Lilium Phase II
by Amol Shirish Jakate · Jakate Mala, Pune
Possession date of Lilium Phase II: 30 April 2029, moved from 30 December 2022 (72 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100003808, and currently active. Its completion date has moved from December 2022 to April 2029: 72 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Lilium Phase II?
How the possession date of Lilium Phase II has moved
30 December 2022
Completion date given when the project was registered
31 December 2028
Extended at the builder's request (MahaRERA application EXT52100013273)
Reason the builder gave MahaRERA:
“To Maharashtra Real Estate Regulatory Authority 6th & 7th Floor, Housefin Bhavan, Plot No: C - 21, E - Block, Bandra Kurla Complex, Bandra (E), Mumbai 400051 Dear Sirs I would like to apply for a revised date of completion and for the same…” Read the full reason
“To Maharashtra Real Estate Regulatory Authority 6th & 7th Floor, Housefin Bhavan, Plot No: C - 21, E - Block, Bandra Kurla Complex, Bandra (E), Mumbai 400051 Dear Sirs I would like to apply for a revised date of completion and for the same purpose I am submitting this request on the MahaRera portal. From the date of registration with MahaRera till today, I haven't entered into any registered agreement for sale or any other registered agreement with any person or entity for this project. Neither I have made further progress in construction work. The current date expires on 30/12/2022 and onl…”30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Lilium Phase II’s extension records on MahaRERA (P52100003808), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Lilium Phase II
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100003808
- Status
- Registered and active
- Builder
- Amol Shirish Jakate
- Location
- Jakate Mala, Pune · 412208
- Project type
- Residential / Group Housing
- Registered on
- 6 Aug 2017
- Completion date at registration
- December 2022
- Latest completion date
- April 2029
- Delay so far
- 72 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 54
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Lilium Phase II, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building B | 100% | 13% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Lilium Phase II every month.
Lilium Phase II: buildings, flats and land, as filed on MahaRERA
- Buildings: Building B (9 floors)
- Land: 1,586 sq m (about 0.4 acres) · sanctioned built-up 6,571 sq m · recreational space 825 sq m
- Boundaries filed include: Road and Gut Number 58
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Lilium Phase II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Lilium Phase II: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Lilium Phase II
What is the possession date of Lilium Phase II?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Lilium Phase II in Jakate Mala, Pune is 30 April 2029 — 72 months later than 30 December 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Lilium Phase II?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Lilium Phase II's builder has filed on MahaRERA, the official one, is 30 April 2029, already 72 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Lilium Phase II extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Lilium Phase II's builder applied to MahaRERA to extend the completion date once: to 31 December 2028, giving the reason "To Maharashtra Real Estate Regulatory Authority 6th & 7th Floor, Housefin Bhavan, Plot No: C - 21, E - Block, Bandra Kurla Complex, Bandra (E), Mumbai 400051 Dear Sirs I would like to apply for a revised date of completion and for the same purpose I am submitting this request on the MahaRera portal. From the date of registration with MahaRera till today, I haven't entered into any registered agreement for sale or any other registered agreement with any person or entity for this project. Neither I have made further progress in construction work. The current date expires on 30/12/2022 and onl…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Lilium Phase II?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Lilium Phase II in Jakate Mala, Pune is P52100003808.
Is Lilium Phase II registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Lilium Phase II is registered as P52100003808 and its status is "Registered and active".
What is the construction status of Lilium Phase II?
According to GharKundli's check of MahaRERA records (updated November 2026), Lilium Phase II's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Building B is 13% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Lilium Phase II have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Lilium Phase II safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Lilium Phase II is registered on MahaRERA as P52100003808, its completion date has moved 72 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Lilium Phase II's possession date changes?
The latest dates are on Lilium Phase II's MahaRERA page (P52100003808). GharKundli's Kundli Watch sends a free WhatsApp update on Lilium Phase II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Lilium Phase II have?
According to GharKundli's check of MahaRERA records (updated November 2026), Lilium Phase II has one building filed: Building B with 9 floors.
How big is the land of Lilium Phase II?
According to GharKundli's check of MahaRERA records (updated November 2026), Lilium Phase II stands on 1,586 sq m of land (about 0.4 acres), with 6,571 sq m of sanctioned built-up area and 825 sq m of recreational open space.
Where can I read reviews of Lilium Phase II?
Google Maps has reviews of Lilium Phase II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Lilium Phase II?
Lilium Phase II by Amol Shirish Jakate is in Jakate Mala, Pune (pincode 412208), Maharashtra, and is registered on MahaRERA as P52100003808, per GharKundli's check of MahaRERA records. Its boundaries filed there include Road and Gut Number 58.
How many homes are in Lilium Phase II?
According to GharKundli's check of MahaRERA records (updated November 2026), Lilium Phase II has 54 homes in 1 tower registered on MahaRERA.
When was Lilium Phase II registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Lilium Phase II was registered on MahaRERA on 6 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Lilium Phase II?
No court cases are listed for Lilium Phase II on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Lilium Phase II?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Amol Shirish Jakate.
Check it yourself on MahaRERA
- How to check the possession date of Lilium Phase II
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Pune →
Other projects in Shirur
- Shantivan Homes Phase 7
- Shantivan Homes Phase 6
- EKDANT PLAZA
- Rayat Regency
- Shantivan Homes Phase 8
- Shantivan Homes Phase 5
- KAMAL BAUG
- Aura Sai Krishnangan-Building B
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.