Shikhar Palms
by Millennium Group · Villeage Chavane, Raigarh
Possession date of Shikhar Palms: 30 April 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under PM1270002502739, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Shikhar Palms?
How the possession date of Shikhar Palms has moved
31 December 2027
Completion date given when the project was registered
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Shikhar Palms’s extension records on MahaRERA (PM1270002502739), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Shikhar Palms
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- PM1270002502739
- Status
- Registered and active
- Builder
- Millennium Group
- Location
- Villeage Chavane, Raigarh · 410207
- Project type
- Mixed
- Registered on
- 12 Mar 2026
- Completion date at registration
- December 2027
- Latest completion date
- April 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 55
- Sold or booked
- 10%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 7
Construction progress of Shikhar Palms, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Shikhar Palm | 0% | 0% | 0% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Shikhar Palm: covers 8 floors
Latest CC order on MahaRERA: dated 15/05/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Shikhar Palms every month.
Shikhar Palms: buildings, flats and land, as filed on MahaRERA
- Buildings: Shikhar Palm (8 floors, 69 units)
- Car parking: 12 covered, 20 open
- Land: 1,750 sq m (about 0.4 acres) · sanctioned built-up 3,706 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Shikhar Palms →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Shikhar Palms: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Shikhar Palms
What is the possession date of Shikhar Palms?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Shikhar Palms in Villeage Chavane, Raigarh is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Shikhar Palms?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Shikhar Palms's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Shikhar Palms?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Shikhar Palms in Villeage Chavane, Raigarh is PM1270002502739.
Is Shikhar Palms registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shikhar Palms is registered as PM1270002502739 and its status is "Registered and active".
What is the construction status of Shikhar Palms?
According to GharKundli's check of MahaRERA records (updated October 2026), Shikhar Palms's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Shikhar Palm is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Shikhar Palms have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Shikhar Palms safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Shikhar Palms is registered on MahaRERA as PM1270002502739, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Shikhar Palms's possession date changes?
The latest dates are on Shikhar Palms's MahaRERA page (PM1270002502739). GharKundli's Kundli Watch sends a free WhatsApp update on Shikhar Palms every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Shikhar Palms have?
According to GharKundli's check of MahaRERA records (updated October 2026), Shikhar Palms has one building filed: Shikhar Palm with 8 floors and 69 units.
How much parking does Shikhar Palms have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 12 covered and 20 open car parking spaces for Shikhar Palms.
How big is the land of Shikhar Palms?
According to GharKundli's check of MahaRERA records (updated October 2026), Shikhar Palms stands on 1,750 sq m of land (about 0.4 acres), with 3,706 sq m of sanctioned built-up area.
Where can I read reviews of Shikhar Palms?
Google Maps has reviews of Shikhar Palms written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Shikhar Palms?
Shikhar Palms by Millennium Group is in Villeage Chavane, Raigarh (pincode 410207), Maharashtra, and is registered on MahaRERA as PM1270002502739, per GharKundli's check of MahaRERA records.
How many homes are in Shikhar Palms?
According to GharKundli's check of MahaRERA records (updated October 2026), Shikhar Palms has 55 homes in 1 tower registered on MahaRERA, and 10% of them are sold or booked.
When was Shikhar Palms registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Shikhar Palms was registered on MahaRERA on 12 March 2026. GharKundli did not find a title report on the land on file there.
Are there court cases on Shikhar Palms?
No court cases are listed for Shikhar Palms on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Shikhar Palms?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Millennium Group, which has 7 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Shikhar Palms
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Raigad →
Other projects in Panvel
- PRAKASH TOWER
- SAI SIDDHI MADHUBAN
- Sai Nilay
- Shivesh Mahavir
- Crystal Co-Operative Housing Society Limited
- Indiabulls Park 2
- Indiabulls Park 1
- Indiabulls Park 4
Other projects by Millennium Group
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.