Avis Residency
by Avi housing Realtors · Ghatkopar East, Mumbai 400077Also near Ghatkopar Kirol, Chembur, Kurla
What’s in the report? →Possession date of Avis Residency (MahaRERA P51800012791): 30 April 2027, moved from 31 December 2019 (84 months later). It has 61 homes (1 Room Kitchen, 2 BHK and 3 BHK, 331–1090 sq ft carpet), 97% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800012791, and currently active. Its completion date has moved from December 2019 to April 2027: 84 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P51800012791, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Avis Residency?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Avis Residency has moved
31 December 2019
Completion date given when the project was registered
31 August 2022
Extended at the builder's request (MahaRERA application EXT51800010729)
Reason the builder gave MahaRERA:
“The Developer were working promptly to complete the project on or before the due line as undertaken before this Hon’ble Authority. In the year 2018-2019 the building’s brick work completed and the finishing work was under process. In the me…” Read the full reason
“The Developer were working promptly to complete the project on or before the due line as undertaken before this Hon’ble Authority. In the year 2018-2019 the building’s brick work completed and the finishing work was under process. In the meantime some the person concerned with the said development project with intent to malafied intention lodge some false and frivolious criminal as well as civil prosecution there by the developers were suffered huge mental agony and the development work was substantially affected. During the said period due to said criminal and civil litigation the interse…”28 February 2024
Extended at the builder's request (MahaRERA application EXT51800015057)
Reason the builder gave MahaRERA: “The project was delayed due to a number of reason one being the lockdown which slowed down the work, the next reason is that there was delay in getting plans approved from the authorities which caused the project to get delayed”
31 October 2024
Extended at the builder's request (MahaRERA application EXT51800019289)
Reason the builder gave MahaRERA:
“The primary cause of the project delay stemmed from the process of obtaining permissions from the authorities, which consequently postponed the construction of the building. However, a significant portion of the construction work has been c…” Read the full reason
“The primary cause of the project delay stemmed from the process of obtaining permissions from the authorities, which consequently postponed the construction of the building. However, a significant portion of the construction work has been completed, and progress is underway on the parking tower, and it will be finished within the extended deadline.”30 June 2025
Extended at the builder's request (MahaRERA application EXT51800025667)
Reason the builder gave MahaRERA:
“1. Project is nearing to completion 2. Consent of 71.43 % of Allotees uploaded for Extension 3. The Revised Form B is uploaded in Other tab No. 1 and also in the main Application 4. PERT Chart is uploaded in Other Tab No. 2 and also in Othe…” Read the full reason
“1. Project is nearing to completion 2. Consent of 71.43 % of Allotees uploaded for Extension 3. The Revised Form B is uploaded in Other tab No. 1 and also in the main Application 4. PERT Chart is uploaded in Other Tab No. 2 and also in Other Technical Tab of the Main Application 5. Reasons for Delay in project Completion Uploaded in Other Tab No. 3”31 December 2026
Extended at the builder's request (MahaRERA application EA11082622088)
Reason the builder gave MahaRERA:
“The Project is approximately 85% completed. The consent of 54.55% of allottees has been uploaded in support of this extension application. TAB 1 - Format B Uploaded TAB 2 - Form B Uploaded TAB 3 - Declaration for extension TAB 4 - PERT Char…” Read the full reason
“The Project is approximately 85% completed. The consent of 54.55% of allottees has been uploaded in support of this extension application. TAB 1 - Format B Uploaded TAB 2 - Form B Uploaded TAB 3 - Declaration for extension TAB 4 - PERT Chart TAB 5 - Notarised Declaration TAB 6 - FORM 2A Uploaded TAB 7 & 8 - FORM 5 Uploaded TAB 9 to 20 - FORM 1,2 & 3 Uploaded The Project got delayed due to following reasons:- The delay in completion of the project is due to the pending Part Occupancy Certificate (OC) from MCGM and certain correction and rectification works required as per the revised sanctio…”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Avis Residency’s extension records on MahaRERA (P51800012791), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Avis Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800012791
- Status
- Registered and active
- Builder
- Avi housing Realtors
- Location
- Ghatkopar East, Mumbai · 400077
- Project type
- Residential / Group Housing
- Registered on
- 7 Sep 2017
- Completion date at registration
- December 2019
- Latest completion date
- April 2027
- Delay so far
- 84 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 61
- Sold or booked
- 97%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Avis Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Avis Residency | 100% | 95% | 90% | 75% |
Commencement certificate (CC), as filed on MahaRERA
- Avis Residency: covers 18 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Avis Residency every 1–2 months.
Avis Residency: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 780 – 815 | 38 |
| 3 BHK | 930 – 1,090 | 21 |
| Shops | 391 – 1,200 | 2 |
| 1 Room Kitchen | 331 | 2 |
- Buildings: Avis Residency (18 floors, 63 units)
- Land: 1,673 sq m (about 0.4 acres) · sanctioned built-up 4,293 sq m
- Boundaries filed include: R N Narkar marg
- Land, as filed: 222
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Avi Housing (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 78 months late); 1 lapsed. 2 complaints on MahaRERA across 1 project.
