by Lak & Hanware Realty LLP · Kevanipada, MumbaiAlso near Andheri West, Jogeshwari East, Andheri East

Possession date of The Residency: 30 October 2026, moved from 30 June 2021 (60 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800004331, and currently active. Its completion date has moved from June 2021 to October 2026: 60 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 4 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (October 2026) has passed.

What do you want to know about The Residency?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of The Residency has moved

  1. 30 June 2021

    Completion date given when the project was registered

  2. 31 December 2021

    Extended at the builder's request (MahaRERA application EXT51800009750)

    Reason the builder gave MahaRERA: “DUE TO THE COVID-19 PANDEMIC LOCKDOWN.”
  3. 30 June 2023

    Extended at the builder's request (MahaRERA application EXT51800012191)

    Reason the builder gave MahaRERA:
    “100% construction of Sale building "B" & "C" is completed. Also for Rehab building construction work up to 14th floor has been completed. Also we have applied for OC for "B' & "C" wing. We have received CC up to 18th Floor for rehab buildin…” Read the full reason“100% construction of Sale building "B" & "C" is completed. Also for Rehab building construction work up to 14th floor has been completed. Also we have applied for OC for "B' & "C" wing. We have received CC up to 18th Floor for rehab building - A Wing. For completing the pending work we need extension.”
  4. 30 June 2024

    Extended at the builder's request (MahaRERA application EXT51800016605)

    Reason the builder gave MahaRERA:
    “A fire NOC is pending due to a tree that lies between the center of the upcoming road, Road has already been handed over to BMC, but because of Tree Fire Department not issuing NOC. And because of the Absence of NOC, Now for Additional Five…” Read the full reason“A fire NOC is pending due to a tree that lies between the center of the upcoming road, Road has already been handed over to BMC, but because of Tree Fire Department not issuing NOC. And because of the Absence of NOC, Now for Additional Five floors above the Rehab building are pending to be Constructed, For this purpose we require MahaRERA Extension.”
  5. 30 June 2025

    Extended at the builder's request (MahaRERA application EXT51800022950)

    Reason the builder gave MahaRERA:
    “We like to inform you that we have completed 100% of sale building “B” & “C” wings & Rehab Building “A” wing up to 14th Floor and we have received Part O.C. till 10th Floor. We have received Full C.C. up to 18th Floor of A-wing which will b…” Read the full reason“We like to inform you that we have completed 100% of sale building “B” & “C” wings & Rehab Building “A” wing up to 14th Floor and we have received Part O.C. till 10th Floor. We have received Full C.C. up to 18th Floor of A-wing which will be completed by June-2025. Therefore, kindly give extension for “A” wing only from 15th floor to 18th Floor till June-2025.”
  6. 30 June 2026

    Extended at the builder's request (MahaRERA application EA10072502038)

    Reason the builder gave MahaRERA:
    “Due to the Eligibility (Patrata) issues concerning three hutments located on the road, the Commencement Certificate (C.C.) for the extension of 19th and 20th floors (Sale Components) of Wing ‘A’ (Which is a rehab building up to the 14th flo…” Read the full reason“Due to the Eligibility (Patrata) issues concerning three hutments located on the road, the Commencement Certificate (C.C.) for the extension of 19th and 20th floors (Sale Components) of Wing ‘A’ (Which is a rehab building up to the 14th floor) was delayed. We have already received LOI – SRA/ENG/2799/KW/PL/LOI. dtd- 21.07.2025 and anticipate receiving the C.C. for the 19th and 20th floors by 30th July 2025. The extension is required only for the 19th & 20th floors of Wing ‘A’.”
  7. 30 October 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: The Residency’s extension records on MahaRERA (P51800004331), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on The Residency

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 4 complaints, and how it ended
  • Construction pace against the October 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800004331
Status
Registered and active
Builder
Lak & Hanware Realty LLP
Location
Kevanipada, Mumbai · 400102
Project type
Residential / Group Housing
Registered on
9 Aug 2017
Completion date at registration
June 2021
Latest completion date
October 2026
Delay so far
60 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
130
Sold or booked
85%
Towers
1
Complaints on MahaRERA
4
Court cases listed
0
Title report on file
Not found

Construction progress of The Residency, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
The Residency100%100%90%75%

Commencement certificate (CC), as filed on MahaRERA

  • The Residency: covers 20 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on The Residency every month.

