AAROH DWELLING
by SHANKAR VITHAL BELDARE AND OTHERS · Datta Nagar, Pune
Possession: AAROH DWELLING is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100007251. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about AAROH DWELLING?
How the possession date of AAROH DWELLING has moved
31 January 2019
Completion date given when the project was registered
30 April 2020
Extended at the builder's request (MahaRERA application EXT52100002297)
Reason the builder gave MahaRERA:
“work is 100% completed, applied for no objection certificate from the airport authority of India and national defense academy.. the same is yet to be received and then the same is required to be submitted to the Pune municipal corporation w…” Read the full reason
“work is 100% completed, applied for no objection certificate from the airport authority of India and national defense academy.. the same is yet to be received and then the same is required to be submitted to the Pune municipal corporation who will subsequently issue a completion certificate.. part completion certificate is already submitted to maharera.”30 April 2021
Extended at the builder's request (MahaRERA application EXT52100008415)
Reason the builder gave MahaRERA:
“Our project work is 100% completed. Developer has applied for No objection certificate (NOC) from the Airport Authority of India and National Defense Academy, the same is yet to be received and then the same is required to be submitted to t…” Read the full reason
“Our project work is 100% completed. Developer has applied for No objection certificate (NOC) from the Airport Authority of India and National Defense Academy, the same is yet to be received and then the same is required to be submitted to the Pune Municipal Corporation (PMC) who will subsequently issue a Completion Certificate. But due to COVID'19 there has been delay in issuing noc/completion from respective authorities (Part completion certificate for Ground & 1st Floor is already received & submitted to Maharera). Kindly requesting for further extension for next 06 months ie 30/04/2021 (…”31 July 2021
Extended at the builder's request (MahaRERA application EXT52100009485)
Reason the builder gave MahaRERA:
“Respected Sir/Madam, Our Project Aaroh Dwelling, DattanagarChowk, Ambegaon BK, Pune 411046 work is 100% completed, applied for No objection certificate from the Airport Authority of India and National Defense Academy, the same is yet to be…” Read the full reason
“Respected Sir/Madam, Our Project Aaroh Dwelling, DattanagarChowk, Ambegaon BK, Pune 411046 work is 100% completed, applied for No objection certificate from the Airport Authority of India and National Defense Academy, the same is yet to be received and then the same is required to be submitted to the Pune Municipal Corporation (PMC) who will subsequently issue a completion certificate. Part completion certificate is already submitted to Maharera. At same time due to expiry of RERA dated 30/04/2021, but due to Covid-19 lockdown which has been announce from 15th April 2021 to 30th April 2021…”31 March 2022
Extended at the builder's request (MahaRERA application EXT52100010459)
Reason the builder gave MahaRERA:
“Respected Sir / Madam We have received MOD NOC (Ministry of Defense) & now MOD NOC is been submitted to Pune Municipal Corporation for completion, but due to COVID-19 the government offices are operating at were minimal man power & also the…” Read the full reason
“Respected Sir / Madam We have received MOD NOC (Ministry of Defense) & now MOD NOC is been submitted to Pune Municipal Corporation for completion, but due to COVID-19 the government offices are operating at were minimal man power & also the concern authority has been transferred 10 days back, so now we awaiting the other authority to take the charge & then will visit, so therefore there is a delay in issuing Completion Certificate. Kindly find attach Architect certificate of work completion for your reference. CA Certificate with all payment details is been attach & Booked customers list 31…”31 October 2022
Extended at the builder's request (MahaRERA application EXT52100011983)
Reason the builder gave MahaRERA:
“Project work is 100% completed, latest Architect & CA certificate attached herewith. We have submitted the file for Occupation Certificate with Pune Municipal Corporation and which is in process & awaited from PMC. Reason for delay is water…” Read the full reason
“Project work is 100% completed, latest Architect & CA certificate attached herewith. We have submitted the file for Occupation Certificate with Pune Municipal Corporation and which is in process & awaited from PMC. Reason for delay is water NOC is allotted for Ground & First floor, but we waiting for entire 8 floors for which is in process with concern department. Once the NOC received the PMC will issue the Occupation Certificate. Kindly allows us further extension till 31/10/2022 for completion of subjected project.”
Source: AAROH DWELLING’s extension records on MahaRERA (P52100007251), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on AAROH DWELLING
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100007251
- Status
- Completed
- Builder
- SHANKAR VITHAL BELDARE AND OTHERS
- Location
- Datta Nagar, Pune · 411046
- Project type
- Others
- Registered on
- 17 Aug 2017
- Completion date at registration
- January 2019
- Latest completion date
- October 2022
- Delay so far
- 45 months
- Homes
- 111
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of AAROH DWELLING, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| AAROH DWELLING | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on AAROH DWELLING every month.
AAROH DWELLING: buildings, flats and land, as filed on MahaRERA
- Buildings: AAROH DWELLING (11 floors)
- Land: 6,000 sq m (about 1.5 acres) · sanctioned built-up 5,523 sq m · recreational space 476 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of AAROH DWELLING →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
AAROH DWELLING: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about AAROH DWELLING
What is the possession date of AAROH DWELLING?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for AAROH DWELLING in Datta Nagar, Pune is 31 October 2022 — 45 months later than 31 January 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for AAROH DWELLING?
