Excellensea Villas Project

by UNICORP REALTY PRIVATE LIMITED · Kolgaon, Raigarh

Possession date of Excellensea Villas Project: 30 December 2026, moved from 30 December 2024 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000050588, and currently active.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Excellensea Villas Project?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Excellensea Villas Project has moved

  1. 30 December 2024

    Completion date given when the project was registered

  2. 30 December 2025

    Extended at the builder's request (MahaRERA application EXT52000025007)

    Reason the builder gave MahaRERA:
    “Due to unavailability of regular supply of material in Alibaug, certain labour issues and heavy monsoon in Alibaug, the work could not be completed within the stipulated time limit, and we are expecting the work to be completed within the n…” Read the full reason“Due to unavailability of regular supply of material in Alibaug, certain labour issues and heavy monsoon in Alibaug, the work could not be completed within the stipulated time limit, and we are expecting the work to be completed within the next 12 months.”
  3. 30 December 2026

    Extended at the builder's request (MahaRERA application EA29122519107)

    Reason the builder gave MahaRERA: “Due to labour issues, the work could not be completed within the stipulated time limit, otherwise all the approvals are in place and we are expecting the work to be completed within next 12 months.”

Source: Excellensea Villas Project’s extension records on MahaRERA (P52000050588), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Excellensea Villas Project

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000050588
Status
Registered and active
Builder
UNICORP REALTY PRIVATE LIMITED
Location
Kolgaon, Raigarh · 402201
Project type
Residential / Group Housing
Registered on
21 Apr 2023
Completion date at registration
December 2024
Latest completion date
December 2026
Delay so far
24 months
Homes
7
Sold or booked
71%
Towers
7
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Excellensea Villas Project, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Villa 1100%100%75%0%
Villa 2100%100%75%0%
Villa 3100%100%75%0%
Villa 4100%100%75%0%
Villa 5100%100%75%0%
Villa 6100%100%75%0%
Villa 7100%100%75%0%

Commencement certificate (CC), as filed on MahaRERA

  • Villa 1: covers 5 floors
  • Villa 2: covers 5 floors
  • Villa 3: covers 5 floors
  • Villa 4: covers 5 floors
  • Villa 5: covers 5 floors
  • Villa 6: covers 5 floors
  • Villa 7: covers 5 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Excellensea Villas Project every month.

Excellensea Villas Project: buildings, flats and land, as filed on MahaRERA

  • Buildings: Villa 1 (5 floors, 1 units) · Villa 2 (5 floors, 1 units) · Villa 3 (5 floors, 1 units) · Villa 4 (5 floors, 1 units) · Villa 5 (5 floors, 1 units) · Villa 6 (5 floors, 1 units) · Villa 7 (5 floors, 1 units)
  • Land: 4,395 sq m (about 1.1 acres) · sanctioned built-up 6,449 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Excellensea Villas Project →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Excellensea Villas Project: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Excellensea Villas Project

What is the possession date of Excellensea Villas Project?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Excellensea Villas Project in Kolgaon, Raigarh is 30 December 2026 — 24 months later than 30 December 2024, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Excellensea Villas Project?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Excellensea Villas Project's builder has filed on MahaRERA, the official one, is 30 December 2026, already 24 months later than the 30 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Excellensea Villas Project extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Excellensea Villas Project's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2025, giving the reason "Due to unavailability of regular supply of material in Alibaug, certain labour issues and heavy monsoon in Alibaug, the work could not be completed within the stipulated time limit, and we are expecting the work to be completed within the next 12 months."; to 30 December 2026, giving the reason "Due to labour issues, the work could not be completed within the stipulated time limit, otherwise all the approvals are in place and we are expecting the work to be completed within next 12 months.".

What is the RERA number of Excellensea Villas Project?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Excellensea Villas Project in Kolgaon, Raigarh is P52000050588.

Is Excellensea Villas Project registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Excellensea Villas Project is registered as P52000050588 and its status is "Registered and active".

What is the construction status of Excellensea Villas Project?

According to GharKundli's check of MahaRERA records (updated October 2026), Excellensea Villas Project's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 7 towers. GharKundli's full report compares construction progress with the deadline.

Does Excellensea Villas Project have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Excellensea Villas Project safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Excellensea Villas Project is registered on MahaRERA as P52000050588, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Excellensea Villas Project's possession date changes?

The latest dates are on Excellensea Villas Project's MahaRERA page (P52000050588). GharKundli's Kundli Watch sends a free WhatsApp update on Excellensea Villas Project every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Excellensea Villas Project have?

According to GharKundli's check of MahaRERA records (updated October 2026), Excellensea Villas Project has 7 buildings filed: Villa 1 with 5 floors and 1 units; Villa 2 with 5 floors and 1 units; Villa 3 with 5 floors and 1 units; Villa 4 with 5 floors and 1 units; Villa 5 with 5 floors and 1 units; Villa 6 with 5 floors and 1 units; and 1 more.

How big is the land of Excellensea Villas Project?

According to GharKundli's check of MahaRERA records (updated October 2026), Excellensea Villas Project stands on 4,395 sq m of land (about 1.1 acres), with 6,449 sq m of sanctioned built-up area.

Where can I read reviews of Excellensea Villas Project?

Google Maps has reviews of Excellensea Villas Project written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Excellensea Villas Project?

Excellensea Villas Project by UNICORP REALTY PRIVATE LIMITED is in Kolgaon, Raigarh (pincode 402201), Maharashtra, and is registered on MahaRERA as P52000050588, per GharKundli's check of MahaRERA records.

How many homes are in Excellensea Villas Project?

According to GharKundli's check of MahaRERA records (updated October 2026), Excellensea Villas Project has 7 homes in 7 towers registered on MahaRERA, and 71% of them are sold or booked.

When was Excellensea Villas Project registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Excellensea Villas Project was registered on MahaRERA on 21 April 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on Excellensea Villas Project?

No court cases are listed for Excellensea Villas Project on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Excellensea Villas Project?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is UNICORP REALTY PRIVATE LIMITED.

All projects with possession due in 2026 in Raigad →

Other projects in Alibag

All 111 projects in Alibag (402201) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.