DINDOSHI SAI SADAN CHS LTD
by SANJAY BAJRANGLAL AGARWAL · Dindoshi, MumbaiAlso near malad east, Kurar Village, Goregaon East
Possession date of DINDOSHI SAI SADAN CHS LTD: 30 December 2022, moved from 30 June 2021 (18 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P51800011217. Status: Lapsed (registration period ended). 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (December 2022) has passed.
What do you want to know about DINDOSHI SAI SADAN CHS LTD?
How the possession date of DINDOSHI SAI SADAN CHS LTD has moved
30 June 2021
Completion date given when the project was registered
30 June 2022
Extended at the builder's request (MahaRERA application EXT51800010677)
Reason the builder gave MahaRERA: “DUE TO APPOINTMENT OF COURT RECEIVER BY MUMBAI HIGH COURT”
30 December 2022
Revised completion date on MahaRERA
Source: DINDOSHI SAI SADAN CHS LTD’s extension records on MahaRERA (P51800011217), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on DINDOSHI SAI SADAN CHS LTD
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the December 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800011217
- Status
- Lapsed (registration period ended)
- Builder
- SANJAY BAJRANGLAL AGARWAL
- Location
- Dindoshi, Mumbai · 400097
- Project type
- Others
- Registered on
- 31 Aug 2017
- Completion date at registration
- June 2021
- Latest completion date
- December 2022
- Delay so far
- 18 months
- Homes
- 76
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of DINDOSHI SAI SADAN CHS LTD, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| DINDOSHI SAI SADAN CHS LTD | 1% | 23% | 4% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on DINDOSHI SAI SADAN CHS LTD every month.
DINDOSHI SAI SADAN CHS LTD: buildings, flats and land, as filed on MahaRERA
- Buildings: DINDOSHI SAI SADAN CHS LTD (24 floors)
- Land: 1,055 sq m (about 0.3 acres) · sanctioned built-up 1,055 sq m
- Boundaries filed include: FILM CITY ROAD
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of DINDOSHI SAI SADAN CHS LTD →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
DINDOSHI SAI SADAN CHS LTD: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about DINDOSHI SAI SADAN CHS LTD
What is the possession date of DINDOSHI SAI SADAN CHS LTD?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for DINDOSHI SAI SADAN CHS LTD in Dindoshi, Mumbai is 30 December 2022 — 18 months later than 30 June 2021, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for DINDOSHI SAI SADAN CHS LTD?
Builders and listing sites often quote an earlier "target" date for handover. The completion date DINDOSHI SAI SADAN CHS LTD's builder has filed on MahaRERA, the official one, is 30 December 2022, already 18 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of DINDOSHI SAI SADAN CHS LTD extended?
According to GharKundli's check of MahaRERA records (updated November 2026), DINDOSHI SAI SADAN CHS LTD's builder applied to MahaRERA to extend the completion date once: to 30 June 2022, giving the reason "DUE TO APPOINTMENT OF COURT RECEIVER BY MUMBAI HIGH COURT".
What is the RERA number of DINDOSHI SAI SADAN CHS LTD?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of DINDOSHI SAI SADAN CHS LTD in Dindoshi, Mumbai is P51800011217.
Is DINDOSHI SAI SADAN CHS LTD registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), DINDOSHI SAI SADAN CHS LTD is registered as P51800011217 and its status is "Lapsed (registration period ended)".
What is the construction status of DINDOSHI SAI SADAN CHS LTD?
According to GharKundli's check of MahaRERA records (updated November 2026), DINDOSHI SAI SADAN CHS LTD's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on DINDOSHI SAI SADAN CHS LTD is 23% done and internal work 4%. GharKundli's full report compares construction progress with the deadline.
Does DINDOSHI SAI SADAN CHS LTD have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is DINDOSHI SAI SADAN CHS LTD safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), DINDOSHI SAI SADAN CHS LTD is registered on MahaRERA as P51800011217, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 18 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if DINDOSHI SAI SADAN CHS LTD's possession date changes?
The latest dates are on DINDOSHI SAI SADAN CHS LTD's MahaRERA page (P51800011217). GharKundli's Kundli Watch sends a free WhatsApp update on DINDOSHI SAI SADAN CHS LTD every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does DINDOSHI SAI SADAN CHS LTD have?
According to GharKundli's check of MahaRERA records (updated November 2026), DINDOSHI SAI SADAN CHS LTD has one building filed: DINDOSHI SAI SADAN CHS LTD with 24 floors.
How big is the land of DINDOSHI SAI SADAN CHS LTD?
According to GharKundli's check of MahaRERA records (updated November 2026), DINDOSHI SAI SADAN CHS LTD stands on 1,055 sq m of land (about 0.3 acres), with 1,055 sq m of sanctioned built-up area.
Where can I read reviews of DINDOSHI SAI SADAN CHS LTD?
Google Maps has reviews of DINDOSHI SAI SADAN CHS LTD written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is DINDOSHI SAI SADAN CHS LTD?
DINDOSHI SAI SADAN CHS LTD by SANJAY BAJRANGLAL AGARWAL is in Dindoshi, Mumbai (pincode 400097), near malad east, Kurar Village, Goregaon East, Maharashtra, and is registered on MahaRERA as P51800011217, per GharKundli's check of MahaRERA records. Its boundaries filed there include FILM CITY ROAD.
How many homes are in DINDOSHI SAI SADAN CHS LTD?
According to GharKundli's check of MahaRERA records (updated November 2026), DINDOSHI SAI SADAN CHS LTD has 76 homes in 1 tower registered on MahaRERA.
When was DINDOSHI SAI SADAN CHS LTD registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), DINDOSHI SAI SADAN CHS LTD was registered on MahaRERA on 31 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on DINDOSHI SAI SADAN CHS LTD?
No court cases are listed for DINDOSHI SAI SADAN CHS LTD on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of DINDOSHI SAI SADAN CHS LTD?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SANJAY BAJRANGLAL AGARWAL.
Check it yourself on MahaRERA
- How to check the possession date of DINDOSHI SAI SADAN CHS LTD
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Borivali
- Blue Zone
- Applaud-38
- SAFFRONWOODS CHSL
- L&T Realty Ahana Tower B
- AVIRAHI ELEGANCE
- L&T Realty Ahana Tower A
- PARSHURAM HEIGHTS
- MARU MANSION
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.