Astha Avana

by Anand Chandanmalji Soni HUF · Nerul Node III, Raigarh

Possession date of Astha Avana: 30 October 2027, moved from 30 June 2026 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000047976, and currently active. Its completion date has moved from June 2026 to October 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Astha Avana?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Astha Avana has moved

  1. 30 June 2026

    Completion date given when the project was registered

  2. 30 June 2027

    Extended at the builder's request (MahaRERA application EA25062621519)

    Reason the builder gave MahaRERA: “There were liquidity issues and delays in funding. Labour and material shortages, along with disruptions in supply chains and workforce availability, are impacting construction timelines.”
  3. 30 October 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Astha Avana’s extension records on MahaRERA (P52000047976), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Astha Avana

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000047976
Status
Registered and active
Builder
Anand Chandanmalji Soni HUF
Location
Nerul Node III, Raigarh · 400706
Project type
Residential / Group Housing
Registered on
2 Dec 2022
Completion date at registration
June 2026
Latest completion date
October 2027
Delay so far
12 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
93
Sold or booked
36%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Astha Avana, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Astha Avana100%100%82.5%30.55%

Commencement certificate (CC), as filed on MahaRERA

  • Astha Avana: covers 17 floors

Latest CC order on MahaRERA: dated 16/09/2025.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Astha Avana every month.

Astha Avana: buildings, flats and land, as filed on MahaRERA

  • Buildings: Astha Avana (17 floors, 109 units)
  • Car parking: 1 covered
  • Land: 2,050 sq m (about 0.5 acres) · sanctioned built-up 2,223 sq m
  • Boundaries filed include: 30 Miter Road

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Astha Avana →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Astha Avana: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Astha Avana

What is the possession date of Astha Avana?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Astha Avana in Nerul Node III, Raigarh is 30 October 2027 — 12 months later than 30 June 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Astha Avana?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Astha Avana's builder has filed on MahaRERA, the official one, is 30 October 2027, already 12 months later than the 30 June 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Astha Avana extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Astha Avana's builder applied to MahaRERA to extend the completion date once: to 30 June 2027, giving the reason "There were liquidity issues and delays in funding. Labour and material shortages, along with disruptions in supply chains and workforce availability, are impacting construction timelines.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Astha Avana?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Astha Avana in Nerul Node III, Raigarh is P52000047976.

Is Astha Avana registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Astha Avana is registered as P52000047976 and its status is "Registered and active".

What is the construction status of Astha Avana?

According to GharKundli's check of MahaRERA records (updated October 2026), Astha Avana's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Astha Avana is 100% done and internal work 82.5%. GharKundli's full report compares construction progress with the deadline.

Does Astha Avana have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Astha Avana safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Astha Avana is registered on MahaRERA as P52000047976, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Astha Avana's possession date changes?

The latest dates are on Astha Avana's MahaRERA page (P52000047976). GharKundli's Kundli Watch sends a free WhatsApp update on Astha Avana every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Astha Avana have?

According to GharKundli's check of MahaRERA records (updated October 2026), Astha Avana has one building filed: Astha Avana with 17 floors and 109 units.

How much parking does Astha Avana have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 1 covered car parking spaces for Astha Avana.

How big is the land of Astha Avana?

According to GharKundli's check of MahaRERA records (updated October 2026), Astha Avana stands on 2,050 sq m of land (about 0.5 acres), with 2,223 sq m of sanctioned built-up area.

Where can I read reviews of Astha Avana?

Google Maps has reviews of Astha Avana written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Astha Avana?

Astha Avana by Anand Chandanmalji Soni HUF is in Nerul Node III, Raigarh (pincode 400706), Maharashtra, and is registered on MahaRERA as P52000047976, per GharKundli's check of MahaRERA records. Its boundaries filed there include 30 Miter Road.

How many homes are in Astha Avana?

According to GharKundli's check of MahaRERA records (updated October 2026), Astha Avana has 93 homes in 1 tower registered on MahaRERA, and 36% of them are sold or booked.

When was Astha Avana registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Astha Avana was registered on MahaRERA on 2 December 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on Astha Avana?

No court cases are listed for Astha Avana on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Astha Avana?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Anand Chandanmalji Soni HUF.

All projects with possession due in 2027 in Thane →

Other projects in pincode 400706

All 172 projects in Nerul (400706) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.