VEER SIDDHANAK CHS LTD
by OM SAI GRIHA NIRMAN PVT LTD · Opp Kurla S.T. Depot, MumbaiAlso near Nehru Nagar, Kurla East, Kurla West
Possession date of VEER SIDDHANAK CHS LTD: 31 December 2026, moved from 1 January 2023 (47 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800015156, and currently active. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about VEER SIDDHANAK CHS LTD?
How the possession date of VEER SIDDHANAK CHS LTD has moved
1 January 2023
Completion date given when the project was registered
31 December 2023
Extended at the builder's request (MahaRERA application EXT51800012545)
Reason the builder gave MahaRERA: “DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 31/12/2023”
31 December 2024
Extended at the builder's request (MahaRERA application EXT51800017852)
Reason the builder gave MahaRERA: “DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 31/12/2024”
31 December 2025
Extended at the builder's request (MahaRERA application EXT51800025269)
Reason the builder gave MahaRERA: “Due to shortage of material and labor not able to complete project please grant us extension till 31/12/2025”
31 December 2026
Extended at the builder's request (MahaRERA application EA31122519177)
Reason the builder gave MahaRERA:
“1) In compliance of a direction by the Building Proposals Department of MCGM to construct an Electric Sub-station on our site premises, due to absence of any other in the vicinity, it took us four months to begin the work after applying to…” Read the full reason
“1) In compliance of a direction by the Building Proposals Department of MCGM to construct an Electric Sub-station on our site premises, due to absence of any other in the vicinity, it took us four months to begin the work after applying to Adani Electricity Mumbai Limited (AEML) for installation of the said Sub-station. The said delay was caused as they unilaterally changed the location of the Sub-station leading to a lot of inconvenience and chaos in accommodating the said instructions. Additionally, AEML appointed several contractors to undertake various ilbs at the proposed Sub-station.…”
Source: VEER SIDDHANAK CHS LTD’s extension records on MahaRERA (P51800015156), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on VEER SIDDHANAK CHS LTD
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800015156
- Status
- Registered and active
- Builder
- OM SAI GRIHA NIRMAN PVT LTD
- Location
- Opp Kurla S.T. Depot, Mumbai · 400024
- Project type
- Residential / Group Housing
- Registered on
- 2 Feb 2018
- Completion date at registration
- January 2023
- Latest completion date
- December 2026
- Delay so far
- 47 months
- Homes
- 39
- Sold or booked
- 82%
- Towers
- 1
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of VEER SIDDHANAK CHS LTD, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| VEER SIDDHANAK CHS LTD | 100% | 100% | 91% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- VEER SIDDHANAK CHS LTD: covers 12 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on VEER SIDDHANAK CHS LTD every month.
VEER SIDDHANAK CHS LTD: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 450 – 645 | 35 |
| Shops | 188 – 2,277 | 6 |
| 1 BHK | 450 – 600 | 3 |
| Other | 547 | 1 |
- Buildings: VEER SIDDHANAK CHS LTD (21 floors, 45 units)
- Car parking: 1 covered
- Land: 1,680 sq m (about 0.4 acres) · sanctioned built-up 9 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of VEER SIDDHANAK CHS LTD →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
VEER SIDDHANAK CHS LTD: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about VEER SIDDHANAK CHS LTD
What is the possession date of VEER SIDDHANAK CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VEER SIDDHANAK CHS LTD in Opp Kurla S.T. Depot, Mumbai is 31 December 2026 — 47 months later than 1 January 2023, the date given at registration.
Is the builder's possession date different from the MahaRERA date for VEER SIDDHANAK CHS LTD?
Builders and listing sites often quote an earlier "target" date for handover. The completion date VEER SIDDHANAK CHS LTD's builder has filed on MahaRERA, the official one, is 31 December 2026, already 47 months later than the 1 January 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of VEER SIDDHANAK CHS LTD extended?
