VISHNU BHASKAR CHS LTD
by SUDHANSHU INFRASTRUCTURES PVT LTD · Kanjurmarg East, MumbaiAlso near Kanjur East, Bhandup East, Bhandup West
Possession: VISHNU BHASKAR CHS LTD is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800015748. Status: Completed. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about VISHNU BHASKAR CHS LTD?
How the possession date of VISHNU BHASKAR CHS LTD has moved
10 September 2019
Completion date given when the project was registered
31 August 2020
Extended at the builder's request (MahaRERA application EXT51800003653)
Reason the builder gave MahaRERA:
“Project Vishnu Bhaskar is been Delayed Due to change in Government Policy. i.e. Government had stopped giving TDR on 6 mtr. widening road to those projects Residing with 6.mtr Road. And Without TDR BMC cannot issue further approval of CC fo…” Read the full reason
“Project Vishnu Bhaskar is been Delayed Due to change in Government Policy. i.e. Government had stopped giving TDR on 6 mtr. widening road to those projects Residing with 6.mtr Road. And Without TDR BMC cannot issue further approval of CC for the Work Completion . Due to which we had submitted application for the road extension from 6 mtr to 9.15 mtr.width., and which we received the approval on 8th January 2019 (approval doc attached below)... And the same has been submitted in MCGM, so that further procedure for approval of CC to be done. And still the file is in process with MCGM.... Ther…”15 April 2022
Extended at the builder's request (MahaRERA application EXT51800009481)
Reason the builder gave MahaRERA:
“Project Vishnu Bhaskar is been Delayed Due to change in Government Policy. i.e. Government had stopped giving TDR on 6 mtr. widening road to those projects Residing with 6.mtr Road. And Without TDR BMC cannot issue further approval of CC fo…” Read the full reason
“Project Vishnu Bhaskar is been Delayed Due to change in Government Policy. i.e. Government had stopped giving TDR on 6 mtr. widening road to those projects Residing with 6.mtr Road. And Without TDR BMC cannot issue further approval of CC for the Work Completion . Due to which we had submitted application for the road extension from 6 mtr to 9.15 mtr.width., and which we received the approval on 8th January 2019 (approval doc attached below)... And the same has been submitted in MCGM, so that further procedure for approval of IOD & CC to be done. We received the IOD on Dt: -05/03/2020 and by…”26 March 2024
Extended at the builder's request (MahaRERA application EXT51800027213)
Reason the builder gave MahaRERA: “As per attachment”
Source: VISHNU BHASKAR CHS LTD’s extension records on MahaRERA (P51800015748), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on VISHNU BHASKAR CHS LTD
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the March 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800015748
- Status
- Completed
- Builder
- SUDHANSHU INFRASTRUCTURES PVT LTD
- Location
- Kanjurmarg East, Mumbai · 400042
- Project type
- Residential / Group Housing
- Registered on
- 22 Mar 2018
- Completion date at registration
- September 2019
- Latest completion date
- March 2024
- Delay so far
- 54 months
- Homes
- 24
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 5
Construction progress of VISHNU BHASKAR CHS LTD, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| VISHNU BHASKAR CHS LTD | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on VISHNU BHASKAR CHS LTD every month.
VISHNU BHASKAR CHS LTD: buildings, flats and land, as filed on MahaRERA
- Buildings: VISHNU BHASKAR CHS LTD (8 floors)
- Land: 440 sq m (about 0.1 acres) · sanctioned built-up 382 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Sudhanshu Infrastructures has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 38 months); 4 still being built, 1 past the promised date (typically 40 months late); 1 lapsed. 5 complaints on MahaRERA across 3 projects.
Read Google reviews of VISHNU BHASKAR CHS LTD →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
VISHNU BHASKAR CHS LTD: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about VISHNU BHASKAR CHS LTD
What is the possession date of VISHNU BHASKAR CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for VISHNU BHASKAR CHS LTD in Kanjurmarg East, Mumbai is 26 March 2024 — 54 months later than 10 September 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for VISHNU BHASKAR CHS LTD?
Builders and listing sites often quote an earlier "target" date for handover. The completion date VISHNU BHASKAR CHS LTD's builder has filed on MahaRERA, the official one, is 26 March 2024, already 54 months later than the 10 September 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of VISHNU BHASKAR CHS LTD extended?
