Hill Shire - Phase 1
by Guardian Promoters & Developers Private Limited · Wagholi, Pune 412207
What’s in the report? →Possession date of Hill Shire - Phase 1 (MahaRERA P52100001572): 30 June 2022, moved from 31 December 2019 (30 months later), and it has already passed. It has 20 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100001572. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P52100001572, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (June 2022) has passed.
What do you want to know about Hill Shire - Phase 1?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Hill Shire - Phase 1 has moved
31 December 2019
Completion date given when the project was registered
30 December 2020
Extended at the builder's request (MahaRERA application EXT52100005874)
Reason the builder gave MahaRERA: “Delay in sanction”
30 June 2022
Extended at the builder's request (MahaRERA application EXT52100010453)
Reason the builder gave MahaRERA: “Due to Covid-19 and lockdown.”
Source: Hill Shire - Phase 1’s extension records on MahaRERA (P52100001572), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Hill Shire - Phase 1
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100001572
- Status
- Lapsed (registration period ended)
- Builder
- Guardian Promoters & Developers Private Limited
- Location
- Wagholi, Pune · 412207
- Project type
- Residential / Group Housing
- Registered on
- 29 Jul 2017
- Completion date at registration
- December 2019
- Latest completion date
- June 2022
- Delay so far
- 30 months
- Homes
- 20
- Towers
- 5
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 4
Construction progress of Hill Shire - Phase 1, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A | 100% | 100% | 100% | 90% |
| B | 100% | 100% | 100% | 90% |
| C | 100% | 100% | 100% | 90% |
| D | 100% | 100% | 100% | 90% |
| E | 100% | 100% | 100% | 90% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Hill Shire - Phase 1 every 1–2 months.
Hill Shire - Phase 1: buildings, flats and land, as filed on MahaRERA
- Buildings: A (14 floors) · B (14 floors) · C (14 floors) · D (14 floors) · E (14 floors)
- Land: 1,000 sq m (about 0.2 acres) · sanctioned built-up 464 sq m
- Land, as filed: Gat No 866/1/2P and 866/3
- Map: Get directions
The builder’s record and reviews
Guardian Promoters & Developers (a group of 3 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 9 months); 4 still being built, 4 past the promised date (typically 29 months late); 3 lapsed. 40 complaints on MahaRERA across 5 projects.
Read Google reviews of Hill Shire - Phase 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Hill Shire - Phase 1: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Hill Shire - Phase 1
What is the possession date of Hill Shire - Phase 1?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Hill Shire - Phase 1 in Wagholi, Pune is 30 June 2022 — 30 months later than 31 December 2019, the date given at registration. That date has already passed.
The date has already moved 30 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Hill Shire - Phase 1?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Hill Shire - Phase 1's builder has filed on MahaRERA, the official one, is 30 June 2022, already 30 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Hill Shire - Phase 1 extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Hill Shire - Phase 1's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2020, giving the reason "Delay in sanction"; to 30 June 2022, giving the reason "Due to Covid-19 and lockdown.".
What is the RERA number of Hill Shire - Phase 1?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Hill Shire - Phase 1 in Wagholi, Pune is P52100001572.
Is Hill Shire - Phase 1 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Hill Shire - Phase 1 is registered as P52100001572 and its status is "Lapsed (registration period ended)".
What is the current construction status of Hill Shire - Phase 1? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Hill Shire - Phase 1's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 5 towers. GharKundli's full report compares construction progress with the deadline.
Does Hill Shire - Phase 1 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Hill Shire - Phase 1 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Hill Shire - Phase 1 is registered on MahaRERA as P52100001572, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 30 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Hill Shire - Phase 1?
Hill Shire - Phase 1 isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Hill Shire - Phase 1?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Hill Shire - Phase 1: gharkundli.com/tools/property-cost-calculator
Has Hill Shire - Phase 1 received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Hill Shire - Phase 1 isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 June 2022 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Hill Shire - Phase 1?
According to GharKundli's check of MahaRERA records (updated November 2026), Hill Shire - Phase 1's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 June 2022) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Hill Shire - Phase 1 uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Hill Shire - Phase 1 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Hill Shire - Phase 1's possession date changes?
The latest dates are on Hill Shire - Phase 1's MahaRERA page (P52100001572). GharKundli's Kundli Watch sends a free WhatsApp update on Hill Shire - Phase 1 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Hill Shire - Phase 1 have?
According to GharKundli's check of MahaRERA records (updated November 2026), Hill Shire - Phase 1 has 5 buildings filed: A with 14 floors; B with 14 floors; C with 14 floors; D with 14 floors; E with 14 floors.
How big is the land of Hill Shire - Phase 1?
According to GharKundli's check of MahaRERA records (updated November 2026), Hill Shire - Phase 1 stands on 1,000 sq m of land (about 0.2 acres), with 464 sq m of sanctioned built-up area.
What is the track record of Hill Shire - Phase 1's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Guardian Promoters & Developers (a group of 3 linked companies) has 10 projects on MahaRERA since 2017, this one included. Of the 9 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 9 months); 4 still being built, 4 past the promised date (typically 29 months late); 3 lapsed. 40 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Hill Shire - Phase 1?
Google Maps has reviews of Hill Shire - Phase 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Hill Shire - Phase 1?
Hill Shire - Phase 1 by Guardian Promoters & Developers Private Limited is in Wagholi, Pune, pincode 412207, Maharashtra, and is registered on MahaRERA as P52100001572, per GharKundli's check of MahaRERA records. Its land is filed as Gat No 866/1/2P and 866/3. GharKundli lists all 379 MahaRERA projects in Wagholi (412207).
How many flats are in Hill Shire - Phase 1?
According to GharKundli's check of MahaRERA records (updated November 2026), Hill Shire - Phase 1 has 20 homes in 5 towers registered on MahaRERA.
When was Hill Shire - Phase 1 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Hill Shire - Phase 1 was registered on MahaRERA on 29 July 2017. GharKundli did not find a title report on the land on file there.
Does Hill Shire - Phase 1 have any legal issues or court cases?
No court cases are listed for Hill Shire - Phase 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Hill Shire - Phase 1?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Guardian Promoters & Developers Private Limited, which has 4 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Hill Shire - Phase 1
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Wagholi (412207)
- Springshire
- AP4 Tech Park
- V Axis
- Equa - Wing C
- Equa - Wing D and E
- Aura Sai Krishnangan-Building A
- 31 Palma Drive Phase 2
- Happy Homes Amenity Building
Other projects by Guardian Promoters & Developers Private Limited
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.