mumbai · 400024
Project type
Residential / Group Housing
Registered on
9 Aug 2017
Completion date at registration
December 2019
Latest completion date
November 2024
Delay so far
59 months
Homes
89
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
5

Kundli Watch

SWANAND BLDG NO 33: buyers & owners

Free. You talk to our team privately — no one sees your number.

How are you connected to this project?

You’ll sign in with your mobile number first, then come straight back here.

Common questions about SWANAND BLDG NO 33

Is SWANAND BLDG NO 33 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SWANAND BLDG NO 33 is registered as P51800004914 and its status is "Completed".

Where is SWANAND BLDG NO 33?

SWANAND BLDG NO 33 by HIRANIMANTHAN BUILDERS AND DEVELOPERS is in Nehru Nagar, Mumbai (pincode 400024), near Kurla West, Chembur, Maharashtra, and is registered on MahaRERA as P51800004914, per GharKundli's check of MahaRERA records.

When is possession of SWANAND BLDG NO 33 due?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SWANAND BLDG NO 33 in Nehru Nagar, Mumbai is 30 November 2024 — 59 months later than 31 December 2019, the date given at registration.

Does SWANAND BLDG NO 33 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

How many homes are in SWANAND BLDG NO 33?

According to GharKundli's check of MahaRERA records (updated November 2026), SWANAND BLDG NO 33 has 89 homes in 1 tower registered on MahaRERA.

When was SWANAND BLDG NO 33 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), SWANAND BLDG NO 33 was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on SWANAND BLDG NO 33?

No court cases are listed for SWANAND BLDG NO 33 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of SWANAND BLDG NO 33?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is HIRANIMANTHAN BUILDERS AND DEVELOPERS, which has 5 other projects registered on MahaRERA.

Other projects in pincode 400024

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.