SUDHANSHU HEIGHTS
by SUDHANSHU INFRASTRUCTURES PVT LTD · Bhandup East, MumbaiAlso near Bhandup West
Possession date of SUDHANSHU HEIGHTS: 31 March 2027, moved from 30 June 2022 (57 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800019314, and currently active. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about SUDHANSHU HEIGHTS?
How the possession date of SUDHANSHU HEIGHTS has moved
30 June 2022
Completion date given when the project was registered
30 June 2023
Extended at the builder's request (MahaRERA application EXT51800012157)
Reason the builder gave MahaRERA:
“Due to Covid-19 lockdown there were labour shortages at site. As the project is a small project and because of lockdown restrictions we couldn't allow labour to stay at site and work therefore we have to brings labour from outsite to work a…” Read the full reason
“Due to Covid-19 lockdown there were labour shortages at site. As the project is a small project and because of lockdown restrictions we couldn't allow labour to stay at site and work therefore we have to brings labour from outsite to work at site. And because of such issues at site the labour were not ready to work and due to which contraction delay took place.”31 March 2027
Extended at the builder's request (MahaRERA application EA30092639013)
Reason the builder gave MahaRERA:
“The current facts of the case are being explained hereunder. We started construction work in full swing. Quality of the construction is our primary preference and therefore we do not compromise with the quality of construction over speed of…” Read the full reason
“The current facts of the case are being explained hereunder. We started construction work in full swing. Quality of the construction is our primary preference and therefore we do not compromise with the quality of construction over speed of the construction. Therefore, as per the given circumstances, the construction work progressed. It may be noted that the construction work of the project is almost complete and internal work. This fact is evident from the Architect Certificate that is Form 1 as on 30/06/2026. The delay was mainly on the account of the delay in completion of the parking to…”
Source: SUDHANSHU HEIGHTS’s extension records on MahaRERA (P51800019314), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SUDHANSHU HEIGHTS
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the March 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800019314
- Status
- Registered and active
- Builder
- SUDHANSHU INFRASTRUCTURES PVT LTD
- Location
- Bhandup East, Mumbai · 400042
- Project type
- Others
- Registered on
- 23 Jan 2019
- Completion date at registration
- June 2022
- Latest completion date
- March 2027
- Delay so far
- 57 months
- Homes
- 43
- Sold or booked
- 100%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 5
Construction progress of SUDHANSHU HEIGHTS, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SUDHANSHU HEIGHTS CO-OP HSG SOC LTD | 100% | 100% | 70% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- SUDHANSHU HEIGHTS CO-OP HSG SOC LTD: covers 12 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SUDHANSHU HEIGHTS every month.
SUDHANSHU HEIGHTS: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 320 – 553 | 23 |
| 2 BHK | 546 – 613 | 19 |
| Shops | 164 – 576 | 7 |
| 1 Room Kitchen | 201 | 1 |
- Buildings: SUDHANSHU HEIGHTS CO-OP HSG SOC LTD (12 floors, 50 units)
- Land: 836 sq m (about 0.2 acres)
The builder’s record and reviews
Sudhanshu Infrastructures has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 38 months); 4 still being built, 1 past the promised date (typically 40 months late); 1 lapsed. 5 complaints on MahaRERA across 3 projects.
Read Google reviews of SUDHANSHU HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SUDHANSHU HEIGHTS: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SUDHANSHU HEIGHTS
What is the possession date of SUDHANSHU HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SUDHANSHU HEIGHTS in Bhandup East, Mumbai is 31 March 2027 — 57 months later than 30 June 2022, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SUDHANSHU HEIGHTS?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SUDHANSHU HEIGHTS's builder has filed on MahaRERA, the official one, is 31 March 2027, already 57 months later than the 30 June 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SUDHANSHU HEIGHTS extended?
