Nakashtra Anagn- A
by MAHESH RAJARAM SAWANT · Mulshi, Pune 412111Also near Urawade
What’s in the report? →Possession date of Nakashtra Anagn- A (MahaRERA P52100013567): 30 June 2022, moved from 31 January 2021 (17 months later), and it has already passed. It has 95 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100013567. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P52100013567, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (June 2022) has passed.
What do you want to know about Nakashtra Anagn- A?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Nakashtra Anagn- A has moved
31 January 2021
Completion date given when the project was registered
1 July 2021
Extended at the builder's request (MahaRERA application EXT52100009012)
Reason the builder gave MahaRERA: “Covid 19 Impact on Labour strength.”
31 December 2021
Extended at the builder's request (MahaRERA application EXT52100010417)
Reason the builder gave MahaRERA: “Covid 19 2nd wave- 2nd Lockdown Impact on Labour strength & Material Shortage .”
30 June 2022
Revised completion date on MahaRERA
Source: Nakashtra Anagn- A’s extension records on MahaRERA (P52100013567), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Nakashtra Anagn- A
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100013567
- Status
- Lapsed (registration period ended)
- Builder
- MAHESH RAJARAM SAWANT
- Location
- Mulshi, Pune · 412111
- Project type
- Residential / Group Housing
- Registered on
- 13 Oct 2017
- Completion date at registration
- January 2021
- Latest completion date
- June 2022
- Delay so far
- 17 months
- Homes
- 95
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Nakashtra Anagn- A, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Nakashtra Anagn- A every 1–2 months.
Nakashtra Anagn- A: buildings, flats and land, as filed on MahaRERA
- Buildings: A (25 floors)
- Land: 4,590 sq m (about 1.1 acres) · sanctioned built-up 4,590 sq m · recreational space 1,471 sq m
- Land, as filed: 299,301,302
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Mahesh Rajaram Sawant (a group of 2 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA.
Read Google reviews of Nakashtra Anagn- A →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Nakashtra Anagn- A: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Nakashtra Anagn- A
What is the possession date of Nakashtra Anagn- A?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Nakashtra Anagn- A in Mulshi, Pune is 30 June 2022 — 17 months later than 31 January 2021, the date given at registration. That date has already passed.
The date has already moved 17 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Nakashtra Anagn- A?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Nakashtra Anagn- A's builder has filed on MahaRERA, the official one, is 30 June 2022, already 17 months later than the 31 January 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Nakashtra Anagn- A extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Nakashtra Anagn- A's builder applied to MahaRERA to extend the completion date 2 times: to 1 July 2021, giving the reason "Covid 19 Impact on Labour strength."; to 31 December 2021, giving the reason "Covid 19 2nd wave- 2nd Lockdown Impact on Labour strength & Material Shortage .".
What is the RERA number of Nakashtra Anagn- A?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Nakashtra Anagn- A in Mulshi, Pune is P52100013567.
Is Nakashtra Anagn- A registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Nakashtra Anagn- A is registered as P52100013567 and its status is "Lapsed (registration period ended)".
What is the current construction status of Nakashtra Anagn- A? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Nakashtra Anagn- A's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on A is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Nakashtra Anagn- A have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Nakashtra Anagn- A safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Nakashtra Anagn- A is registered on MahaRERA as P52100013567, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 17 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Nakashtra Anagn- A?
Nakashtra Anagn- A isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Nakashtra Anagn- A?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Nakashtra Anagn- A: gharkundli.com/tools/property-cost-calculator
Has Nakashtra Anagn- A received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Nakashtra Anagn- A isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 June 2022 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Nakashtra Anagn- A?
According to GharKundli's check of MahaRERA records (updated November 2026), Nakashtra Anagn- A's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 June 2022) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Nakashtra Anagn- A uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Nakashtra Anagn- A was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Nakashtra Anagn- A's possession date changes?
The latest dates are on Nakashtra Anagn- A's MahaRERA page (P52100013567). GharKundli's Kundli Watch sends a free WhatsApp update on Nakashtra Anagn- A every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Nakashtra Anagn- A have?
According to GharKundli's check of MahaRERA records (updated November 2026), Nakashtra Anagn- A has one building filed: A with 25 floors.
How big is the land of Nakashtra Anagn- A?
According to GharKundli's check of MahaRERA records (updated November 2026), Nakashtra Anagn- A stands on 4,590 sq m of land (about 1.1 acres), with 4,590 sq m of sanctioned built-up area and 1,471 sq m of recreational open space.
What is the track record of Nakashtra Anagn- A's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Mahesh Rajaram Sawant (a group of 2 linked companies) has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 1 finished, all within the promised date; 2 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Nakashtra Anagn- A?
Google Maps has reviews of Nakashtra Anagn- A written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Nakashtra Anagn- A?
Nakashtra Anagn- A by MAHESH RAJARAM SAWANT is in Mulshi, Pune, pincode 412111 (near Urawade), Maharashtra, and is registered on MahaRERA as P52100013567, per GharKundli's check of MahaRERA records. Its land is filed as 299,301,302.
How many flats are in Nakashtra Anagn- A?
According to GharKundli's check of MahaRERA records (updated November 2026), Nakashtra Anagn- A has 95 homes in 1 tower registered on MahaRERA.
When was Nakashtra Anagn- A registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Nakashtra Anagn- A was registered on MahaRERA on 13 October 2017. GharKundli did not find a title report on the land on file there.
Does Nakashtra Anagn- A have any legal issues or court cases?
No court cases are listed for Nakashtra Anagn- A on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Nakashtra Anagn- A?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is MAHESH RAJARAM SAWANT, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Nakashtra Anagn- A
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Mulshi
Other projects by MAHESH RAJARAM SAWANT
All Pune projects with no pincode on MahaRERA →
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.