Rustomjee Summit

by KEYSTONE REALTORS LIMITED (Rustomjee) · Rajendra Nagar, MumbaiAlso near Borivali West, Borivali East, Magathane

Possession date of Rustomjee Summit: 31 December 2027, moved from 31 December 2021 (72 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800003590, and currently active. MahaRERA has issued a regulatory order on this project. 7 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Rustomjee Summit?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Rustomjee Summit has moved

  1. 31 December 2021

    Completion date given when the project was registered

  2. 31 December 2022

    Extended at the builder's request (MahaRERA application EXT51800005724)

    Reason the builder gave MahaRERA: “As there was delay in procuring further permissions required for completing construction of this project, the Promoter needs extension of one years time to complete the said project.”
  3. 30 December 2024

    Extended at the builder's request (MahaRERA application EXT51800018271)

    Reason the builder gave MahaRERA:
    “1. The said Real Estate Project has received part occupation certificate dated 18th August, 2023 with regards to Basement + Ground + 1st to 38th upper floors. Full Occupation Certificate for all floors of the said Real Estate Project partic…” Read the full reason“1. The said Real Estate Project has received part occupation certificate dated 18th August, 2023 with regards to Basement + Ground + 1st to 38th upper floors. Full Occupation Certificate for all floors of the said Real Estate Project particularly occupation certificate for the 39th and 40th floors is yet to be procured owing to the following pre-requisites for the issuance of full Occupation Certificate for the said Real Estate Project insisted upon by MHADA, which are enumerated in the MHADA Consent letter to Occupation Certificate dated 11th August 2023. A) Execution and registration of D…”
  4. 31 December 2027

    Extended at the builder's request (MahaRERA application EA27072621882)

    Reason the builder gave MahaRERA:
    “The Project comprises of Basement + Ground + 1st to 40th upper floors. The Occupation Certificate for all the sanctioned floors have been received except Flat No. 3906 on the 39th Floor and Flat No. 4003 on the 40th Floor. The Occupation Ce…” Read the full reason“The Project comprises of Basement + Ground + 1st to 40th upper floors. The Occupation Certificate for all the sanctioned floors have been received except Flat No. 3906 on the 39th Floor and Flat No. 4003 on the 40th Floor. The Occupation Certificate for the said two Flats has not been issued owing to the condition imposed by Maharashtra Housing and Area Development Authority (“MHADA”) for the amalgamation of the 2 (two) erstwhile societies, being Rajendra Nagar Co-operative Housing Ltd. and Rajendra Nagar Manjunath Co-operative Housing Society Limited (“said Societies”) who along with their…”

Source: Rustomjee Summit’s extension records on MahaRERA (P51800003590), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Rustomjee Summit

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 7 complaints and 8 court cases, and how it ended
  • Construction pace against the December 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800003590
Status
Registered and active
Builder
KEYSTONE REALTORS LIMITED
Location
Rajendra Nagar, Mumbai · 400066
Project type
Residential / Group Housing
Registered on
5 Aug 2017
Completion date at registration
December 2021
Latest completion date
December 2027
Delay so far
72 months
Homes
233
Sold or booked
0%
Towers
1
Complaints on MahaRERA
7
Court cases listed
8
Appeals at the tribunal
5
MahaRERA regulatory orders
1
Title report on file
Not found
Builder's other MahaRERA projects
19

Construction progress of Rustomjee Summit, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Summit100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • Summit: covers 44 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Rustomjee Summit every month.

Rustomjee Summit: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
3 BHK706 – 3,549233

The builder’s record and reviews

Keystone Realtors has 21 projects on MahaRERA since 2017, this one included. Of the 21 GharKundli has checked: 12 finished, all within the promised date; 8 still being built, 1 past the promised date (typically 46 months late); 1 lapsed. 16 complaints on MahaRERA across 4 projects.

