RAGHAV PARIJAT
by RAGHAV Realty Developers · Kurla East, Mumbai
Possession date of RAGHAV PARIJAT: 29 December 2026, moved from 30 December 2025 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800050808, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about RAGHAV PARIJAT?
How the possession date of RAGHAV PARIJAT has moved
30 December 2025
Completion date given when the project was registered
29 December 2026
Extended at the builder's request (MahaRERA application EA18122518736)
Reason the builder gave MahaRERA: “Shortage of labour and construction materials”
Source: RAGHAV PARIJAT’s extension records on MahaRERA (P51800050808), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on RAGHAV PARIJAT
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 3 court cases, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800050808
- Status
- Registered and active
- Builder
- RAGHAV Realty Developers
- Location
- Kurla East, Mumbai · 400024
- Project type
- Residential / Group Housing
- Registered on
- 3 May 2023
- Completion date at registration
- December 2025
- Latest completion date
- December 2026
- Delay so far
- 12 months
- Homes
- 146
- Sold or booked
- 98%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 3
- Title report on file
- Not found
Construction progress of RAGHAV PARIJAT, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| RAGHAV PARIJAT | 100% | 100% | 75% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- RAGHAV PARIJAT: covers 17 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on RAGHAV PARIJAT every month.
RAGHAV PARIJAT: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 393 – 588 | 109 |
| 1 BHK | 393 | 37 |
- Buildings: RAGHAV PARIJAT (21 floors, 146 units)
- Land: 868 sq m (about 0.2 acres) · sanctioned built-up 5,699 sq m
The builder’s record and reviews
Raghav RAJ Builders & Developers (a group of 5 linked companies) has 15 projects on MahaRERA since 2019, this one included. Of the 15 GharKundli has checked: 4 finished, 2 within the promised date and 2 needed more time (typically 12 months); 10 still being built, 1 past the promised date (typically 10 months late); 1 lapsed. 6 complaints on MahaRERA across 4 projects.
Read Google reviews of RAGHAV PARIJAT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
RAGHAV PARIJAT: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about RAGHAV PARIJAT
What is the possession date of RAGHAV PARIJAT?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for RAGHAV PARIJAT in Kurla East, Mumbai is 29 December 2026 — 12 months later than 30 December 2025, the date given at registration.
Is the builder's possession date different from the MahaRERA date for RAGHAV PARIJAT?
Builders and listing sites often quote an earlier "target" date for handover. The completion date RAGHAV PARIJAT's builder has filed on MahaRERA, the official one, is 29 December 2026, already 12 months later than the 30 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of RAGHAV PARIJAT extended?
According to GharKundli's check of MahaRERA records (updated October 2026), RAGHAV PARIJAT's builder applied to MahaRERA to extend the completion date once: to 29 December 2026, giving the reason "Shortage of labour and construction materials".
What is the RERA number of RAGHAV PARIJAT?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of RAGHAV PARIJAT in Kurla East, Mumbai is P51800050808.
Is RAGHAV PARIJAT registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), RAGHAV PARIJAT is registered as P51800050808 and its status is "Registered and active".
What is the construction status of RAGHAV PARIJAT?
According to GharKundli's check of MahaRERA records (updated October 2026), RAGHAV PARIJAT's status on MahaRERA is "Registered and active". As filed by the builder, slab work on RAGHAV PARIJAT is 100% done and internal work 75%. GharKundli's full report compares construction progress with the deadline.
Does RAGHAV PARIJAT have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is RAGHAV PARIJAT safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), RAGHAV PARIJAT is registered on MahaRERA as P51800050808, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if RAGHAV PARIJAT's possession date changes?
The latest dates are on RAGHAV PARIJAT's MahaRERA page (P51800050808). GharKundli's Kundli Watch sends a free WhatsApp update on RAGHAV PARIJAT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does RAGHAV PARIJAT have?
According to GharKundli's check of MahaRERA records (updated October 2026), RAGHAV PARIJAT has one building filed: RAGHAV PARIJAT with 21 floors and 146 units.
What are the flat sizes (carpet area) in RAGHAV PARIJAT?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for RAGHAV PARIJAT: 2 BHK: 393 to 588 sq ft carpet (109 homes); 1 BHK: 393 sq ft carpet (37 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of RAGHAV PARIJAT?
According to GharKundli's check of MahaRERA records (updated October 2026), RAGHAV PARIJAT stands on 868 sq m of land (about 0.2 acres), with 5,699 sq m of sanctioned built-up area.
What is the track record of RAGHAV PARIJAT's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Raghav RAJ Builders & Developers (a group of 5 linked companies) has 15 projects on MahaRERA since 2019, this one included. Of the 15 GharKundli has checked: 4 finished, 2 within the promised date and 2 needed more time (typically 12 months); 10 still being built, 1 past the promised date (typically 10 months late); 1 lapsed. 6 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of RAGHAV PARIJAT?
Google Maps has reviews of RAGHAV PARIJAT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is RAGHAV PARIJAT?
RAGHAV PARIJAT by RAGHAV Realty Developers is in Kurla East, Mumbai (pincode 400024), Maharashtra, and is registered on MahaRERA as P51800050808, per GharKundli's check of MahaRERA records.
How many homes are in RAGHAV PARIJAT?
According to GharKundli's check of MahaRERA records (updated October 2026), RAGHAV PARIJAT has 146 homes in 1 tower registered on MahaRERA, and 98% of them are sold or booked.
When was RAGHAV PARIJAT registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), RAGHAV PARIJAT was registered on MahaRERA on 3 May 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on RAGHAV PARIJAT?
3 court cases are listed for RAGHAV PARIJAT on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of RAGHAV PARIJAT?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RAGHAV Realty Developers.
Check it yourself on MahaRERA
- How to check the possession date of RAGHAV PARIJAT
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in Kurla East
All 85 projects in Kurla East (400024) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.