Builders and listing sites often quote an earlier "target" date for handover. The completion date AAROH DWELLING's builder has filed on MahaRERA, the official one, is 31 October 2022, already 45 months later than the 31 January 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of AAROH DWELLING extended?
According to GharKundli's check of MahaRERA records (updated November 2026), AAROH DWELLING's builder applied to MahaRERA to extend the completion date 5 times: to 30 April 2020, giving the reason "work is 100% completed, applied for no objection certificate from the airport authority of India and national defense academy.. the same is yet to be received and then the same is required to be submitted to the Pune municipal corporation who will subsequently issue a completion certificate.. part completion certificate is already submitted to maharera."; to 30 April 2021, giving the reason "Our project work is 100% completed. Developer has applied for No objection certificate (NOC) from the Airport Authority of India and National Defense Academy, the same is yet to be received and then the same is required to be submitted to the Pune Municipal Corporation (PMC) who will subsequently issue a Completion Certificate. But due to COVID'19 there has been delay in issuing noc/completion from respective authorities (Part completion certificate for Ground & 1st Floor is already received & submitted to Maharera). Kindly requesting for further extension for next 06 months ie 30/04/2021 (…"; to 31 July 2021, giving the reason "Respected Sir/Madam, Our Project Aaroh Dwelling, DattanagarChowk, Ambegaon BK, Pune 411046 work is 100% completed, applied for No objection certificate from the Airport Authority of India and National Defense Academy, the same is yet to be received and then the same is required to be submitted to the Pune Municipal Corporation (PMC) who will subsequently issue a completion certificate. Part completion certificate is already submitted to Maharera. At same time due to expiry of RERA dated 30/04/2021, but due to Covid-19 lockdown which has been announce from 15th April 2021 to 30th April 2021…"; to 31 March 2022, giving the reason "Respected Sir / Madam We have received MOD NOC (Ministry of Defense) & now MOD NOC is been submitted to Pune Municipal Corporation for completion, but due to COVID-19 the government offices are operating at were minimal man power & also the concern authority has been transferred 10 days back, so now we awaiting the other authority to take the charge & then will visit, so therefore there is a delay in issuing Completion Certificate. Kindly find attach Architect certificate of work completion for your reference. CA Certificate with all payment details is been attach & Booked customers list 31…"; to 31 October 2022, giving the reason "Project work is 100% completed, latest Architect & CA certificate attached herewith. We have submitted the file for Occupation Certificate with Pune Municipal Corporation and which is in process & awaited from PMC. Reason for delay is water NOC is allotted for Ground & First floor, but we waiting for entire 8 floors for which is in process with concern department. Once the NOC received the PMC will issue the Occupation Certificate. Kindly allows us further extension till 31/10/2022 for completion of subjected project.".
What is the RERA number of AAROH DWELLING?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of AAROH DWELLING in Datta Nagar, Pune is P52100007251.
Is AAROH DWELLING registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), AAROH DWELLING is registered as P52100007251 and its status is "Completed".
What is the construction status of AAROH DWELLING?
According to GharKundli's check of MahaRERA records (updated November 2026), AAROH DWELLING's status on MahaRERA is "Completed". As filed by the builder, slab work on AAROH DWELLING is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does AAROH DWELLING have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is AAROH DWELLING safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), AAROH DWELLING is registered on MahaRERA as P52100007251, its MahaRERA status is "Completed", its completion date has moved 45 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if AAROH DWELLING's possession date changes?
The latest dates are on AAROH DWELLING's MahaRERA page (P52100007251). GharKundli's Kundli Watch sends a free WhatsApp update on AAROH DWELLING every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does AAROH DWELLING have?
According to GharKundli's check of MahaRERA records (updated November 2026), AAROH DWELLING has one building filed: AAROH DWELLING with 11 floors.
How big is the land of AAROH DWELLING?
According to GharKundli's check of MahaRERA records (updated November 2026), AAROH DWELLING stands on 6,000 sq m of land (about 1.5 acres), with 5,523 sq m of sanctioned built-up area and 476 sq m of recreational open space.
Where can I read reviews of AAROH DWELLING?
Google Maps has reviews of AAROH DWELLING written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is AAROH DWELLING?
AAROH DWELLING by SHANKAR VITHAL BELDARE AND OTHERS is in Datta Nagar, Pune (pincode 411046), Maharashtra, and is registered on MahaRERA as P52100007251, per GharKundli's check of MahaRERA records.
How many homes are in AAROH DWELLING?
According to GharKundli's check of MahaRERA records (updated November 2026), AAROH DWELLING has 111 homes in 1 tower registered on MahaRERA.
When was AAROH DWELLING registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), AAROH DWELLING was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on AAROH DWELLING?
No court cases are listed for AAROH DWELLING on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of AAROH DWELLING?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SHANKAR VITHAL BELDARE AND OTHERS.
Check it yourself on MahaRERA
- How to check the possession date of AAROH DWELLING
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Datta Nagar
All 229 projects in Katraj (411046) →Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.