Read Google reviews of Avis Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Avis Residency: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Avis Residency
What is the possession date of Avis Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Avis Residency in Ghatkopar East, Mumbai is 30 April 2027 — 84 months later than 31 December 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 84 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Avis Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Avis Residency's builder has filed on MahaRERA, the official one, is 30 April 2027, already 84 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Avis Residency extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Avis Residency's builder applied to MahaRERA to extend the completion date 5 times: to 31 August 2022, giving the reason "The Developer were working promptly to complete the project on or before the due line as undertaken before this Hon’ble Authority. In the year 2018-2019 the building’s brick work completed and the finishing work was under process. In the meantime some the person concerned with the said development project with intent to malafied intention lodge some false and frivolious criminal as well as civil prosecution there by the developers were suffered huge mental agony and the development work was substantially affected. During the said period due to said criminal and civil litigation the interse…"; to 28 February 2024, giving the reason "The project was delayed due to a number of reason one being the lockdown which slowed down the work, the next reason is that there was delay in getting plans approved from the authorities which caused the project to get delayed"; to 31 October 2024, giving the reason "The primary cause of the project delay stemmed from the process of obtaining permissions from the authorities, which consequently postponed the construction of the building. However, a significant portion of the construction work has been completed, and progress is underway on the parking tower, and it will be finished within the extended deadline."; to 30 June 2025, giving the reason "1. Project is nearing to completion 2. Consent of 71.43 % of Allotees uploaded for Extension 3. The Revised Form B is uploaded in Other tab No. 1 and also in the main Application 4. PERT Chart is uploaded in Other Tab No. 2 and also in Other Technical Tab of the Main Application 5. Reasons for Delay in project Completion Uploaded in Other Tab No. 3"; to 31 December 2026, giving the reason "The Project is approximately 85% completed. The consent of 54.55% of allottees has been uploaded in support of this extension application. TAB 1 - Format B Uploaded TAB 2 - Form B Uploaded TAB 3 - Declaration for extension TAB 4 - PERT Chart TAB 5 - Notarised Declaration TAB 6 - FORM 2A Uploaded TAB 7 & 8 - FORM 5 Uploaded TAB 9 to 20 - FORM 1,2 & 3 Uploaded The Project got delayed due to following reasons:- The delay in completion of the project is due to the pending Part Occupancy Certificate (OC) from MCGM and certain correction and rectification works required as per the revised sanctio…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Avis Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Avis Residency in Ghatkopar East, Mumbai is P51800012791.
Is Avis Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Avis Residency is registered as P51800012791 and its status is "Registered and active".
What is the current construction status of Avis Residency? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Avis Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Avis Residency is 95% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.
Does Avis Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Avis Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Avis Residency is registered on MahaRERA as P51800012791, its completion date has moved 84 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Avis Residency?
Avis Residency is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Avis Residency are 331 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Avis Residency?
For a flat in Avis Residency (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Avis Residency received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Avis Residency is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Is Avis Residency a redevelopment or SRA project?
According to GharKundli's check of MahaRERA records (updated October 2026), Avis Residency is a redevelopment: 29 of its flats are set aside for existing occupants (rehab), and the rest are for sale.
Has Avis Residency uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Avis Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Avis Residency's possession date changes?
The latest dates are on Avis Residency's MahaRERA page (P51800012791). GharKundli's Kundli Watch sends a free WhatsApp update on Avis Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Avis Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), Avis Residency has one building filed: Avis Residency with 18 floors and 63 units.
What are the flat sizes (carpet area) in Avis Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Avis Residency: 2 BHK: 780 to 815 sq ft carpet (38 homes); 3 BHK: 930 to 1090 sq ft carpet (21 homes); 1 Room Kitchen: 331 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Avis Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Avis Residency stands on 1,673 sq m of land (about 0.4 acres), with 4,293 sq m of sanctioned built-up area.
What is the track record of Avis Residency's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Avi Housing (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 still being built, 1 past the promised date (typically 78 months late); 1 lapsed. 2 complaints on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
What are the reviews of Avis Residency?
Google Maps has reviews of Avis Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Avis Residency?
Avis Residency by Avi housing Realtors is in Ghatkopar East, Mumbai, pincode 400077 (near Ghatkopar Kirol, Chembur, Kurla), Maharashtra, and is registered on MahaRERA as P51800012791, per GharKundli's check of MahaRERA records. Its boundaries filed there include R N Narkar marg. Its land is filed as 222. GharKundli lists all 228 MahaRERA projects in Ghatkopar East (400077).
How many flats are in Avis Residency, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Avis Residency has 61 homes in 1 tower registered on MahaRERA, and 97% of them are sold or booked.
When was Avis Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Avis Residency was registered on MahaRERA on 7 September 2017. GharKundli did not find a title report on the land on file there.
Does Avis Residency have any legal issues or court cases?
No court cases are listed for Avis Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Avis Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Avi housing Realtors.
Check it yourself on MahaRERA
- How to check the possession date of Avis Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Ghatkopar East (400077)
- Jai Arihant
- Terraform Dwarka - Wing D
- Omkaar Pride
- Palatina
- North Sea Heights (A1) - upto 14th floor
- Om Shreepal
- Manhattan Residency (A4) - upto 14th Floor
- Damji Shamji Corporate Square - Wing C
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.