Mulund Narayan Pushp CHS LTD
by Greenfield Developers · Wagle Estate, Mumbai 400080Also near Mulund West, Bhandup West, Mulund East
What’s in the report? →Possession date of Mulund Narayan Pushp CHS LTD (MahaRERA P51800003710): 31 August 2024, moved from 31 July 2019 (61 months later), and it has already passed. It has 21 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800003710. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P51800003710, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (August 2024) has passed.
What do you want to know about Mulund Narayan Pushp CHS LTD?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Mulund Narayan Pushp CHS LTD has moved
31 July 2019
Completion date given when the project was registered
30 July 2020
Extended at the builder's request (MahaRERA application EXT51800002386)
Reason the builder gave MahaRERA:
“The New DCPR was introduced on 8th May 2018. It was supposed to be functional from 23rd June, 2018. Now for reason unexplained, they had delayed the implementation date to 1st September, 2018 as stated in Corrigendum to Notice No. TPB-4317/…” Read the full reason
“The New DCPR was introduced on 8th May 2018. It was supposed to be functional from 23rd June, 2018. Now for reason unexplained, they had delayed the implementation date to 1st September, 2018 as stated in Corrigendum to Notice No. TPB-4317/629/CR-118/2017/EP/UD-11, dt. 22/06/2018.The said DCPR-2034 was implemented on 01/09/2018 without EP’s (Excluded Part) only on 13/11/2018 was the DCPR fully implemented including all EP’s we submitted our file on 21/02/2019 under regulation 33 (7) B of DCPR-2034,but was rejected on 01/03/2019 due to policy not being finalized. The regulation 33 (7) B allo…”31 May 2022
Extended at the builder's request (MahaRERA application EXT51800009635)
Reason the builder gave MahaRERA: “Extension Applied as per Circular No. 28-2021 Dated: 08-03-2021”
31 March 2023
Extended at the builder's request (MahaRERA application EXT51800012938)
Reason the builder gave MahaRERA: “We are in the process of applying OC.”
30 September 2023
Extended at the builder's request (MahaRERA application EXT51800015170)
Reason the builder gave MahaRERA: “APPLICATION FOR EXTENSION ATTACHED”
30 January 2024
Extended at the builder's request (MahaRERA application EXT51800017700)
Reason the builder gave MahaRERA: “FINISHING WORK IS GOING ON .”
31 August 2024
Extended at the builder's request (MahaRERA application EXT51800019156)
Reason the builder gave MahaRERA: “Building Construction work is done just Final and finishing work is pending.”
Source: Mulund Narayan Pushp CHS LTD’s extension records on MahaRERA (P51800003710), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Mulund Narayan Pushp CHS LTD
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the August 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800003710
- Status
- Lapsed (registration period ended)
- Builder
- Greenfield Developers
- Location
- Wagle Estate, Mumbai · 400080
- Project type
- Residential / Group Housing
- Registered on
- 6 Aug 2017
- Completion date at registration
- July 2019
- Latest completion date
- August 2024
- Delay so far
- 61 months
- Homes
- 21
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Mulund Narayan Pushp CHS LTD, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| MULUND NARAYAN PUSHP CHS LTD | 100% | 100% | 95% | 60% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Mulund Narayan Pushp CHS LTD every 1–2 months.
Mulund Narayan Pushp CHS LTD: buildings, flats and land, as filed on MahaRERA
- Buildings: MULUND NARAYAN PUSHP CHS LTD (9 floors)
- Land: 836 sq m (about 0.2 acres) · sanctioned built-up 1,246 sq m
- Land, as filed: CTS NO 1055 A
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Mulund Narayan Pushp CHS LTD →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Mulund Narayan Pushp CHS LTD: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Mulund Narayan Pushp CHS LTD
What is the possession date of Mulund Narayan Pushp CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Mulund Narayan Pushp CHS LTD in Wagle Estate, Mumbai is 31 August 2024 — 61 months later than 31 July 2019, the date given at registration. That date has already passed.
