Jai Arihant
by Nakoda Infrastructure (Arihant) · Ghatkopar East, Mumbai 400077Also near Chembur, Tilak Nagar, Panvel
What’s in the report? →Possession date of Jai Arihant (MahaRERA P51800052413): 31 December 2027, moved from 31 December 2026 (12 months later). It has 72 homes (1 BHK and 2 BHK, 435–650 sq ft carpet), 15% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800052413, and currently active.
Source: MahaRERA website — records for P51800052413, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Jai Arihant?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Jai Arihant has moved
31 December 2026
Completion date given when the project was registered
31 December 2027
Extended at the builder's request (MahaRERA application EA10092622501)
Reason the builder gave MahaRERA:
“The delay in completion of project has occurred due to the closure of the PTC scheme for the last six months. Since the scheme has remained closed during this period, we have been unable to process the necessary applications, approvals, and…” Read the full reason
“The delay in completion of project has occurred due to the closure of the PTC scheme for the last six months. Since the scheme has remained closed during this period, we have been unable to process the necessary applications, approvals, and other formalities required for carrying out the further work under the project. As a result, the subsequent project activities could not be initiated or progressed as planned, which has significantly affected the overall project timeline. The delay is therefore primarily attributable to the non-availability/closure of the PTC scheme, which is beyond our…”
Source: Jai Arihant’s extension records on MahaRERA (P51800052413), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Jai Arihant
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800052413
- Status
- Registered and active
- Builder
- Nakoda Infrastructure
- Location
- Ghatkopar East, Mumbai · 400077
- Project type
- Others
- Registered on
- 22 Aug 2023
- Completion date at registration
- December 2026
- Latest completion date
- December 2027
- Delay so far
- 12 months
- Homes
- 72
- Sold or booked
- 15%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Jai Arihant, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Arihant Sankalp Wing A | 100% | 50% | 0% | 0% |
| Arihant Sankalp Wing B | 100% | 50% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Arihant Sankalp Wing A: covers 1 floors
- Arihant Sankalp Wing B: covers 1 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Jai Arihant every 1–2 months.
Jai Arihant: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 1 BHK | 435 | 36 |
| 2 BHK | 583 – 650 | 36 |
| Office Space | 491 – 1,490 | 3 |
- Buildings: Arihant Sankalp Wing A (1 floors, 37 units) · Arihant Sankalp Wing B (1 floors, 38 units)
- Land: 1,442 sq m (about 0.4 acres) · recreational space 220 sq m
- Boundaries filed include: Vidya Bhavan Marg
- Land, as filed: 194A
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Trimurti Construction (a group of 8 linked companies) has 14 projects on MahaRERA since 2017, this one included. Of the 14 GharKundli has checked: 4 finished, all within the promised date; 9 still being built, 4 past the promised date (typically 27 months late); 1 lapsed. 7 complaints on MahaRERA across 4 projects.
Read Google reviews of Jai Arihant →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Jai Arihant: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Jai Arihant
What is the possession date of Jai Arihant?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Jai Arihant in Ghatkopar East, Mumbai is 31 December 2027 — 12 months later than 31 December 2026, the date given at registration.
The date has already moved 12 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Jai Arihant?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Jai Arihant's builder has filed on MahaRERA, the official one, is 31 December 2027, already 12 months later than the 31 December 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Jai Arihant extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Jai Arihant's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "The delay in completion of project has occurred due to the closure of the PTC scheme for the last six months. Since the scheme has remained closed during this period, we have been unable to process the necessary applications, approvals, and other formalities required for carrying out the further work under the project. As a result, the subsequent project activities could not be initiated or progressed as planned, which has significantly affected the overall project timeline. The delay is therefore primarily attributable to the non-availability/closure of the PTC scheme, which is beyond our…".
What is the RERA number of Jai Arihant?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Jai Arihant in Ghatkopar East, Mumbai is P51800052413.
Is Jai Arihant registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Jai Arihant is registered as P51800052413 and its status is "Registered and active".
What is the current construction status of Jai Arihant? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Jai Arihant's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 50% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Jai Arihant have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Jai Arihant safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Jai Arihant is registered on MahaRERA as P51800052413, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Jai Arihant?
Jai Arihant is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Jai Arihant are 435 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Jai Arihant?
For a flat in Jai Arihant (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Jai Arihant received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Jai Arihant is still under construction, with 31 December 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Jai Arihant a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Jai Arihant's planning authority on MahaRERA is MCGM, not the Slum Rehabilitation Authority, so it isn't an SRA scheme, and no flats are filed as rehab flats for existing occupants.
Has Jai Arihant uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Jai Arihant was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Jai Arihant's possession date changes?
The latest dates are on Jai Arihant's MahaRERA page (P51800052413). GharKundli's Kundli Watch sends a free WhatsApp update on Jai Arihant every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Jai Arihant have?
According to GharKundli's check of MahaRERA records (updated October 2026), Jai Arihant has 2 buildings filed: Arihant Sankalp Wing A with 1 floors and 37 units; Arihant Sankalp Wing B with 1 floors and 38 units.
What are the flat sizes (carpet area) in Jai Arihant?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Jai Arihant: 1 BHK: 435 sq ft carpet (36 homes); 2 BHK: 583 to 650 sq ft carpet (36 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Jai Arihant?
According to GharKundli's check of MahaRERA records (updated October 2026), Jai Arihant stands on 1,442 sq m of land (about 0.4 acres) and 220 sq m of recreational open space.
What is the track record of Jai Arihant's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Trimurti Construction (a group of 8 linked companies) has 14 projects on MahaRERA since 2017, this one included. Of the 14 GharKundli has checked: 4 finished, all within the promised date; 9 still being built, 4 past the promised date (typically 27 months late); 1 lapsed. 7 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Jai Arihant?
Google Maps has reviews of Jai Arihant written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Jai Arihant?
Jai Arihant by Nakoda Infrastructure (Arihant) is in Ghatkopar East, Mumbai, pincode 400077 (near Chembur, Tilak Nagar, Panvel), Maharashtra, and is registered on MahaRERA as P51800052413, per GharKundli's check of MahaRERA records. Its boundaries filed there include Vidya Bhavan Marg. Its land is filed as 194A. GharKundli lists all 228 MahaRERA projects in Ghatkopar East (400077).
How many flats are in Jai Arihant, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Jai Arihant has 72 homes in 2 towers registered on MahaRERA, and 15% of them are sold or booked.
When was Jai Arihant registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Jai Arihant was registered on MahaRERA on 22 August 2023. GharKundli did not find a title report on the land on file there.
Does Jai Arihant have any legal issues or court cases?
No court cases are listed for Jai Arihant on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Jai Arihant?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Nakoda Infrastructure, the company Arihant files this project under.
Check it yourself on MahaRERA
- How to check the possession date of Jai Arihant
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Ghatkopar East (400077)
- Terraform Dwarka - Wing D
- Avis Residency
- Omkaar Pride
- Om Shreepal
- Damji Shamji Corporate Square - Wing C
- North Sea Heights (A1) - upto 14th floor
- Manhattan Residency (A4) - upto 14th Floor
- Palatina
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.