SAPTARSHI MARK
by Saptrishi Realtors · Nehru Nagar, MumbaiAlso near Kurla West
Possession date of SAPTARSHI MARK: 31 March 2027, moved from 30 December 2023 (39 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800017508, and currently active. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SAPTARSHI MARK?
How the possession date of SAPTARSHI MARK has moved
30 December 2023
Completion date given when the project was registered
29 December 2024
Extended at the builder's request (MahaRERA application EXT51800018743)
Reason the builder gave MahaRERA: “As per the attachment”
29 December 2025
Extended at the builder's request (MahaRERA application EXT51800025951)
Reason the builder gave MahaRERA: “As per attachment”
31 March 2027
Extended at the builder's request (MahaRERA application EA01042620519)
Reason the builder gave MahaRERA: “We are applying order bearing number 40/2022 dated 22nd December 2022 issued by the Maharashtra Real Estate Regulatory Authority(MahaRERA)” that is extension without consent”
Source: SAPTARSHI MARK’s extension records on MahaRERA (P51800017508), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SAPTARSHI MARK
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the March 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800017508
- Status
- Registered and active
- Builder
- Saptrishi Realtors
- Location
- Nehru Nagar, Mumbai · 400024
- Project type
- Residential / Group Housing
- Registered on
- 23 Aug 2018
- Completion date at registration
- December 2023
- Latest completion date
- March 2027
- Delay so far
- 39 months
- Homes
- 134
- Sold or booked
- 73%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Appeals at the tribunal
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of SAPTARSHI MARK, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SAPTARSHI MARK | 100% | 78% | 30% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- SAPTARSHI MARK: covers 19 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAPTARSHI MARK every month.
SAPTARSHI MARK: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 508 – 589 | 82 |
| 1 BHK | 421 – 487 | 35 |
| 1 Room Kitchen | 305 – 308 | 17 |
- Buildings: SAPTARSHI MARK (19 floors, 134 units)
- Land: 821 sq m (about 0.2 acres)
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SAPTARSHI MARK →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SAPTARSHI MARK: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SAPTARSHI MARK
What is the possession date of SAPTARSHI MARK?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SAPTARSHI MARK in Nehru Nagar, Mumbai is 31 March 2027 — 39 months later than 30 December 2023, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SAPTARSHI MARK?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SAPTARSHI MARK's builder has filed on MahaRERA, the official one, is 31 March 2027, already 39 months later than the 30 December 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SAPTARSHI MARK extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SAPTARSHI MARK's builder applied to MahaRERA to extend the completion date 3 times: to 29 December 2024, giving the reason "As per the attachment"; to 29 December 2025, giving the reason "As per attachment"; to 31 March 2027, giving the reason "We are applying order bearing number 40/2022 dated 22nd December 2022 issued by the Maharashtra Real Estate Regulatory Authority(MahaRERA)” that is extension without consent".
What is the RERA number of SAPTARSHI MARK?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SAPTARSHI MARK in Nehru Nagar, Mumbai is P51800017508.
Is SAPTARSHI MARK registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAPTARSHI MARK is registered as P51800017508 and its status is "Registered and active".
What is the construction status of SAPTARSHI MARK?
According to GharKundli's check of MahaRERA records (updated October 2026), SAPTARSHI MARK's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SAPTARSHI MARK is 78% done and internal work 30%. GharKundli's full report compares construction progress with the deadline.
Does SAPTARSHI MARK have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SAPTARSHI MARK safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SAPTARSHI MARK is registered on MahaRERA as P51800017508, its completion date has moved 39 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SAPTARSHI MARK's possession date changes?
The latest dates are on SAPTARSHI MARK's MahaRERA page (P51800017508). GharKundli's Kundli Watch sends a free WhatsApp update on SAPTARSHI MARK every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SAPTARSHI MARK have?
According to GharKundli's check of MahaRERA records (updated October 2026), SAPTARSHI MARK has one building filed: SAPTARSHI MARK with 19 floors and 134 units.
What are the flat sizes (carpet area) in SAPTARSHI MARK?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SAPTARSHI MARK: 2 BHK: 508 to 589 sq ft carpet (82 homes); 1 BHK: 421 to 487 sq ft carpet (35 homes); 1 Room Kitchen: 305 to 308 sq ft carpet (17 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of SAPTARSHI MARK?
According to GharKundli's check of MahaRERA records (updated October 2026), SAPTARSHI MARK stands on 821 sq m of land (about 0.2 acres).
Where can I read reviews of SAPTARSHI MARK?
Google Maps has reviews of SAPTARSHI MARK written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SAPTARSHI MARK?
SAPTARSHI MARK by Saptrishi Realtors is in Nehru Nagar, Mumbai (pincode 400024), near Kurla West, Maharashtra, and is registered on MahaRERA as P51800017508, per GharKundli's check of MahaRERA records.
How many homes are in SAPTARSHI MARK?
According to GharKundli's check of MahaRERA records (updated October 2026), SAPTARSHI MARK has 134 homes in 1 tower registered on MahaRERA, and 73% of them are sold or booked.
When was SAPTARSHI MARK registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SAPTARSHI MARK was registered on MahaRERA on 23 August 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on SAPTARSHI MARK?
No court cases are listed for SAPTARSHI MARK on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of SAPTARSHI MARK?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Saptrishi Realtors, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SAPTARSHI MARK
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400024
- VEER SIDDHANAK CHS LTD
- SAPTARSHI AVALON
- AMBARISH CHS LTD
- ROHA VATIKA-ROHA KUMUD
- RAGHAV PARIJAT
- Ruparel Crest
- SAYBA TULIP
- DTG APEX
Other projects by Saptrishi Realtors
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.