According to GharKundli's check of MahaRERA records (updated October 2026), VISHNU BHASKAR CHS LTD's builder applied to MahaRERA to extend the completion date 3 times: to 31 August 2020, giving the reason "Project Vishnu Bhaskar is been Delayed Due to change in Government Policy. i.e. Government had stopped giving TDR on 6 mtr. widening road to those projects Residing with 6.mtr Road. And Without TDR BMC cannot issue further approval of CC for the Work Completion . Due to which we had submitted application for the road extension from 6 mtr to 9.15 mtr.width., and which we received the approval on 8th January 2019 (approval doc attached below)... And the same has been submitted in MCGM, so that further procedure for approval of CC to be done. And still the file is in process with MCGM.... Ther…"; to 15 April 2022, giving the reason "Project Vishnu Bhaskar is been Delayed Due to change in Government Policy. i.e. Government had stopped giving TDR on 6 mtr. widening road to those projects Residing with 6.mtr Road. And Without TDR BMC cannot issue further approval of CC for the Work Completion . Due to which we had submitted application for the road extension from 6 mtr to 9.15 mtr.width., and which we received the approval on 8th January 2019 (approval doc attached below)... And the same has been submitted in MCGM, so that further procedure for approval of IOD & CC to be done. We received the IOD on Dt: -05/03/2020 and by…"; to 26 March 2024, giving the reason "As per attachment".
What is the RERA number of VISHNU BHASKAR CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of VISHNU BHASKAR CHS LTD in Kanjurmarg East, Mumbai is P51800015748.
Is VISHNU BHASKAR CHS LTD registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), VISHNU BHASKAR CHS LTD is registered as P51800015748 and its status is "Completed".
What is the construction status of VISHNU BHASKAR CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), VISHNU BHASKAR CHS LTD's status on MahaRERA is "Completed". As filed by the builder, slab work on VISHNU BHASKAR CHS LTD is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does VISHNU BHASKAR CHS LTD have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is VISHNU BHASKAR CHS LTD safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), VISHNU BHASKAR CHS LTD is registered on MahaRERA as P51800015748, its MahaRERA status is "Completed", its completion date has moved 54 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if VISHNU BHASKAR CHS LTD's possession date changes?
The latest dates are on VISHNU BHASKAR CHS LTD's MahaRERA page (P51800015748). GharKundli's Kundli Watch sends a free WhatsApp update on VISHNU BHASKAR CHS LTD every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does VISHNU BHASKAR CHS LTD have?
According to GharKundli's check of MahaRERA records (updated October 2026), VISHNU BHASKAR CHS LTD has one building filed: VISHNU BHASKAR CHS LTD with 8 floors.
How big is the land of VISHNU BHASKAR CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), VISHNU BHASKAR CHS LTD stands on 440 sq m of land (about 0.1 acres), with 382 sq m of sanctioned built-up area.
What is the track record of VISHNU BHASKAR CHS LTD's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Sudhanshu Infrastructures has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 38 months); 4 still being built, 1 past the promised date (typically 40 months late); 1 lapsed. 5 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of VISHNU BHASKAR CHS LTD?
Google Maps has reviews of VISHNU BHASKAR CHS LTD written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is VISHNU BHASKAR CHS LTD?
VISHNU BHASKAR CHS LTD by SUDHANSHU INFRASTRUCTURES PVT LTD is in Kanjurmarg East, Mumbai (pincode 400042), near Kanjur East, Bhandup East, Bhandup West, Maharashtra, and is registered on MahaRERA as P51800015748, per GharKundli's check of MahaRERA records.
How many homes are in VISHNU BHASKAR CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), VISHNU BHASKAR CHS LTD has 24 homes in 1 tower registered on MahaRERA.
When was VISHNU BHASKAR CHS LTD registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), VISHNU BHASKAR CHS LTD was registered on MahaRERA on 22 March 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on VISHNU BHASKAR CHS LTD?
No court cases are listed for VISHNU BHASKAR CHS LTD on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of VISHNU BHASKAR CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SUDHANSHU INFRASTRUCTURES PVT LTD, which has 5 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of VISHNU BHASKAR CHS LTD
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Kurla
- ARKADE EARTH - HAZEL
- Saptashringi
- SUDHANSHU HEIGHTS
- Jai Arihant
- Kanakdhara
- Privilon
- Heritage Lakeside
- Kalyan Kutir Co-operative Housing Society Limited
Other projects by SUDHANSHU INFRASTRUCTURES PVT LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.