Nirmiti Saiban
by Nirmiti Promoters and Builders · B. J. Corner, Pune 412210Registered on MahaRERA as “SAIBAN”
What’s in the report? →Possession date of Nirmiti Saiban (MahaRERA P52100013318): 30 October 2020, moved from 30 October 2018 (24 months later), and it has already passed. It has 25 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100013318. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P52100013318, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (October 2020) has passed.
What do you want to know about Nirmiti Saiban?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Nirmiti Saiban has moved
30 October 2018
Completion date given when the project was registered
30 April 2020
Extended at the builder's request (MahaRERA application EXT52100002579)
Reason the builder gave MahaRERA:
“Due to drought in Maharashtra region at the relevant time the project could not be completed in stipulated time period. The work of project is 100 % completed now. But application for extension was not made till today due to some health pro…” Read the full reason
“Due to drought in Maharashtra region at the relevant time the project could not be completed in stipulated time period. The work of project is 100 % completed now. But application for extension was not made till today due to some health problems of Promoters. Hence this application for extension is made to comply provisions of Rera Act, such as to form legal entity/ society of the flat owners and to obtain completion certificate from competent Authority and to upload said certificates and Form 4 on Rera Website. The delay to make application for extension may be condoned and extension for p…”30 October 2020
Revised completion date on MahaRERA
Source: Nirmiti Saiban’s extension records on MahaRERA (P52100013318), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Nirmiti Saiban
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2020 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100013318
- Status
- Lapsed (registration period ended)
- Builder
- Nirmiti Promoters and Builders
- Location
- B. J. Corner, Pune · 412210
- Project type
- Residential / Group Housing
- Registered on
- 22 Sep 2017
- Completion date at registration
- October 2018
- Latest completion date
- October 2020
- Delay so far
- 24 months
- Homes
- 25
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Nirmiti Saiban, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SAIBAN -B | 100% | 100% | 100% | 100% |
| SAIBAN-C | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Nirmiti Saiban every 1–2 months.
Nirmiti Saiban: buildings, flats and land, as filed on MahaRERA
- Buildings: SAIBAN -B (5 floors) · SAIBAN-C (5 floors)
- Land: 1,517 sq m (about 0.4 acres) · sanctioned built-up 1,820 sq m
- Land, as filed: Gat No 941 plus 942 Plot No 8 to 12
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Nirmiti Saiban →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Nirmiti Saiban: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Nirmiti Saiban
What is the possession date of Nirmiti Saiban?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Nirmiti Saiban in B. J. Corner, Pune is 30 October 2020 — 24 months later than 30 October 2018, the date given at registration. That date has already passed.
The date has already moved 24 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Nirmiti Saiban?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Nirmiti Saiban's builder has filed on MahaRERA, the official one, is 30 October 2020, already 24 months later than the 30 October 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Nirmiti Saiban extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Nirmiti Saiban's builder applied to MahaRERA to extend the completion date once: to 30 April 2020, giving the reason "Due to drought in Maharashtra region at the relevant time the project could not be completed in stipulated time period. The work of project is 100 % completed now. But application for extension was not made till today due to some health problems of Promoters. Hence this application for extension is made to comply provisions of Rera Act, such as to form legal entity/ society of the flat owners and to obtain completion certificate from competent Authority and to upload said certificates and Form 4 on Rera Website. The delay to make application for extension may be condoned and extension for p…".
What is the RERA number of Nirmiti Saiban?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Nirmiti Saiban in B. J. Corner, Pune is P52100013318.
Is Nirmiti Saiban registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Nirmiti Saiban is registered as P52100013318 and its status is "Lapsed (registration period ended)".
What is the current construction status of Nirmiti Saiban? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Nirmiti Saiban's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Nirmiti Saiban have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Nirmiti Saiban safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Nirmiti Saiban is registered on MahaRERA as P52100013318, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Nirmiti Saiban?
Nirmiti Saiban isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Nirmiti Saiban?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Nirmiti Saiban: gharkundli.com/tools/property-cost-calculator
Has Nirmiti Saiban received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Nirmiti Saiban isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 October 2020 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Nirmiti Saiban?
According to GharKundli's check of MahaRERA records (updated November 2026), Nirmiti Saiban's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 October 2020) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Nirmiti Saiban uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Nirmiti Saiban was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Nirmiti Saiban's possession date changes?
The latest dates are on Nirmiti Saiban's MahaRERA page (P52100013318). GharKundli's Kundli Watch sends a free WhatsApp update on Nirmiti Saiban every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Nirmiti Saiban have?
According to GharKundli's check of MahaRERA records (updated November 2026), Nirmiti Saiban has 2 buildings filed: SAIBAN -B with 5 floors; SAIBAN-C with 5 floors.
How big is the land of Nirmiti Saiban?
According to GharKundli's check of MahaRERA records (updated November 2026), Nirmiti Saiban stands on 1,517 sq m of land (about 0.4 acres), with 1,820 sq m of sanctioned built-up area.
What are the reviews of Nirmiti Saiban?
Google Maps has reviews of Nirmiti Saiban written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Nirmiti Saiban?
Nirmiti Saiban by Nirmiti Promoters and Builders is in B. J. Corner, Pune, pincode 412210, Maharashtra, and is registered on MahaRERA as P52100013318, per GharKundli's check of MahaRERA records. Its land is filed as Gat No 941 plus 942 Plot No 8 to 12. GharKundli lists all 85 MahaRERA projects in Shirur (412210).
How many flats are in Nirmiti Saiban?
According to GharKundli's check of MahaRERA records (updated November 2026), Nirmiti Saiban has 25 homes in 2 towers registered on MahaRERA.
When was Nirmiti Saiban registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Nirmiti Saiban was registered on MahaRERA on 22 September 2017. GharKundli did not find a title report on the land on file there.
Does Nirmiti Saiban have any legal issues or court cases?
No court cases are listed for Nirmiti Saiban on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Nirmiti Saiban?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Nirmiti Promoters and Builders.
Check it yourself on MahaRERA
- How to check the possession date of Nirmiti Saiban
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Shirur
- Shantivan Homes Phase 6
- Shantivan Homes Phase 7
- Ekdant Plaza
- Rayat Regency
- Shantivan Homes Phase 8
- Shantivan Homes Phase 5
- Kamal Baug
- Aura Sai Krishnangan-Building B
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.