by KAILASH BHAGWANDAS DUSEJA · Near Shastri Park, Pune 411017

What’s in the report? →

Possession date of Dwarka Homes (MahaRERA P52100002266): 31 December 2019, moved from 31 December 2018 (12 months later), and it has already passed. It has 17 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100002266. Status: Lapsed (registration period ended).

Source: MahaRERA website — records for P52100002266, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (December 2019) has passed.

What do you want to know about Dwarka Homes?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Dwarka Homes has moved

  1. 31 December 2018

    Completion date given when the project was registered

  2. 31 December 2019

    Extended at the builder's request (MahaRERA application EXT52100001689)

    Reason the builder gave MahaRERA: “That while uploading the completion date of project by mistakenly due to typing mistake it was uploaded 31/12/2018 but the actual date of completion is 31/12/2019.”

Source: Dwarka Homes’s extension records on MahaRERA (P52100002266), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Dwarka Homes

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2019 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100002266
Status
Lapsed (registration period ended)
Builder
KAILASH BHAGWANDAS DUSEJA
Location
Near Shastri Park, Pune · 411017
Project type
Residential / Group Housing
Registered on
31 Jul 2017
Completion date at registration
December 2018
Latest completion date
December 2019
Delay so far
12 months
Homes
17
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Dwarka Homes, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
DWARKA HOMES100%100%80%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Dwarka Homes every 1–2 months.

Dwarka Homes: buildings, flats and land, as filed on MahaRERA

  • Buildings: DWARKA HOMES (7 floors)
  • Land: 267 sq m (about 0.1 acres) · sanctioned built-up 511 sq m
  • Land, as filed: 858 TO 861/1
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Dwarka Homes →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Dwarka Homes: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Dwarka Homes

What is the possession date of Dwarka Homes?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Dwarka Homes in Near Shastri Park, Pune is 31 December 2019 — 12 months later than 31 December 2018, the date given at registration. That date has already passed.

The date has already moved 12 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Dwarka Homes?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Dwarka Homes's builder has filed on MahaRERA, the official one, is 31 December 2019, already 12 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Dwarka Homes extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Dwarka Homes's builder applied to MahaRERA to extend the completion date once: to 31 December 2019, giving the reason "That while uploading the completion date of project by mistakenly due to typing mistake it was uploaded 31/12/2018 but the actual date of completion is 31/12/2019.".

What is the RERA number of Dwarka Homes?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Dwarka Homes in Near Shastri Park, Pune is P52100002266.

Is Dwarka Homes registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Dwarka Homes is registered as P52100002266 and its status is "Lapsed (registration period ended)".

What is the current construction status of Dwarka Homes? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Dwarka Homes's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on DWARKA HOMES is 100% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.

Does Dwarka Homes have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Dwarka Homes safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Dwarka Homes is registered on MahaRERA as P52100002266, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Dwarka Homes?

Dwarka Homes isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Dwarka Homes?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Dwarka Homes: gharkundli.com/tools/property-cost-calculator

Has Dwarka Homes received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Dwarka Homes isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 December 2019 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Dwarka Homes?

According to GharKundli's check of MahaRERA records (updated November 2026), Dwarka Homes's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 December 2019) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Has Dwarka Homes uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Dwarka Homes was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Dwarka Homes's possession date changes?

The latest dates are on Dwarka Homes's MahaRERA page (P52100002266). GharKundli's Kundli Watch sends a free WhatsApp update on Dwarka Homes every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Dwarka Homes have?

According to GharKundli's check of MahaRERA records (updated November 2026), Dwarka Homes has one building filed: DWARKA HOMES with 7 floors.

How big is the land of Dwarka Homes?

According to GharKundli's check of MahaRERA records (updated November 2026), Dwarka Homes stands on 267 sq m of land (about 0.1 acres), with 511 sq m of sanctioned built-up area.

What are the reviews of Dwarka Homes?

Google Maps has reviews of Dwarka Homes written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Dwarka Homes?

Dwarka Homes by KAILASH BHAGWANDAS DUSEJA is in Near Shastri Park, Pune, pincode 411017, Maharashtra, and is registered on MahaRERA as P52100002266, per GharKundli's check of MahaRERA records. Its land is filed as 858 TO 861/1. GharKundli lists all 161 MahaRERA projects in Rahatani (411017).

How many flats are in Dwarka Homes?

According to GharKundli's check of MahaRERA records (updated November 2026), Dwarka Homes has 17 homes in 1 tower registered on MahaRERA.

When was Dwarka Homes registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Dwarka Homes was registered on MahaRERA on 31 July 2017. GharKundli did not find a title report on the land on file there.

Does Dwarka Homes have any legal issues or court cases?

No court cases are listed for Dwarka Homes on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Dwarka Homes?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is KAILASH BHAGWANDAS DUSEJA.

Other projects in Haveli

All 161 projects in Rahatani (411017) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.