VRUNDAAVAN HEIGHTS

by KRUSHNAI DEVELOPERS · Saswad, Pune

Possession date of VRUNDAAVAN HEIGHTS: 7 May 2025, moved from 30 March 2023 (26 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52100013279. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (May 2025) has passed.

What do you want to know about VRUNDAAVAN HEIGHTS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of VRUNDAAVAN HEIGHTS has moved

  1. 30 March 2023

    Completion date given when the project was registered

  2. 7 May 2025

    Extended at the builder's request (MahaRERA application EXT52100011904)

    Reason the builder gave MahaRERA: “DUE TO CORONA PANDEMIC. WORKERS AND LABOUR PROBLEMS DELAY FOR PROJECT. LESS BOOKING AND BOOKING CANCELLATIONS DUE TO CORONA AFFET CONSTRCTION SPEED.”

Source: VRUNDAAVAN HEIGHTS’s extension records on MahaRERA (P52100013279), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on VRUNDAAVAN HEIGHTS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the May 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100013279
Status
Lapsed (registration period ended)
Builder
KRUSHNAI DEVELOPERS
Location
Saswad, Pune · 412301
Project type
Residential / Group Housing
Registered on
21 Sep 2017
Completion date at registration
March 2023
Latest completion date
May 2025
Delay so far
26 months
Homes
48
Sold or booked
71%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of VRUNDAAVAN HEIGHTS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
VRUNDAAVAN HEIGHTS100%70%70%25%

Commencement certificate (CC), as filed on MahaRERA

  • VRUNDAAVAN HEIGHTS: covers 6 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on VRUNDAAVAN HEIGHTS every month.

VRUNDAAVAN HEIGHTS: buildings, flats and land, as filed on MahaRERA

  • Buildings: VRUNDAAVAN HEIGHTS (6 floors, 58 units)
  • Land: 3,602 sq m (about 0.9 acres) · sanctioned built-up 3,604 sq m · recreational space 308 sq m
  • Boundaries filed include: SONORI ROAD
  • Map: the location the builder filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of VRUNDAAVAN HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

VRUNDAAVAN HEIGHTS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about VRUNDAAVAN HEIGHTS

What is the possession date of VRUNDAAVAN HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for VRUNDAAVAN HEIGHTS in Saswad, Pune is 7 May 2025 — 26 months later than 30 March 2023, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for VRUNDAAVAN HEIGHTS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date VRUNDAAVAN HEIGHTS's builder has filed on MahaRERA, the official one, is 7 May 2025, already 26 months later than the 30 March 2023 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of VRUNDAAVAN HEIGHTS extended?

According to GharKundli's check of MahaRERA records (updated November 2026), VRUNDAAVAN HEIGHTS's builder applied to MahaRERA to extend the completion date once: to 7 May 2025, giving the reason "DUE TO CORONA PANDEMIC. WORKERS AND LABOUR PROBLEMS DELAY FOR PROJECT. LESS BOOKING AND BOOKING CANCELLATIONS DUE TO CORONA AFFET CONSTRCTION SPEED.".

What is the RERA number of VRUNDAAVAN HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of VRUNDAAVAN HEIGHTS in Saswad, Pune is P52100013279.

Is VRUNDAAVAN HEIGHTS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), VRUNDAAVAN HEIGHTS is registered as P52100013279 and its status is "Lapsed (registration period ended)".

What is the construction status of VRUNDAAVAN HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), VRUNDAAVAN HEIGHTS's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on VRUNDAAVAN HEIGHTS is 70% done and internal work 70%. GharKundli's full report compares construction progress with the deadline.

Does VRUNDAAVAN HEIGHTS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is VRUNDAAVAN HEIGHTS safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), VRUNDAAVAN HEIGHTS is registered on MahaRERA as P52100013279, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 26 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if VRUNDAAVAN HEIGHTS's possession date changes?

The latest dates are on VRUNDAAVAN HEIGHTS's MahaRERA page (P52100013279). GharKundli's Kundli Watch sends a free WhatsApp update on VRUNDAAVAN HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does VRUNDAAVAN HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated November 2026), VRUNDAAVAN HEIGHTS has one building filed: VRUNDAAVAN HEIGHTS with 6 floors and 58 units.

How big is the land of VRUNDAAVAN HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), VRUNDAAVAN HEIGHTS stands on 3,602 sq m of land (about 0.9 acres), with 3,604 sq m of sanctioned built-up area and 308 sq m of recreational open space.

Where can I read reviews of VRUNDAAVAN HEIGHTS?

Google Maps has reviews of VRUNDAAVAN HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is VRUNDAAVAN HEIGHTS?

VRUNDAAVAN HEIGHTS by KRUSHNAI DEVELOPERS is in Saswad, Pune (pincode 412301), Maharashtra, and is registered on MahaRERA as P52100013279, per GharKundli's check of MahaRERA records. Its boundaries filed there include SONORI ROAD.

How many homes are in VRUNDAAVAN HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), VRUNDAAVAN HEIGHTS has 48 homes in 1 tower registered on MahaRERA, and 71% of them are sold or booked.

When was VRUNDAAVAN HEIGHTS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), VRUNDAAVAN HEIGHTS was registered on MahaRERA on 21 September 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on VRUNDAAVAN HEIGHTS?

No court cases are listed for VRUNDAAVAN HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of VRUNDAAVAN HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is KRUSHNAI DEVELOPERS, which has 1 other project registered on MahaRERA.

Other projects in pincode 412301

All 54 projects in Saswad (412301) →

Other projects by KRUSHNAI DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.