According to GharKundli's check of MahaRERA records (updated October 2026), VEER SIDDHANAK CHS LTD's builder applied to MahaRERA to extend the completion date 4 times: to 31 December 2023, giving the reason "DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION TILL 31/12/2023"; to 31 December 2024, giving the reason "DUE TO COVID-19 AND PERMISSION DELAY THE PROJECT WAS NOT ABLE TO GET COMPLETED ON TIME. WE WOULD LIKE TO REQUEST YOU TO FURTHER GRANT US EXTENSION FOR 31/12/2024"; to 31 December 2025, giving the reason "Due to shortage of material and labor not able to complete project please grant us extension till 31/12/2025"; to 31 December 2026, giving the reason "1) In compliance of a direction by the Building Proposals Department of MCGM to construct an Electric Sub-station on our site premises, due to absence of any other in the vicinity, it took us four months to begin the work after applying to Adani Electricity Mumbai Limited (AEML) for installation of the said Sub-station. The said delay was caused as they unilaterally changed the location of the Sub-station leading to a lot of inconvenience and chaos in accommodating the said instructions. Additionally, AEML appointed several contractors to undertake various ilbs at the proposed Sub-station.…".
What is the RERA number of VEER SIDDHANAK CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of VEER SIDDHANAK CHS LTD in Opp Kurla S.T. Depot, Mumbai is P51800015156.
Is VEER SIDDHANAK CHS LTD registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), VEER SIDDHANAK CHS LTD is registered as P51800015156 and its status is "Registered and active".
What is the construction status of VEER SIDDHANAK CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), VEER SIDDHANAK CHS LTD's status on MahaRERA is "Registered and active". As filed by the builder, slab work on VEER SIDDHANAK CHS LTD is 100% done and internal work 91%. GharKundli's full report compares construction progress with the deadline.
Does VEER SIDDHANAK CHS LTD have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is VEER SIDDHANAK CHS LTD safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), VEER SIDDHANAK CHS LTD is registered on MahaRERA as P51800015156, its completion date has moved 47 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if VEER SIDDHANAK CHS LTD's possession date changes?
The latest dates are on VEER SIDDHANAK CHS LTD's MahaRERA page (P51800015156). GharKundli's Kundli Watch sends a free WhatsApp update on VEER SIDDHANAK CHS LTD every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does VEER SIDDHANAK CHS LTD have?
According to GharKundli's check of MahaRERA records (updated October 2026), VEER SIDDHANAK CHS LTD has one building filed: VEER SIDDHANAK CHS LTD with 21 floors and 45 units.
What are the flat sizes (carpet area) in VEER SIDDHANAK CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for VEER SIDDHANAK CHS LTD: 2 BHK: 450 to 645 sq ft carpet (35 homes); 1 BHK: 450 to 600 sq ft carpet (3 homes); Other: 547 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does VEER SIDDHANAK CHS LTD have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered car parking spaces for VEER SIDDHANAK CHS LTD.
How big is the land of VEER SIDDHANAK CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), VEER SIDDHANAK CHS LTD stands on 1,680 sq m of land (about 0.4 acres), with 9 sq m of sanctioned built-up area.
Where can I read reviews of VEER SIDDHANAK CHS LTD?
Google Maps has reviews of VEER SIDDHANAK CHS LTD written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is VEER SIDDHANAK CHS LTD?
VEER SIDDHANAK CHS LTD by OM SAI GRIHA NIRMAN PVT LTD is in Opp Kurla S.T. Depot, Mumbai (pincode 400024), near Nehru Nagar, Kurla East, Kurla West, Maharashtra, and is registered on MahaRERA as P51800015156, per GharKundli's check of MahaRERA records.
How many homes are in VEER SIDDHANAK CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), VEER SIDDHANAK CHS LTD has 39 homes in 1 tower registered on MahaRERA, and 82% of them are sold or booked.
When was VEER SIDDHANAK CHS LTD registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), VEER SIDDHANAK CHS LTD was registered on MahaRERA on 2 February 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on VEER SIDDHANAK CHS LTD?
No court cases are listed for VEER SIDDHANAK CHS LTD on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of VEER SIDDHANAK CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is OM SAI GRIHA NIRMAN PVT LTD.
Check it yourself on MahaRERA
- How to check the possession date of VEER SIDDHANAK CHS LTD
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in Kurla
- SUDHANSHU HEIGHTS
- Saptashringi
- Jai Arihant
- Kalyan Kutir Co-operative Housing Society Limited
- Heritage Lakeside
- Kanakdhara
- Privilon
- Valentina CHS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.