Corner Stone
by Thalia & Aishwarya Builders (Parsn) · Kurla East, Mumbai 400024Also near Nehru Nagar, Kurla West, Chembur
What’s in the report? →Possession date of Corner Stone (MahaRERA PR1180002502582): 30 April 2032. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under PR1180002502582, and currently active. Its completion date is now April 2032, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: MahaRERA website — records for PR1180002502582, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Corner Stone?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Corner Stone has moved
31 December 2031
Completion date given when the project was registered
30 April 2032
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Corner Stone’s extension records on MahaRERA (PR1180002502582), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Corner Stone
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2032 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PR1180002502582
- Status
- Registered and active
- Builder
- Thalia & Aishwarya Builders
- Location
- Kurla East, Mumbai · 400024
- Project type
- Residential / Group Housing
- Registered on
- 4 Mar 2026
- Completion date at registration
- December 2031
- Latest completion date
- April 2032
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Corner Stone, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| CORNER STONE | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- CORNER STONE: covers Upto Plinth Level
Latest CC order on MahaRERA: dated 11/12/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Corner Stone every 1–2 months.
Corner Stone: buildings, flats and land, as filed on MahaRERA
- Buildings: CORNER STONE (2 floors)
- Land: 1,151 sq m (about 0.3 acres)
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Parsn Construction AND Developers (a group of 4 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 57 months); 6 still being built, 2 past the promised date (typically 6 months late); 2 lapsed. 18 complaints on MahaRERA across 3 projects.
Read Google reviews of Corner Stone →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Corner Stone: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Corner Stone
What is the possession date of Corner Stone?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Corner Stone in Kurla East, Mumbai is 30 April 2032, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Corner Stone?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Corner Stone's builder has filed on MahaRERA, the official one, is 30 April 2032, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Corner Stone?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Corner Stone in Kurla East, Mumbai is PR1180002502582.
Is Corner Stone registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Corner Stone is registered as PR1180002502582 and its status is "Registered and active".
What is the current construction status of Corner Stone? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Corner Stone's status on MahaRERA is "Registered and active". As filed by the builder, slab work on CORNER STONE is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Corner Stone have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Corner Stone safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Corner Stone is registered on MahaRERA as PR1180002502582, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Corner Stone?
Corner Stone is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Corner Stone?
For a flat in Corner Stone (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Corner Stone received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Corner Stone is still under construction, with 30 April 2032 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Corner Stone uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Corner Stone was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Corner Stone's possession date changes?
The latest dates are on Corner Stone's MahaRERA page (PR1180002502582). GharKundli's Kundli Watch sends a free WhatsApp update on Corner Stone every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Corner Stone have?
According to GharKundli's check of MahaRERA records (updated October 2026), Corner Stone has one building filed: CORNER STONE with 2 floors.
How big is the land of Corner Stone?
According to GharKundli's check of MahaRERA records (updated October 2026), Corner Stone stands on 1,151 sq m of land (about 0.3 acres).
What is the track record of Corner Stone's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Parsn Construction AND Developers (a group of 4 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 10 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 57 months); 6 still being built, 2 past the promised date (typically 6 months late); 2 lapsed. 18 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Corner Stone?
Google Maps has reviews of Corner Stone written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Corner Stone?
Corner Stone by Thalia & Aishwarya Builders (Parsn) is in Kurla East, Mumbai, pincode 400024 (near Nehru Nagar, Kurla West, Chembur), Maharashtra, and is registered on MahaRERA as PR1180002502582, per GharKundli's check of MahaRERA records. GharKundli lists all 85 MahaRERA projects in Kurla East (400024).
When was Corner Stone registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Corner Stone was registered on MahaRERA on 4 March 2026. GharKundli did not find a title report on the land on file there.
Does Corner Stone have any legal issues or court cases?
No court cases are listed for Corner Stone on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Corner Stone?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Thalia & Aishwarya Builders, the company Parsn files this project under.
Check it yourself on MahaRERA
- How to check the possession date of Corner Stone
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Kurla East (400024)
All 85 projects in Kurla East (400024) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.