Read Google reviews of Rustomjee Summit →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Rustomjee Summit: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Rustomjee Summit

What is the possession date of Rustomjee Summit?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Rustomjee Summit in Rajendra Nagar, Mumbai is 31 December 2027 — 72 months later than 31 December 2021, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Rustomjee Summit?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Rustomjee Summit's builder has filed on MahaRERA, the official one, is 31 December 2027, already 72 months later than the 31 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Rustomjee Summit extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Rustomjee Summit's builder applied to MahaRERA to extend the completion date 3 times: to 31 December 2022, giving the reason "As there was delay in procuring further permissions required for completing construction of this project, the Promoter needs extension of one years time to complete the said project."; to 30 December 2024, giving the reason "1. The said Real Estate Project has received part occupation certificate dated 18th August, 2023 with regards to Basement + Ground + 1st to 38th upper floors. Full Occupation Certificate for all floors of the said Real Estate Project particularly occupation certificate for the 39th and 40th floors is yet to be procured owing to the following pre-requisites for the issuance of full Occupation Certificate for the said Real Estate Project insisted upon by MHADA, which are enumerated in the MHADA Consent letter to Occupation Certificate dated 11th August 2023. A) Execution and registration of D…"; to 31 December 2027, giving the reason "The Project comprises of Basement + Ground + 1st to 40th upper floors. The Occupation Certificate for all the sanctioned floors have been received except Flat No. 3906 on the 39th Floor and Flat No. 4003 on the 40th Floor. The Occupation Certificate for the said two Flats has not been issued owing to the condition imposed by Maharashtra Housing and Area Development Authority (“MHADA”) for the amalgamation of the 2 (two) erstwhile societies, being Rajendra Nagar Co-operative Housing Ltd. and Rajendra Nagar Manjunath Co-operative Housing Society Limited (“said Societies”) who along with their…".

What is the RERA number of Rustomjee Summit?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Rustomjee Summit in Rajendra Nagar, Mumbai is P51800003590.

Is Rustomjee Summit registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Rustomjee Summit is registered as P51800003590 and its status is "Registered and active".

What is the construction status of Rustomjee Summit?

According to GharKundli's check of MahaRERA records (updated October 2026), Rustomjee Summit's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Summit is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Rustomjee Summit have complaints on MahaRERA?

7 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Rustomjee Summit safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Rustomjee Summit is registered on MahaRERA as P51800003590, its completion date has moved 72 months since registration and 7 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Rustomjee Summit's possession date changes?

The latest dates are on Rustomjee Summit's MahaRERA page (P51800003590). GharKundli's Kundli Watch sends a free WhatsApp update on Rustomjee Summit every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Rustomjee Summit have?

According to GharKundli's check of MahaRERA records (updated October 2026), Rustomjee Summit has one building filed: Summit with 44 floors and 233 units.

What are the flat sizes (carpet area) in Rustomjee Summit?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Rustomjee Summit: 3 BHK: 706 to 3549 sq ft carpet (233 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Rustomjee Summit?

According to GharKundli's check of MahaRERA records (updated October 2026), Rustomjee Summit stands on 1,111 sq m of land (about 0.3 acres), with 21,284 sq m of sanctioned built-up area and 706 sq m of recreational open space.

What is the track record of Rustomjee Summit's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Keystone Realtors has 21 projects on MahaRERA since 2017, this one included. Of the 21 GharKundli has checked: 12 finished, all within the promised date; 8 still being built, 1 past the promised date (typically 46 months late); 1 lapsed. 16 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Rustomjee Summit?

Google Maps has reviews of Rustomjee Summit written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 7 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Rustomjee Summit?

Rustomjee Summit by KEYSTONE REALTORS LIMITED (Rustomjee) is in Rajendra Nagar, Mumbai (pincode 400066), near Borivali West, Borivali East, Magathane, Maharashtra, and is registered on MahaRERA as P51800003590, per GharKundli's check of MahaRERA records.

How many homes are in Rustomjee Summit?

According to GharKundli's check of MahaRERA records (updated October 2026), Rustomjee Summit has 233 homes in 1 tower registered on MahaRERA, and 0% of them are sold or booked.

When was Rustomjee Summit registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Rustomjee Summit was registered on MahaRERA on 5 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Rustomjee Summit?

8 court cases are listed for Rustomjee Summit on MahaRERA, and 5 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Rustomjee Summit?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KEYSTONE REALTORS LIMITED, the company Rustomjee files this project under, which has 19 other projects registered on MahaRERA.

All projects with possession due in 2027 in Mumbai Suburban →

Other projects in pincode 400066

All 228 projects in Borivali East (400066) →

Other projects by KEYSTONE REALTORS LIMITED

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.