The Residency: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK312 – 487127
2 BHK4533

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of The Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

The Residency: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about The Residency

What is the possession date of The Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for The Residency in Kevanipada, Mumbai is 30 October 2026 — 60 months later than 30 June 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

Is the builder's possession date different from the MahaRERA date for The Residency?

Builders and listing sites often quote an earlier "target" date for handover. The completion date The Residency's builder has filed on MahaRERA, the official one, is 30 October 2026, already 60 months later than the 30 June 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of The Residency extended?

According to GharKundli's check of MahaRERA records (updated October 2026), The Residency's builder applied to MahaRERA to extend the completion date 5 times: to 31 December 2021, giving the reason "DUE TO THE COVID-19 PANDEMIC LOCKDOWN."; to 30 June 2023, giving the reason "100% construction of Sale building "B" & "C" is completed. Also for Rehab building construction work up to 14th floor has been completed. Also we have applied for OC for "B' & "C" wing. We have received CC up to 18th Floor for rehab building - A Wing. For completing the pending work we need extension."; to 30 June 2024, giving the reason "A fire NOC is pending due to a tree that lies between the center of the upcoming road, Road has already been handed over to BMC, but because of Tree Fire Department not issuing NOC. And because of the Absence of NOC, Now for Additional Five floors above the Rehab building are pending to be Constructed, For this purpose we require MahaRERA Extension."; to 30 June 2025, giving the reason "We like to inform you that we have completed 100% of sale building “B” & “C” wings & Rehab Building “A” wing up to 14th Floor and we have received Part O.C. till 10th Floor. We have received Full C.C. up to 18th Floor of A-wing which will be completed by June-2025. Therefore, kindly give extension for “A” wing only from 15th floor to 18th Floor till June-2025."; to 30 June 2026, giving the reason "Due to the Eligibility (Patrata) issues concerning three hutments located on the road, the Commencement Certificate (C.C.) for the extension of 19th and 20th floors (Sale Components) of Wing ‘A’ (Which is a rehab building up to the 14th floor) was delayed. We have already received LOI – SRA/ENG/2799/KW/PL/LOI. dtd- 21.07.2025 and anticipate receiving the C.C. for the 19th and 20th floors by 30th July 2025. The extension is required only for the 19th & 20th floors of Wing ‘A’.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of The Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of The Residency in Kevanipada, Mumbai is P51800004331.

Is The Residency registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), The Residency is registered as P51800004331 and its status is "Registered and active".

What is the construction status of The Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), The Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work on The Residency is 100% done and internal work 90%. GharKundli's full report compares construction progress with the deadline.

Does The Residency have complaints on MahaRERA?

4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is The Residency safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), The Residency is registered on MahaRERA as P51800004331, its completion date has moved 60 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if The Residency's possession date changes?

The latest dates are on The Residency's MahaRERA page (P51800004331). GharKundli's Kundli Watch sends a free WhatsApp update on The Residency every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does The Residency have?

According to GharKundli's check of MahaRERA records (updated October 2026), The Residency has one building filed: The Residency with 26 floors and 130 units.

What are the flat sizes (carpet area) in The Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for The Residency: 1 BHK: 312 to 487 sq ft carpet (127 homes); 2 BHK: 453 sq ft carpet (3 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How much parking does The Residency have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 56 covered car parking spaces for The Residency.

How big is the land of The Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), The Residency stands on 1,811 sq m of land (about 0.4 acres), with 6,194 sq m of sanctioned built-up area.

Where can I read reviews of The Residency?

Google Maps has reviews of The Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is The Residency?

The Residency by Lak & Hanware Realty LLP is in Kevanipada, Mumbai (pincode 400102), near Andheri West, Jogeshwari East, Andheri East, Maharashtra, and is registered on MahaRERA as P51800004331, per GharKundli's check of MahaRERA records.

How many homes are in The Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), The Residency has 130 homes in 1 tower registered on MahaRERA, and 85% of them are sold or booked.

When was The Residency registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), The Residency was registered on MahaRERA on 9 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on The Residency?

No court cases are listed for The Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of The Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Lak & Hanware Realty LLP.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in Andheri

All 116 projects in Jogeshwari West (400102) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.