According to GharKundli's check of MahaRERA records (updated October 2026), SUDHANSHU HEIGHTS's builder applied to MahaRERA to extend the completion date 2 times: to 30 June 2023, giving the reason "Due to Covid-19 lockdown there were labour shortages at site. As the project is a small project and because of lockdown restrictions we couldn't allow labour to stay at site and work therefore we have to brings labour from outsite to work at site. And because of such issues at site the labour were not ready to work and due to which contraction delay took place."; to 31 March 2027, giving the reason "The current facts of the case are being explained hereunder. We started construction work in full swing. Quality of the construction is our primary preference and therefore we do not compromise with the quality of construction over speed of the construction. Therefore, as per the given circumstances, the construction work progressed. It may be noted that the construction work of the project is almost complete and internal work. This fact is evident from the Architect Certificate that is Form 1 as on 30/06/2026. The delay was mainly on the account of the delay in completion of the parking to…".
What is the RERA number of SUDHANSHU HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SUDHANSHU HEIGHTS in Bhandup East, Mumbai is P51800019314.
Is SUDHANSHU HEIGHTS registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SUDHANSHU HEIGHTS is registered as P51800019314 and its status is "Registered and active".
What is the construction status of SUDHANSHU HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), SUDHANSHU HEIGHTS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SUDHANSHU HEIGHTS CO-OP HSG SOC LTD is 100% done and internal work 70%. GharKundli's full report compares construction progress with the deadline.
Does SUDHANSHU HEIGHTS have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SUDHANSHU HEIGHTS safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), SUDHANSHU HEIGHTS is registered on MahaRERA as P51800019314, its completion date has moved 57 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SUDHANSHU HEIGHTS's possession date changes?
The latest dates are on SUDHANSHU HEIGHTS's MahaRERA page (P51800019314). GharKundli's Kundli Watch sends a free WhatsApp update on SUDHANSHU HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SUDHANSHU HEIGHTS have?
According to GharKundli's check of MahaRERA records (updated October 2026), SUDHANSHU HEIGHTS has one building filed: SUDHANSHU HEIGHTS CO-OP HSG SOC LTD with 12 floors and 50 units.
What are the flat sizes (carpet area) in SUDHANSHU HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SUDHANSHU HEIGHTS: 1 BHK: 320 to 553 sq ft carpet (23 homes); 2 BHK: 546 to 613 sq ft carpet (19 homes); 1 Room Kitchen: 201 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of SUDHANSHU HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), SUDHANSHU HEIGHTS stands on 836 sq m of land (about 0.2 acres).
What is the track record of SUDHANSHU HEIGHTS's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Sudhanshu Infrastructures has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 38 months); 4 still being built, 1 past the promised date (typically 40 months late); 1 lapsed. 5 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SUDHANSHU HEIGHTS?
Google Maps has reviews of SUDHANSHU HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SUDHANSHU HEIGHTS?
SUDHANSHU HEIGHTS by SUDHANSHU INFRASTRUCTURES PVT LTD is in Bhandup East, Mumbai (pincode 400042), near Bhandup West, Maharashtra, and is registered on MahaRERA as P51800019314, per GharKundli's check of MahaRERA records.
How many homes are in SUDHANSHU HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), SUDHANSHU HEIGHTS has 43 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.
When was SUDHANSHU HEIGHTS registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), SUDHANSHU HEIGHTS was registered on MahaRERA on 23 January 2019. GharKundli did not find a title report on the land on file there.
Are there court cases on SUDHANSHU HEIGHTS?
No court cases are listed for SUDHANSHU HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of SUDHANSHU HEIGHTS?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SUDHANSHU INFRASTRUCTURES PVT LTD, which has 5 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SUDHANSHU HEIGHTS
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in pincode 400042
- SOUTHFIELD GRAVITY
- Runwal Bliss - Wing F
- Runwal Avenue Wing - M
- RAJSHREE ASHISH CO-OPERATIVE HOUSING SOCIETY LIMITED
- Shivmangal Residency
- SATRE HAPPYNEST
- Bhandup Siddhivinayak CHS Ltd
- Agadh Sagar Co-Op Housing Society Ltd
Other projects by SUDHANSHU INFRASTRUCTURES PVT LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.