Maitreya Residency
by MAITREYA CONSTRUCTION AND DEVELOPERS · Bhosari, Pune 411039
What’s in the report? →Possession date of Maitreya Residency (MahaRERA P52100014460): 2 November 2022, moved from 3 May 2021 (18 months later), and it has already passed. It has 13 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100014460. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P52100014460, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (November 2022) has passed.
What do you want to know about Maitreya Residency?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Maitreya Residency has moved
3 May 2021
Completion date given when the project was registered
2 May 2022
Extended at the builder's request (MahaRERA application EXT52100009700)
Reason the builder gave MahaRERA: “due to medical emergency of the partner and due to pandemic situation our project work is delayed and we need extension to complete the project.”
2 November 2022
Revised completion date on MahaRERA
Source: Maitreya Residency’s extension records on MahaRERA (P52100014460), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Maitreya Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the November 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100014460
- Status
- Lapsed (registration period ended)
- Builder
- MAITREYA CONSTRUCTION AND DEVELOPERS
- Location
- Bhosari, Pune · 411039
- Project type
- Residential / Group Housing
- Registered on
- 4 Dec 2017
- Completion date at registration
- May 2021
- Latest completion date
- November 2022
- Delay so far
- 18 months
- Homes
- 13
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Maitreya Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A- BUILDING | 100% | 20% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Maitreya Residency every 1–2 months.
Maitreya Residency: buildings, flats and land, as filed on MahaRERA
- Buildings: A- BUILDING (6 floors)
- Land: 232 sq m (about 0.1 acres) · sanctioned built-up 464 sq m
- Land, as filed: CTS NO 949
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Maitreya Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Maitreya Residency: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Maitreya Residency
What is the possession date of Maitreya Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Maitreya Residency in Bhosari, Pune is 2 November 2022 — 18 months later than 3 May 2021, the date given at registration. That date has already passed.
The date has already moved 18 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Maitreya Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Maitreya Residency's builder has filed on MahaRERA, the official one, is 2 November 2022, already 18 months later than the 3 May 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Maitreya Residency extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Maitreya Residency's builder applied to MahaRERA to extend the completion date once: to 2 May 2022, giving the reason "due to medical emergency of the partner and due to pandemic situation our project work is delayed and we need extension to complete the project.".
What is the RERA number of Maitreya Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Maitreya Residency in Bhosari, Pune is P52100014460.
Is Maitreya Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Maitreya Residency is registered as P52100014460 and its status is "Lapsed (registration period ended)".
What is the current construction status of Maitreya Residency? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Maitreya Residency's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on A- BUILDING is 20% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Maitreya Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Maitreya Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Maitreya Residency is registered on MahaRERA as P52100014460, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 18 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Maitreya Residency?
Maitreya Residency isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Maitreya Residency?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Maitreya Residency: gharkundli.com/tools/property-cost-calculator
Has Maitreya Residency received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Maitreya Residency isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 2 November 2022 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Maitreya Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), Maitreya Residency's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (2 November 2022) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Maitreya Residency uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Maitreya Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Maitreya Residency's possession date changes?
The latest dates are on Maitreya Residency's MahaRERA page (P52100014460). GharKundli's Kundli Watch sends a free WhatsApp update on Maitreya Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Maitreya Residency have?
According to GharKundli's check of MahaRERA records (updated November 2026), Maitreya Residency has one building filed: A- BUILDING with 6 floors.
How big is the land of Maitreya Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), Maitreya Residency stands on 232 sq m of land (about 0.1 acres), with 464 sq m of sanctioned built-up area.
What are the reviews of Maitreya Residency?
Google Maps has reviews of Maitreya Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Maitreya Residency?
Maitreya Residency by MAITREYA CONSTRUCTION AND DEVELOPERS is in Bhosari, Pune, pincode 411039, Maharashtra, and is registered on MahaRERA as P52100014460, per GharKundli's check of MahaRERA records. Its land is filed as CTS NO 949. GharKundli lists all 60 MahaRERA projects in Bhosari (411039).
How many flats are in Maitreya Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), Maitreya Residency has 13 homes in 1 tower registered on MahaRERA.
When was Maitreya Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Maitreya Residency was registered on MahaRERA on 4 December 2017. GharKundli did not find a title report on the land on file there.
Does Maitreya Residency have any legal issues or court cases?
No court cases are listed for Maitreya Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Maitreya Residency?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is MAITREYA CONSTRUCTION AND DEVELOPERS.
Check it yourself on MahaRERA
- How to check the possession date of Maitreya Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Bhosari (411039)
- Riya Casa
- Smrutigandha
- Aditi Avenue
- Martand
- Vision Exotica
- Gandharv Marigold RH 7 to 12
- Gandharv Marigold RH 19 to 24
- Gandharv Marigold RH 13 to 18
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.