The Prestige Avenue
by SIX ACES REALTORS LLP · Pashan, Pune 411021Also near Baner, Sus, Jai Bhavani Nagar
What’s in the report? →Possession date of The Prestige Avenue (MahaRERA P52100001856): 30 June 2022, moved from 31 December 2019 (30 months later), and it has already passed. It has 82 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100001856. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P52100001856, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (June 2022) has passed.
What do you want to know about The Prestige Avenue?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of The Prestige Avenue has moved
31 December 2019
Completion date given when the project was registered
30 December 2020
Extended at the builder's request (MahaRERA application EXT52100005108)
Reason the builder gave MahaRERA: “WE GOT FINAL COMMENCEMENT CERTIFICATE IN THE MONTH OF JULY 2019”
31 December 2021
Extended at the builder's request (MahaRERA application EXT52100010230)
Reason the builder gave MahaRERA: “Work has been completed 95% & the possession date will be on or before 31/12/2021 The current competition date delayed because of covide-19 pendamic issue.”
30 June 2022
Revised completion date on MahaRERA
Source: The Prestige Avenue’s extension records on MahaRERA (P52100001856), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on The Prestige Avenue
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100001856
- Status
- Lapsed (registration period ended)
- Builder
- SIX ACES REALTORS LLP
- Location
- Pashan, Pune · 411021
- Project type
- Others
- Registered on
- 29 Jul 2017
- Completion date at registration
- December 2019
- Latest completion date
- June 2022
- Delay so far
- 30 months
- Homes
- 82
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of The Prestige Avenue, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| THE PRESTIGE AVENUE | 100% | 60% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on The Prestige Avenue every 1–2 months.
The Prestige Avenue: buildings, flats and land, as filed on MahaRERA
- Buildings: THE PRESTIGE AVENUE (15 floors)
- Land: 3,133 sq m (about 0.8 acres) · sanctioned built-up 5,639 sq m
- Boundaries filed include: BANER PASHAN LINK ROAD
- Land, as filed: 130/2
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of The Prestige Avenue →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
The Prestige Avenue: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about The Prestige Avenue
What is the possession date of The Prestige Avenue?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for The Prestige Avenue in Pashan, Pune is 30 June 2022 — 30 months later than 31 December 2019, the date given at registration. That date has already passed.
The date has already moved 30 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for The Prestige Avenue?
Builders and listing sites often quote an earlier "target" date for handover. The completion date The Prestige Avenue's builder has filed on MahaRERA, the official one, is 30 June 2022, already 30 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of The Prestige Avenue extended?
According to GharKundli's check of MahaRERA records (updated November 2026), The Prestige Avenue's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2020, giving the reason "WE GOT FINAL COMMENCEMENT CERTIFICATE IN THE MONTH OF JULY 2019"; to 31 December 2021, giving the reason "Work has been completed 95% & the possession date will be on or before 31/12/2021 The current competition date delayed because of covide-19 pendamic issue.".
What is the RERA number of The Prestige Avenue?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of The Prestige Avenue in Pashan, Pune is P52100001856.
Is The Prestige Avenue registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), The Prestige Avenue is registered as P52100001856 and its status is "Lapsed (registration period ended)".
What is the current construction status of The Prestige Avenue? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), The Prestige Avenue's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on THE PRESTIGE AVENUE is 60% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does The Prestige Avenue have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is The Prestige Avenue safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), The Prestige Avenue is registered on MahaRERA as P52100001856, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 30 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in The Prestige Avenue?
The Prestige Avenue isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in The Prestige Avenue?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in The Prestige Avenue: gharkundli.com/tools/property-cost-calculator
Has The Prestige Avenue received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), The Prestige Avenue isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 June 2022 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for The Prestige Avenue?
According to GharKundli's check of MahaRERA records (updated November 2026), The Prestige Avenue's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 June 2022) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has The Prestige Avenue uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for The Prestige Avenue was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if The Prestige Avenue's possession date changes?
The latest dates are on The Prestige Avenue's MahaRERA page (P52100001856). GharKundli's Kundli Watch sends a free WhatsApp update on The Prestige Avenue every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does The Prestige Avenue have?
According to GharKundli's check of MahaRERA records (updated November 2026), The Prestige Avenue has one building filed: THE PRESTIGE AVENUE with 15 floors.
How big is the land of The Prestige Avenue?
According to GharKundli's check of MahaRERA records (updated November 2026), The Prestige Avenue stands on 3,133 sq m of land (about 0.8 acres), with 5,639 sq m of sanctioned built-up area.
What are the reviews of The Prestige Avenue?
Google Maps has reviews of The Prestige Avenue written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of The Prestige Avenue?
The Prestige Avenue by SIX ACES REALTORS LLP is in Pashan, Pune, pincode 411021 (near Baner, Sus, Jai Bhavani Nagar), Maharashtra, and is registered on MahaRERA as P52100001856, per GharKundli's check of MahaRERA records. Its boundaries filed there include BANER PASHAN LINK ROAD. Its land is filed as 130/2. GharKundli lists all 332 MahaRERA projects in Armament (411021).
How many flats are in The Prestige Avenue?
According to GharKundli's check of MahaRERA records (updated November 2026), The Prestige Avenue has 82 homes in 1 tower registered on MahaRERA.
When was The Prestige Avenue registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), The Prestige Avenue was registered on MahaRERA on 29 July 2017. GharKundli did not find a title report on the land on file there.
Does The Prestige Avenue have any legal issues or court cases?
No court cases are listed for The Prestige Avenue on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of The Prestige Avenue?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SIX ACES REALTORS LLP.
Check it yourself on MahaRERA
- How to check the possession date of The Prestige Avenue
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Armament (411021)
- Samruddhi Wing D
- Whispering Wind Phase III
- Sangharsa Apartment Building F
- Yash Residency Phase 2 “A Wing”
- Sus Business Centre
- The Lords Part 1
- Sahadeo Polaris
- Vekatesh Ganga
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.