The date has already moved 61 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Mulund Narayan Pushp CHS LTD?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Mulund Narayan Pushp CHS LTD's builder has filed on MahaRERA, the official one, is 31 August 2024, already 61 months later than the 31 July 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Mulund Narayan Pushp CHS LTD extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Mulund Narayan Pushp CHS LTD's builder applied to MahaRERA to extend the completion date 6 times: to 30 July 2020, giving the reason "The New DCPR was introduced on 8th May 2018. It was supposed to be functional from 23rd June, 2018. Now for reason unexplained, they had delayed the implementation date to 1st September, 2018 as stated in Corrigendum to Notice No. TPB-4317/629/CR-118/2017/EP/UD-11, dt. 22/06/2018.The said DCPR-2034 was implemented on 01/09/2018 without EP’s (Excluded Part) only on 13/11/2018 was the DCPR fully implemented including all EP’s we submitted our file on 21/02/2019 under regulation 33 (7) B of DCPR-2034,but was rejected on 01/03/2019 due to policy not being finalized. The regulation 33 (7) B allo…"; to 31 May 2022, giving the reason "Extension Applied as per Circular No. 28-2021 Dated: 08-03-2021"; to 31 March 2023, giving the reason "We are in the process of applying OC."; to 30 September 2023, giving the reason "APPLICATION FOR EXTENSION ATTACHED"; to 30 January 2024, giving the reason "FINISHING WORK IS GOING ON ."; to 31 August 2024, giving the reason "Building Construction work is done just Final and finishing work is pending.".
What is the RERA number of Mulund Narayan Pushp CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Mulund Narayan Pushp CHS LTD in Wagle Estate, Mumbai is P51800003710.
Is Mulund Narayan Pushp CHS LTD registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Mulund Narayan Pushp CHS LTD is registered as P51800003710 and its status is "Lapsed (registration period ended)".
What is the current construction status of Mulund Narayan Pushp CHS LTD? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Mulund Narayan Pushp CHS LTD's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on MULUND NARAYAN PUSHP CHS LTD is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.
Does Mulund Narayan Pushp CHS LTD have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Mulund Narayan Pushp CHS LTD safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Mulund Narayan Pushp CHS LTD is registered on MahaRERA as P51800003710, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 61 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Mulund Narayan Pushp CHS LTD?
Mulund Narayan Pushp CHS LTD isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Mulund Narayan Pushp CHS LTD?
For a flat in Mulund Narayan Pushp CHS LTD (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator
Has Mulund Narayan Pushp CHS LTD received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Mulund Narayan Pushp CHS LTD isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 August 2024 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Mulund Narayan Pushp CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), Mulund Narayan Pushp CHS LTD's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 August 2024) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Mulund Narayan Pushp CHS LTD uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Mulund Narayan Pushp CHS LTD was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Mulund Narayan Pushp CHS LTD's possession date changes?
The latest dates are on Mulund Narayan Pushp CHS LTD's MahaRERA page (P51800003710). GharKundli's Kundli Watch sends a free WhatsApp update on Mulund Narayan Pushp CHS LTD every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Mulund Narayan Pushp CHS LTD have?
According to GharKundli's check of MahaRERA records (updated October 2026), Mulund Narayan Pushp CHS LTD has one building filed: MULUND NARAYAN PUSHP CHS LTD with 9 floors.
How big is the land of Mulund Narayan Pushp CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), Mulund Narayan Pushp CHS LTD stands on 836 sq m of land (about 0.2 acres), with 1,246 sq m of sanctioned built-up area.
What are the reviews of Mulund Narayan Pushp CHS LTD?
Google Maps has reviews of Mulund Narayan Pushp CHS LTD written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Mulund Narayan Pushp CHS LTD?
Mulund Narayan Pushp CHS LTD by Greenfield Developers is in Wagle Estate, Mumbai, pincode 400080 (near Mulund West, Bhandup West, Mulund East), Maharashtra, and is registered on MahaRERA as P51800003710, per GharKundli's check of MahaRERA records. Its land is filed as CTS NO 1055 A. GharKundli lists all 303 MahaRERA projects in Mulund West (400080).
How many flats are in Mulund Narayan Pushp CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), Mulund Narayan Pushp CHS LTD has 21 homes in 1 tower registered on MahaRERA.
When was Mulund Narayan Pushp CHS LTD registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Mulund Narayan Pushp CHS LTD was registered on MahaRERA on 6 August 2017. GharKundli did not find a title report on the land on file there.
Does Mulund Narayan Pushp CHS LTD have any legal issues or court cases?
No court cases are listed for Mulund Narayan Pushp CHS LTD on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Mulund Narayan Pushp CHS LTD?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Greenfield Developers, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Mulund Narayan Pushp CHS LTD
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Mulund West (400080)
- L&T Realty Vayam Tower 3
- L&T Realty Vayam Tower 4
- Eos It Park
- Dosti 604
- Sunrise Corporate Park Phase II
- Sunrise Corporate Park- Phase I
- O22 Business Park
- Aikyam It Park
Other projects by Greenfield Developers
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.