SAPTARSHI AVALON

by Saptrishi Realtors · Nehru Nagar Kurla East, MumbaiAlso near Kurla West

Possession date of SAPTARSHI AVALON: 30 April 2027, moved from 30 May 2025 (23 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800021280, and currently active. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about SAPTARSHI AVALON?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of SAPTARSHI AVALON has moved

  1. 30 May 2025

    Completion date given when the project was registered

  2. 30 April 2026

    Extended at the builder's request (MahaRERA application EA16092502606)

    Reason the builder gave MahaRERA:
    “The main reason for the delay is pace of sales being slower than expected and thereby effecting the cash flows of the project. Lower than expected cash flows has in turn effected the pace of construction of the project thereby making it imp…” Read the full reason“The main reason for the delay is pace of sales being slower than expected and thereby effecting the cash flows of the project. Lower than expected cash flows has in turn effected the pace of construction of the project thereby making it impossible to meet the scheduled due date 30/05/2025. In addition to poor cash flows, cost overruns on projects, unexpected expenses, economic downturns are reasons that further contributed the delay. Without the sufficient funds due to poor cash flow, we struggled to meet financial obligations, leading to a downward spiral of financial difficulties. Despite…”
  3. 30 August 2026

    Extended at the builder's request

  4. 30 April 2027

    Extended at the builder's request (MahaRERA application EA18062621419)

    Reason the builder gave MahaRERA:
    “The current facts of the case are being explained hereunder. We started construction work in the full swing. Quality of the construction is our primary preference and therefore we do not compromise with the quality of construction over spee…” Read the full reason“The current facts of the case are being explained hereunder. We started construction work in the full swing. Quality of the construction is our primary preference and therefore we do not compromise with the quality of construction over speed of the construction. Therefore, as per the given circumstances, the construction work progressed. As everybody is aware, Real Estate Industry is facing severe slowdown all across the country and we are no exceptions. It has affected our sales and further our liquidity. Lack of liquidity is affecting project progress which ultimately affecting Sales of t…”

Source: SAPTARSHI AVALON’s extension records on MahaRERA (P51800021280), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on SAPTARSHI AVALON

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800021280
Status
Registered and active
Builder
Saptrishi Realtors
Location
Nehru Nagar Kurla East, Mumbai · 400024
Project type
Residential / Group Housing
Registered on
18 Jun 2019
Completion date at registration
May 2025
Latest completion date
April 2027
Delay so far
23 months
Homes
57
Sold or booked
68%
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of SAPTARSHI AVALON, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
SAPTARSHI AVALON100%70%40%0%

Commencement certificate (CC), as filed on MahaRERA

  • SAPTARSHI AVALON: covers 19 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAPTARSHI AVALON every month.

SAPTARSHI AVALON: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK409 – 43632
2 BHK510 – 54116
3 BHK7729
  • Buildings: SAPTARSHI AVALON (19 floors, 57 units)
  • Land: 699 sq m (about 0.2 acres)
  • Boundaries filed include: SCHOOL

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of SAPTARSHI AVALON →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

SAPTARSHI AVALON: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about SAPTARSHI AVALON

What is the possession date of SAPTARSHI AVALON?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for SAPTARSHI AVALON in Nehru Nagar Kurla East, Mumbai is 30 April 2027 — 23 months later than 30 May 2025, the date given at registration.

Is the builder's possession date different from the MahaRERA date for SAPTARSHI AVALON?

Builders and listing sites often quote an earlier "target" date for handover. The completion date SAPTARSHI AVALON's builder has filed on MahaRERA, the official one, is 30 April 2027, already 23 months later than the 30 May 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of SAPTARSHI AVALON extended?

According to GharKundli's check of MahaRERA records (updated October 2026), SAPTARSHI AVALON's builder applied to MahaRERA to extend the completion date 3 times: to 30 April 2026, giving the reason "The main reason for the delay is pace of sales being slower than expected and thereby effecting the cash flows of the project. Lower than expected cash flows has in turn effected the pace of construction of the project thereby making it impossible to meet the scheduled due date 30/05/2025. In addition to poor cash flows, cost overruns on projects, unexpected expenses, economic downturns are reasons that further contributed the delay. Without the sufficient funds due to poor cash flow, we struggled to meet financial obligations, leading to a downward spiral of financial difficulties. Despite…"; to 30 August 2026; to 30 April 2027, giving the reason "The current facts of the case are being explained hereunder. We started construction work in the full swing. Quality of the construction is our primary preference and therefore we do not compromise with the quality of construction over speed of the construction. Therefore, as per the given circumstances, the construction work progressed. As everybody is aware, Real Estate Industry is facing severe slowdown all across the country and we are no exceptions. It has affected our sales and further our liquidity. Lack of liquidity is affecting project progress which ultimately affecting Sales of t…".

What is the RERA number of SAPTARSHI AVALON?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of SAPTARSHI AVALON in Nehru Nagar Kurla East, Mumbai is P51800021280.

Is SAPTARSHI AVALON registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAPTARSHI AVALON is registered as P51800021280 and its status is "Registered and active".

What is the construction status of SAPTARSHI AVALON?

According to GharKundli's check of MahaRERA records (updated October 2026), SAPTARSHI AVALON's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SAPTARSHI AVALON is 70% done and internal work 40%. GharKundli's full report compares construction progress with the deadline.

Does SAPTARSHI AVALON have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is SAPTARSHI AVALON safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), SAPTARSHI AVALON is registered on MahaRERA as P51800021280, its completion date has moved 23 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if SAPTARSHI AVALON's possession date changes?

The latest dates are on SAPTARSHI AVALON's MahaRERA page (P51800021280). GharKundli's Kundli Watch sends a free WhatsApp update on SAPTARSHI AVALON every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does SAPTARSHI AVALON have?

According to GharKundli's check of MahaRERA records (updated October 2026), SAPTARSHI AVALON has one building filed: SAPTARSHI AVALON with 19 floors and 57 units.

What are the flat sizes (carpet area) in SAPTARSHI AVALON?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for SAPTARSHI AVALON: 1 BHK: 409 to 436 sq ft carpet (32 homes); 2 BHK: 510 to 541 sq ft carpet (16 homes); 3 BHK: 772 sq ft carpet (9 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of SAPTARSHI AVALON?

According to GharKundli's check of MahaRERA records (updated October 2026), SAPTARSHI AVALON stands on 699 sq m of land (about 0.2 acres).

Where can I read reviews of SAPTARSHI AVALON?

Google Maps has reviews of SAPTARSHI AVALON written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is SAPTARSHI AVALON?

SAPTARSHI AVALON by Saptrishi Realtors is in Nehru Nagar Kurla East, Mumbai (pincode 400024), near Kurla West, Maharashtra, and is registered on MahaRERA as P51800021280, per GharKundli's check of MahaRERA records. Its boundaries filed there include SCHOOL.

How many homes are in SAPTARSHI AVALON?

According to GharKundli's check of MahaRERA records (updated October 2026), SAPTARSHI AVALON has 57 homes in 1 tower registered on MahaRERA, and 68% of them are sold or booked.

When was SAPTARSHI AVALON registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), SAPTARSHI AVALON was registered on MahaRERA on 18 June 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on SAPTARSHI AVALON?

No court cases are listed for SAPTARSHI AVALON on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of SAPTARSHI AVALON?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Saptrishi Realtors, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in pincode 400024

All 85 projects in Kurla East (400024) →

Other projects by Saptrishi Realtors

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.