Damji Shamji Corporate Square - Wing C

by Coronate Constructions (Vinayak) · Ghatkopar East, MumbaiAlso near Ghatkopar West, Pant Nagar, Vile Parle West

Possession date of Damji Shamji Corporate Square - Wing C: 30 December 2026, moved from 30 December 2024 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800025317, and currently active.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Damji Shamji Corporate Square - Wing C?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Damji Shamji Corporate Square - Wing C has moved

  1. 30 December 2024

    Completion date given when the project was registered

  2. 30 December 2025

    Extended at the builder's request (MahaRERA application EXT51800025620)

    Reason the builder gave MahaRERA:
    “We have already obtained Occupation certificate for the said building uptill 9th floor. Extension is only for the 10th floor, being pendency on the completion of layout conditions which is in process. The same pending documentations are ant…” Read the full reason“We have already obtained Occupation certificate for the said building uptill 9th floor. Extension is only for the 10th floor, being pendency on the completion of layout conditions which is in process. The same pending documentations are anticipated to get over at the earliest for successfully obtaining the OCCUPATION CERTIFICATE for the Last Pending Floor.”
  3. 30 December 2026

    Extended at the builder's request (MahaRERA application EA25122518985)

    Reason the builder gave MahaRERA:
    “We have acquired the development rights vide a Development Agreement in respect of the property falling under the purview of the said project. Pursuant thereto, we have completed the construction of our project comprising of 10 floors and h…” Read the full reason“We have acquired the development rights vide a Development Agreement in respect of the property falling under the purview of the said project. Pursuant thereto, we have completed the construction of our project comprising of 10 floors and have obtained the Part Occupation Certificate (for short, “OC”) up to 9 floors. We would also like to further state that premises on the 10th floor in our project are ready for occupation and possession in all respects but however, the OC is yet to be issued due to technical reasons viz. pendency of compliance of layout conditions by the owner of the land.…”

Source: Damji Shamji Corporate Square - Wing C’s extension records on MahaRERA (P51800025317), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Damji Shamji Corporate Square - Wing C

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800025317
Status
Registered and active
Builder
Coronate Constructions
Location
Ghatkopar East, Mumbai · 400075
Project type
Commercial
Registered on
10 Apr 2020
Completion date at registration
December 2024
Latest completion date
December 2026
Delay so far
24 months
Homes
0
Sold or booked
94%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Damji Shamji Corporate Square - Wing C, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Damji Shamji Corporate Square - Wing C100%100%99.67%98.01%

Commencement certificate (CC), as filed on MahaRERA

  • Damji Shamji Corporate Square - Wing C: covers 10 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Damji Shamji Corporate Square - Wing C every month.

Damji Shamji Corporate Square - Wing C: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Office Space154 – 591194
  • Buildings: Damji Shamji Corporate Square - Wing C (13 floors, 194 units)
  • Land: 721 sq m (about 0.2 acres) · sanctioned built-up 2,993 sq m · recreational space 2,653 sq m
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Vinayak Developers (a group of 11 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 25 GharKundli has checked: 8 finished, 6 within the promised date and 2 needed more time (typically 22 months); 14 still being built, 5 past the promised date (typically 18 months late); 3 lapsed. 16 complaints on MahaRERA across 7 projects.

Read Google reviews of Damji Shamji Corporate Square - Wing C →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Damji Shamji Corporate Square - Wing C: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Damji Shamji Corporate Square - Wing C

