by NEW TOWN LEASING AND FINANCE PVT LTD · Pradhikaran, Pune 411044Also near Ravet, Panshet, P.C.N.TRegistered on MahaRERA as “NTLF ISTA”

What’s in the report? →

Possession date of Town NTLF Ista (MahaRERA P52100006863): 31 January 2020, moved from 31 January 2019 (12 months later), and it has already passed. It has 17 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100006863. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P52100006863, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (January 2020) has passed.

What do you want to know about Town NTLF Ista?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Town NTLF Ista has moved

  1. 31 January 2019

    Completion date given when the project was registered

  2. 31 January 2020

    Extended at the builder's request (MahaRERA application EXT52100001327)

    Reason the builder gave MahaRERA: “PROJECT IS EXTENDED DATE BECAUSE REVISED THE PLAN”

Source: Town NTLF Ista’s extension records on MahaRERA (P52100006863), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Town NTLF Ista

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the January 2020 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100006863
Status
Lapsed (registration period ended)
Builder
NEW TOWN LEASING AND FINANCE PVT LTD
Location
Pradhikaran, Pune · 411044
Project type
Residential / Group Housing
Registered on
16 Aug 2017
Completion date at registration
January 2019
Latest completion date
January 2020
Delay so far
12 months
Homes
17
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Town NTLF Ista, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
NTLF ISTA100%5%55%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Town NTLF Ista every 1–2 months.

Town NTLF Ista: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Town NTLF Ista →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Town NTLF Ista: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Town NTLF Ista

What is the possession date of Town NTLF Ista?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Town NTLF Ista in Pradhikaran, Pune is 31 January 2020 — 12 months later than 31 January 2019, the date given at registration. That date has already passed.

The date has already moved 12 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Town NTLF Ista?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Town NTLF Ista's builder has filed on MahaRERA, the official one, is 31 January 2020, already 12 months later than the 31 January 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Town NTLF Ista extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Town NTLF Ista's builder applied to MahaRERA to extend the completion date once: to 31 January 2020, giving the reason "PROJECT IS EXTENDED DATE BECAUSE REVISED THE PLAN".

What is the RERA number of Town NTLF Ista?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Town NTLF Ista in Pradhikaran, Pune is P52100006863.

Is Town NTLF Ista registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Town NTLF Ista is registered as P52100006863 and its status is "Lapsed (registration period ended)".

What is the current construction status of Town NTLF Ista? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Town NTLF Ista's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on NTLF ISTA is 5% done and internal work 55%. GharKundli's full report compares construction progress with the deadline.

Does Town NTLF Ista have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Town NTLF Ista safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Town NTLF Ista is registered on MahaRERA as P52100006863, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Town NTLF Ista?

Town NTLF Ista isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Town NTLF Ista?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Town NTLF Ista: gharkundli.com/tools/property-cost-calculator

Has Town NTLF Ista received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Town NTLF Ista isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 January 2020 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Town NTLF Ista?

According to GharKundli's check of MahaRERA records (updated November 2026), Town NTLF Ista's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 January 2020) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Town NTLF Ista uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Town NTLF Ista was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Town NTLF Ista's possession date changes?

The latest dates are on Town NTLF Ista's MahaRERA page (P52100006863). GharKundli's Kundli Watch sends a free WhatsApp update on Town NTLF Ista every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Town NTLF Ista have?

According to GharKundli's check of MahaRERA records (updated November 2026), Town NTLF Ista has one building filed: NTLF ISTA with 6 floors.

How big is the land of Town NTLF Ista?

According to GharKundli's check of MahaRERA records (updated November 2026), Town NTLF Ista stands on 1,461 sq m of land (about 0.4 acres), with 12,655 sq m of sanctioned built-up area and 1,234 sq m of recreational open space.

What are the reviews of Town NTLF Ista?

Google Maps has reviews of Town NTLF Ista written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Town NTLF Ista?

Town NTLF Ista by NEW TOWN LEASING AND FINANCE PVT LTD is in Pradhikaran, Pune, pincode 411044 (near Ravet, Panshet, P.C.N.T), Maharashtra, and is registered on MahaRERA as P52100006863, per GharKundli's check of MahaRERA records. Its land is filed as SERVE NO 9/1 CTS NO 218, PLOT NO. 6,7,8. GharKundli lists all 70 MahaRERA projects in P.C.N.T. (411044).

How many flats are in Town NTLF Ista?

According to GharKundli's check of MahaRERA records (updated November 2026), Town NTLF Ista has 17 homes in 1 tower registered on MahaRERA.

When was Town NTLF Ista registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Town NTLF Ista was registered on MahaRERA on 16 August 2017. GharKundli did not find a title report on the land on file there.

Does Town NTLF Ista have any legal issues or court cases?

No court cases are listed for Town NTLF Ista on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Town NTLF Ista?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is NEW TOWN LEASING AND FINANCE PVT LTD.