What is the possession date of Damji Shamji Corporate Square - Wing C?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Damji Shamji Corporate Square - Wing C in Ghatkopar East, Mumbai is 30 December 2026 — 24 months later than 30 December 2024, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Damji Shamji Corporate Square - Wing C?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Damji Shamji Corporate Square - Wing C's builder has filed on MahaRERA, the official one, is 30 December 2026, already 24 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Damji Shamji Corporate Square - Wing C extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Damji Shamji Corporate Square - Wing C's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2025, giving the reason "We have already obtained Occupation certificate for the said building uptill 9th floor. Extension is only for the 10th floor, being pendency on the completion of layout conditions which is in process. The same pending documentations are anticipated to get over at the earliest for successfully obtaining the OCCUPATION CERTIFICATE for the Last Pending Floor."; to 30 December 2026, giving the reason "We have acquired the development rights vide a Development Agreement in respect of the property falling under the purview of the said project. Pursuant thereto, we have completed the construction of our project comprising of 10 floors and have obtained the Part Occupation Certificate (for short, “OC”) up to 9 floors. We would also like to further state that premises on the 10th floor in our project are ready for occupation and possession in all respects but however, the OC is yet to be issued due to technical reasons viz. pendency of compliance of layout conditions by the owner of the land.…".

What is the RERA number of Damji Shamji Corporate Square - Wing C?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Damji Shamji Corporate Square - Wing C in Ghatkopar East, Mumbai is P51800025317.

Is Damji Shamji Corporate Square - Wing C registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Damji Shamji Corporate Square - Wing C is registered as P51800025317 and its status is "Registered and active".

What is the construction status of Damji Shamji Corporate Square - Wing C?

According to GharKundli's check of MahaRERA records (updated October 2026), Damji Shamji Corporate Square - Wing C's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Damji Shamji Corporate Square - Wing C is 100% done and internal work 99.67%. GharKundli's full report compares construction progress with the deadline.

Does Damji Shamji Corporate Square - Wing C have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Damji Shamji Corporate Square - Wing C safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Damji Shamji Corporate Square - Wing C is registered on MahaRERA as P51800025317, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Damji Shamji Corporate Square - Wing C's possession date changes?

The latest dates are on Damji Shamji Corporate Square - Wing C's MahaRERA page (P51800025317). GharKundli's Kundli Watch sends a free WhatsApp update on Damji Shamji Corporate Square - Wing C every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Damji Shamji Corporate Square - Wing C have?

According to GharKundli's check of MahaRERA records (updated October 2026), Damji Shamji Corporate Square - Wing C has one building filed: Damji Shamji Corporate Square - Wing C with 13 floors and 194 units.

How big is the land of Damji Shamji Corporate Square - Wing C?

According to GharKundli's check of MahaRERA records (updated October 2026), Damji Shamji Corporate Square - Wing C stands on 721 sq m of land (about 0.2 acres), with 2,993 sq m of sanctioned built-up area and 2,653 sq m of recreational open space.

What is the track record of Damji Shamji Corporate Square - Wing C's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Vinayak Developers (a group of 11 linked companies) has 25 projects on MahaRERA since 2017, this one included. Of the 25 GharKundli has checked: 8 finished, 6 within the promised date and 2 needed more time (typically 22 months); 14 still being built, 5 past the promised date (typically 18 months late); 3 lapsed. 16 complaints on MahaRERA across 7 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Damji Shamji Corporate Square - Wing C?

Google Maps has reviews of Damji Shamji Corporate Square - Wing C written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Damji Shamji Corporate Square - Wing C?

Damji Shamji Corporate Square - Wing C by Coronate Constructions (Vinayak) is in Ghatkopar East, Mumbai (pincode 400075), near Ghatkopar West, Pant Nagar, Vile Parle West, Maharashtra, and is registered on MahaRERA as P51800025317, per GharKundli's check of MahaRERA records.

How many homes are in Damji Shamji Corporate Square - Wing C?

According to GharKundli's check of MahaRERA records (updated October 2026), Damji Shamji Corporate Square - Wing C has 0 homes in 1 tower registered on MahaRERA, and 94% of them are sold or booked.

When was Damji Shamji Corporate Square - Wing C registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Damji Shamji Corporate Square - Wing C was registered on MahaRERA on 10 April 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on Damji Shamji Corporate Square - Wing C?

No court cases are listed for Damji Shamji Corporate Square - Wing C on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Damji Shamji Corporate Square - Wing C?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Coronate Constructions, the company Vinayak files this project under, which has 1 other project registered on MahaRERA.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in Ghatkopar East

All 133 projects in Ghatkopar East (400075) →

Other projects by Coronate Constructions

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.